Guessing as to your Construction Damages is Not the Best Approach
November 18, 2019 —
David Adelstein - Florida Construction Legal UpdatesArbitrarily guessing as to your construction damages is NOT the best approach. Sure, experts can be costly. No doubt about it. Having an expert versus guessing as to your construction damages caused by another party’s breach of contract is a no brainer. Engage an expert or, at a minimum, be in a position to competently testify as to your damages caused by another party’s breach of contract. Otherwise, the guessing is not going to get you very far as a concrete subcontractor found out in Patrick Concrete Constructors, Inc. v. Layne Christensen Co., 2018 WL 6528485 (W.D. New York 2018) where the subcontractor could not competently support its delay-related damages or change orders and, equally important, could not support that the damages were proximately caused by the general contractor’s breach of the subcontract.
In this case, the concrete subcontractor entered into a subcontract to perform concrete work for a public project. The project was delayed and the general contractor was required to pay liquidated damages to the owner. Not surprisingly, the subcontractor disputed liability for delays and sued the general contractor for all of its delay-related damages “in the form of labor and materials escalation, loss of productivity, procurement and impact costs, field and home office overhead, idle equipment, inability to take on other work, lost profits, and interest.” Patrick Concrete Constructors, 2018 WL at *1.
The general contractor moved for summary judgment as to the plaintiff’s delay-related damages – the subcontractor’s damages were nothing but guesses and the subcontractor could not prove the general contractor was the cause of the subcontractor’s damages.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Fannie-Freddie Propose Liquidity Rules for Mortgage Insurers
July 16, 2014 —
Clea Benson and Zachary Tracer – BloombergMs. Benson may be contacted at cbenson20@bloomberg.net; Mr. Tracer may be contacted at ztracer1@bloomberg.net
Private mortgage insurers looking to do business with Fannie Mae and Freddie Mac would have to hold minimum amounts of liquid assets under standards proposed by the companies and their regulator.
To back loans packaged into securities by the U.S.-owned mortgage-finance giants, insurers would have to hold liquid assets worth at least 5.6 percent of their risk exposure, and possibly more depending on the quality of the loans they cover, according to the proposal released today by the companies and the Federal Housing Finance Agency.
“Mortgage insurance counterparties must be able to fulfill their intended role of providing private capital, even in adverse market conditions,” FHFA Director Melvin L. Watt said in an e-mailed statement.
Ms. Benson may be contacted at cbenson20@bloomberg.net; Mr. Tracer may be contacted at ztracer1@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Clea Benson and Zachary Tracer, Bloomberg
Appetite for Deconstruction
July 02, 2024 —
Patrick Sisson - BloombergThe death of 206 College Avenue was slow and painstaking. Over several days in January 2022, dozens of bundled-up volunteers swarmed over the three-story property, a tired wooden boarding house built in the early 1900s in Ithaca, New York. Long used as rental apartments for Cornell University students, the 13-bedroom house was set to be demolished, along with several neighboring structures of the same vintage, to make room for a new multi-use complex. But while those buildings were quickly reduced to rubble by trackhoes, the house at 206 was deconstructed, piece by piece, so that its elements could be used again.
The Catherine Commons Deconstruction Project, an effort by Cornell’s Circular Construction Lab, was a large-scale pilot designed to show how building waste can be kept out of landfills. As volunteers pulled nails out of fir, oak, and walnut boards and hauled lumber off to be sorted and redistributed, a team of eight workers with heavy machinery began meticulously sawing, slicing and removing 8-by-18-foot panels of the old building. These were trucked off to a warehouse, where they’d be taken apart and recycled.
The labor that went into this process was substantially more than a typical demolition. But it avoided the societal penalties left behind at nearly every building and demo site across the US. The sheer volume of waste generated by knocking down, adding to or renovating buildings in the US is stunning: 600 million tons of construction demolition waste annually, according to the most recent EPA estimate from 2018. Roughly 75% gets ground up into aggregate and fill, and only a small share is recycled and reused, necessitating production of new material for the next project. For scale, municipal solid waste only accounts for 300 million tons every year.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick Sisson, Bloomberg
Renters ‘Sold Out’ by NYC Pensions Press Mayor on Housing
May 19, 2014 —
Martin Z. Braun – BloombergElevators break down, ceilings leak and security is lax at the Metro North apartments overlooking the East River in Harlem, says retired rehabilitation technician Bob Montesi, who’s lived there for more than three decades.
Even as deterioration accelerates at the 761-unit complex, which used to be in a state affordable-housing program, some tenants are facing rent increases of as much as 80 percent.
For Montesi, 74, who worked at a New York City-run hospital for 41 years, the changes are especially galling. One of the owners of the building is his pension fund.
Read the court decisionRead the full story...Reprinted courtesy of
Martin Z. Braun, BloombergMr. Braun may be contacted at
mbraun6@bloomberg.net
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 —
CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Let’s Get Surety Podcast – #126 Building the Future: AI, Construction and Law
December 31, 2024 —
Denis Serkin - Peckar & Abramson, P.C.Denis Serkin, partner in P&A’s New York and New Jersey offices, joins the latest episode of the NASBP podcast “
Let’s Get Surety” to delve into the transformative impact of AI on the construction industry and construction law.
In this insightful discussion, Denis explores how AI tools are already enhancing design and supply chains and shares his vision for AI’s eventual integration across every facet of the industry.
Read the court decisionRead the full story...Reprinted courtesy of
Denis Serkin, Peckar & Abramson, P.C.Mr. Serkin may be contacted at
dserkin@pecklaw.com
Top Developments March 2024
April 22, 2024 —
Complex Insurance Coverage ReporterCLAIMS-MADE COVERAGE
Zurich Am. Ins. Co. v. Syngenta Crop Prot. LLC, 2024 Del. LEXIS 68 (Del. Feb. 26, 2024)
Delaware Supreme Court concludes that a letter from a lawyer informing an insured of possible lawsuits without identifying potential plaintiffs or demanding payment is not a “claim for damages” within the meaning of claims-made CGL and umbrella liability policies. Citing case law from Delaware and other jurisdictions, it reasoned that, in the ordinary sense, a “claim for damages” (which the policies did not define) is “a demand or request for monetary relief by or on behalf of an identifiable claimant.” According to the court, the letter in question did not meet this definition because it did not identify any claimants “except in the vaguest terms” or request monetary relief on any claimant’s behalf, but rather communicated only a threat of future litigation. As a result, the letter was not a claim made before the policy periods at issue.
POLLUTION EXCLUSION
Wesco Ins. Co. v. Brad Ingram Constr., 2024 U.S. App. LEXIS 1488 (9th Cir. Jan. 23, 2024)
A divided Ninth Circuit panel, applying California law, holds that a pollution exclusion* in a CGL policy does not preclude a duty to defend an underlying suit alleging physical injury from exposure to “clouds of toxic dust” deposited in the environment by a wildfire and released during clean up efforts. Citing MacKinnon v. Truck Ins. Exch., 73 P.3d 1205 (Cal. 2003), the majority explained that determining whether a “pollution event” (i.e., “environmental pollution”) resulting in excluded injury has occurred involves consideration of “the character of the injurious substance” and whether the exposure resulted from a “mechanism specified in the policy.” It concluded that a potential for coverage (and, therefore, a defense obligation) existed because, although wildfire debris may be considered a “pollutant” in certain circumstances, the mechanism alleged in the underlying complaint – “expos[ure] . . . to clouds of toxic dust during the loading and unloading of [the underlying plaintiff’s] truck” – did not clearly constitute an “event commonly thought of as pollution.”
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Oregon Condo Owners Make Construction Defect Claim
January 13, 2014 —
CDJ STAFFResidents of two condominiums in Florence, Oregon have filed suits alleging that construction defects have led to water intrusion and damage. The two condominium projects were built by separate developers. Each association has brought its own lawsuit, according to an article in the Register-Guard.
The Bridgeport Landing condominium owners have sued CJ Cable LLC for $2.5 million. Cindy Cable said of lawsuit, “I’ve done everything I could do to get this resolved, and I still get sued.” She said that “the only way to get it corrected is with a lawsuit.”
Meanwhile, residents of the Stillwater Condominiums have sued Thomas Hornback Construction for $2.1 million. Hornback is reported to have denied the allegations made by the Stillwater owners, but says that any problems would be due to subcontractors or failure of the owners to maintain the buildings.
Read the court decisionRead the full story...Reprinted courtesy of