Connecticut District Court to Review Proposed Class Action in Defective Concrete Suit
July 13, 2017 —
Tiffany Casanova - Saxe Doernberger & Vita, P.C.Thousands of Connecticut homeowners have fallen victim to a defective concrete epidemic. Over the last thirty years, the foundation in many homes, particularly in the Northeast region of the state, was built with a concrete aggregate that contained the mineral pyrrhotite. When exposed to the elements, including water and air, pyrrhotite oxidizes, resulting in cracking and disintegration over time. For Connecticut homeowners, this has resulted in disaster, both financially and to the foundations of their homes.
Previously, many homeowners insurance policies provided coverage for a “collapse” caused by the “use of defective material . . . in construction, remodeling or renovation.” As the pyrrhotite epidemic became more prevalent, insurers altered the coverage afforded for a “collapse” in several ways that potentially minimized or eliminated coverage for these types of claims. Primarily, coverage for a “collapse” is now restricted to collapses that are “abrupt,” and coverage is excluded for buildings in danger of falling down or those that are still standing, even if evidence of cracking or settling is demonstrated. The insurers did not notify homeowners of the change. Thus, homeowners who renewed policies were not informed of a coverage reduction nor were they provided with a corresponding reduction in the amount of premium.
Read the court decisionRead the full story...Reprinted courtesy of
Tiffany Casanova, Saxe Doernberger & Vita, P.C.Ms. Casanova may be contacted at
tlc@sdvlaw.com
Contractors’ Right to Sue in Washington Requires Registration
July 03, 2022 —
John Leary - Gordon & Rees Construction Law BlogSummary:
In Washington, contractors must be properly registered in order to pursue a legal action against a customer for breach of contract. Dobson v. Archibald, a February 2022 decision by the Washington Court of Appeals, reinforced how the governing statute – RCW 18.27.080 – does not simply create an affirmative defense but establishes a mandatory pleading prerequisite.1
Discussion:
In 2018, Archibald hired Dobson to refinish his hardwood floors for $3,200. Dobson was not a registered contractor. She had been referred to Archibald by acquaintances who were familiar with her construction and home repair work, including improvements Dobson had made to her own home. Archibald paid Dobson a $700 deposit before Dobson began her work. At the completion of the floor repair project, Archibald was unhappy with the appearance of the floors and informed Dobson that he would not pay the remaining $2,500.
Read the court decisionRead the full story...Reprinted courtesy of
John Leary, Gordon & ReesMr. Leary may be contacted at
jleary@grsm.com
Indemnification Against Release/“Disposal” of Hazardous Materials
May 18, 2020 —
Brian S. Wood & Miranda R. Millerick - ConsensusDocsIt is very common, if not nearly an industry standard, for construction contracts and subcontracts to contain provisions addressing the discovery of unanticipated hazardous materials. Many of these provisions require a contractor or subcontractor to discontinue work where hazardous materials are discovered. An example of such a clause can be found in the American Institute of Architects (AIA) Document A201 (2017), Section 10.3.1, which states in part:
If the Contractor encounters a hazardous material or substance not addressed in the Contract Documents and if reasonable precautions will be inadequate to prevent foreseeable bodily injury or death to persons resulting from a material or substance, including but not limited to asbestos or polychlorinated biphenyl (PCB), encountered on the site by the Contractor, the Contractor shall, upon recognizing the condition, immediately stop Work in the affected area and notify the Owner and Architect of the condition.
A similar clause in ConsensusDocs does not require the contractor to stop work, but provides that the “Contractor shall not be obligated to commence or continue work until any Hazardous Material discovered at the Work site has been removed, rendered or determined to be harmless by the Owner as certified by an independent testing laboratory and approved by the appropriate government agency.”
Reprinted courtesy of
Brian S. Wood, Smith, Currie & Hancock LLP and
Miranda R. Millerick, Smith, Currie & Hancock LLP
Mr. Wood may be contacted at bswood@smithcurrie.com
Ms. Millerick may be contacted at mrmillerick@smithcurrie.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Contract Basics: Venue and Choice of Law
February 19, 2024 —
Christopher G. Hill - Construction Law MusingsPreviously in this on-again-off-again series of posts on construction contract basics, I discussed attorney fees provisions and indemnification. In this installment, the topic at hand is venue and choice of law.
As construction professionals (outside of us construction attorneys), you are likely to be focused on things like the scope of work in a construction contract, the price terms, payment, delays, change orders, and the like. However, the venue (where any lawsuit or arbitration will have to happen) and the choice of law (what state’s law applies) can be equally important. You need to know where you will have to enforce your rights under the contract and also what law will apply. Will you need to go to another state to enforce your rights? Even if not, will your local attorney have to learn the law of another jurisdiction? These are important questions when reading and negotiating your prime contract (if with the owner) or subcontract (if with the general contractor).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Forethought Is Key to Overcoming Construction Calamities
February 10, 2020 —
Mitch Cohen - Construction ExecutiveWithout warning, an under-construction structure in the southern United States suffered a catastrophic collapse. The tragedy resulted in the death of several people. As a result, engineering and construction post-collapse forensics experts engaged in an 18-month investigation.
Those involved in the design and build project included the general contractor hired by the owner, a prime engineer, a consulting peer-review engineer and a prime structural design firm supported by a sub-consulting structural engineer. Although significant cracking was noticed several weeks before the failure, no one sounded the alarm or deemed the cracking worthy of corrective action.
In their findings, forensic experts found the collapse resulted from the combined failure of the general contractor, engineers and even the owner, who all failed to shut down the work once the cracking reached unacceptable levels and/or take the appropriate actions needed to secure the public safety and mitigate the risk. This was even after the general contractor requested that the engineer-of-record and design manager assess the structure’s extreme cracking. Consequently, the choice to not seriously investigate the crack or seek an independent peer review to design a rectification plan contributed directly to the tragedy. This is typically referred to within the industry as a “negligent professional design error.”
Reprinted courtesy of
Mitch Cohen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Cohen may be contacted at
mitch.cohen@rtspecialty.com
Disjointed Proof of Loss Sufficient
June 11, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe court found that when considered as a whole, separately filed proofs of loss and estimates of damage were sufficient to meet the requirements of a flood policy. Young v. Imperial Fire & Cas. Ins. Co., 2014 U.S. Dist. LEXIS 51863 (April 15, 2014).
On August 29, 2012, plaintiffs' property sustained flood damage due to Hurricane Isaac. After Imperial's adjustor inspected the property, advance payments were made for $5000 under the building coverage and $5000 under the contents coverage.
On October 26, 2012, the plaintiffs' adjustor submitted a proof of loss for building damages, stating the amount of loss was $175,100, which was the policy limit minus the deductible. The insured wife signed the proof of loss. The actual case value, full cost of replacement or repair, and applicable depreciation were listed "undetermined."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Do Construction Contracts and Fraud Mix After All?
October 27, 2016 —
Christopher G. Hill – Construction Law MusingsOn several occasions here at Construction Law Musings, I’ve discussed the fact that, with a few exceptions, fraud claims and written construction contract based claims do not mix. One of the exceptions to the so called “economic loss rule” that would seem to preclude both fraud and contract claims in the same lawsuit is where fraud is used to induce the contract in the first place. This exception would only apply where an independent duty, wholly outside of the duties created by the contract, is properly plead and proven to the court. For the same reason, namely a separate duty outside of the contract, the Virginia Consumer Protection Act (“VCPA”) may allow for an exception that would allow a cause of action under this statute.
Up until recently, the courts of Virginia have used these exceptions sparingly. However, the recent Loudoun County, VA Circuit Court opinion in Interbuild, Inc. v. Sayers (opinion also found at Virginia Lawyers Weekly) may signal a broadening of these exceptions. In the Interbuild case, the Court considered a claim for fraud in the inducement and breach of the VCPA. The basic facts plead by the plaintiffs were that Interbuild induced them into the contract through statements that it had been an established business since 1981, the project did not require a building permit, it had obtained all necessary subcontractor prices and would provide full-time project supervision, the project would be completed within 16 weeks, 4000 PSI concrete would be used for the project and that the project would be located in the agreed-upon area depicted and that they reasonably relied on these representations in deciding to enter into the contract to build their recreational facility.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Court Grants Summary Judgment to Insurer in HVAC Defect Case
August 04, 2011 —
CDJ STAFFThe US District Court in Colorado has determined in the case of RK Mechanical, Inc. v. Travelers Property Casualty Company of America that Travelers did not breach its insurance contract when it refused to cover RK Mechanical.
RK Mechanical performed an HVAC installation for a residential project for which J.E. Dunn Rocky Mountain was the general contractor. As part of the work, RK “installed approximately one hundred seventy-one CPVC flanges, which were manufactured by Charlotte Pipe and Foundry Company.” Two of these flanges failed in June, 2009 leading to water damage. RK replaced the cracked flanges and engaged in water remediation. “Travelers paid Dunn and RK for the costs associated with the water damage associated with the Flange Failure.” The court notes that Travelers did not pay for the cracked flanges, however.
Subsequently, RK examined the remaining flanges, finding many cracked ones. These were replaced with new ones. Later, all the Charlotte flanges were replaced with ones from another manufacturer. RK applied for coverage.
All sides brought in their experts: “Microbac Laboratories, Inc. prepared a report on behalf of RK concluding that the Flange Failure was due, in part, to an assembly or workmanship defect in addition to manufacturing defects in the flanges. Higgins & Associates prepared a report on behalf of Travelers concluding that the flanges failed due to improper installation. Plastic Failure Labs prepared a report on behalf of the flange manufacturer concluding that the flanges failed due to improper installation by RK.”
At this point, Travelers denied coverage. RK sued alleging that the coverage for flange failure and water damage implicitly includes mitigation costs. The court rejected this claim, noting it would do so even if Travelers had paid for the replacement of the first two flanges. Nor did the court find that replacement of the faulty flanges is not "a covered cause of loss." RK also argued that as it was required to mitigate, Travelers was obligated to cover costs. However, the court found that “the mitigation costs expended by RK were not incurred in an effort to avoid damages from a potential breach of contract by Travelers.” The court additionally noted that despite RK’s claims, the Colorado courts have not found a common law duty to mitigate. Finally, the court found that the exclusions in the policy were not in violation of public policy.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of