Heads I Win, Tails You Lose. Court Finds Indemnity Provision Went Too Far
May 25, 2020 —
Garret Murai - California Construction Law BlogWe all love David and Goliath stories. The underdog winning against the far stronger (and dastardly) opponent. Think Rocky Balboa versus Ivan Drago, the Star Wars Rebellion versus the Galatic Empire, Indiana Jones versus a good chunk of the Third Reich. And now, we have Margaret Williams.
The Story of Margaret Williams and her LLC
The story, told in Long Beach Unified School District v. Margaret Williams, LLC, Case No. B290069 (December 9, 2019), is about Margaret Williams. Ms. Williams (we’ll just call her “Margaret” going forward because it just sounds better when telling a story) worked for nearly ten years full-time for the Long Beach Unified School District, toiling day in and day out doing construction management and environmental compliance work, including work involving the clean up of material at a school construction site contaminated with arsenic.
Although she worked full-time for the District for nearly ten years, she wasn’t an employee. Rather, she was a contractor. And, on top of it all, as a condition of working for the District, the District required that she form a company in order to contract with the District. According to Margaret, “In order to work with the District, I was directed . . . to form a corporation or partnership. This was the only way I could work for the District: I could not enter into a contract with the District as an individual.” So, in 2006, she formed a company, simply called Margaret Williams, LLC.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
What Every Project Participant Needs to Know About Delay Claims
August 05, 2024 —
Andrew G. Vicknair - The Dispute ResolverA “delay” on a construction project is defined as the stretching out of the time for completion of certain key milestone scopes of work which can impact the completion date of an entire project, due to some circumstances or events that were not reasonably anticipated when the project began. 2 Construction Law ¶ 6.01 (Matthew Bender, 2024). While delays can be caused by any number of events, the most common are defective plans and specifications; design changes; severe weather and other, similar unforeseeable events; unforeseen or differing site conditions; unavailability of materials or labor; labor inefficiencies or stoppages; contractor negligence; and owner influences, including construction changes or outright interference by the owner or its agents. If the project schedule is not recovered following a delay, then the project schedule will likely be extended, resulting in an increase in the contractor’s costs of performance. A contractor that has experienced a delay on a project can take certain actions to pursue recovery of any damages the contractor may have incurred. However, to do so it is important to understand the different types of delays and the methods for establishing the delays.
I. Types of Delays
Delays may be categorized as (1) critical versus non-critical delays, (2) excusable versus non-excusable delays, and (3) compensable versus non-compensable delays. A critical delay is a delay that affects the project completion date and delays the entire project. In essence, a critical delay is one that will extend the critical path of a project. A non-critical delay is a delay that has no effect on the project’s critical path. Courts have recognized that delays to work not on the critical path will generally not delay the completion of a project. G.M. Shupe, Inc. v U.S., 5 Cl. Ct. 662, 728 (1984). Such a non-critical delay may affect the completion of certain activities, but does not affect the completion date of the entire project. In order for a delay to provide the basis for a claim for additional time or money, the delay must impact critical path activities on the project schedule.
Read the court decisionRead the full story...Reprinted courtesy of
Andrew G. Vicknair, D'Arcy Vicknair, LLCMr. Vicknair may be contacted at
agv@darcyvicknair.com
One More Mechanic’s Lien Number- the Number 30
March 06, 2023 —
Christopher G. Hill - Construction Law MusingsI’ve spoken here often about the numbers
90 and 150 as they relate to
Virginia mechanic’s liens. These numbers are important for all mechanic’s liens in Virginia, whether commercial or residential (meaning liens for 1 and 2-family homes). There is another number, 30, that is important for those construction contractors that perform work on single and two-family homes. Where a mechanic’s lien agent is named on the building permit (or possibly just named if not stated on the permit), and
among other requirements,
Va. Code 43-4.01 requires that, in order to have lien rights at the project, the contractor must provide notice to the mechanic’s lien agent within 30 days of beginning work that it is performing work and shall seek payment for the work.
Further, the mechanic’s lien agent notice must contain the following:
(i) the name, mailing address, and telephone number of the person sending such notice, (ii) the person’s license or certificate number issued by the Board for Contractors pursuant to Chapter 11 (§ 54.1-1100 et seq.) of Title 54.1, if any, and the date such license or certificate was issued and the date such license or certificate expires, (iii) the building permit number on the building permit, (iv) a description of the property as shown on the building permit, and (v) a statement that the person filing such notice seeks payment for labor performed or material furnished.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Home Prices on the Rise
September 03, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to CoreLogic, in July, housing prices rose 6.9% compared to last year, reported Housing Wire. Furthermore, prices increased by 1.7% compared to June 2015.
“Home sales continued their brisk rebound in July and home prices reflected that, up 6.9% from a year ago,” Frank Nothaft, chief economist for CoreLogic, told Housing Wire. “Over the same period, the National Association of Realtors reported existing sales up 10% and the Census Bureau reported new home sales up 26% in July.”
Read the court decisionRead the full story...Reprinted courtesy of
Daily Construction Reports: Don’t Leave the Job Without Them
January 11, 2022 —
Patrick Barthet - Construction ExecutiveTrying to remember exactly what was done at a job site last week, last month or last quarter along with knowing who worked at the site is nearly impossible without a written, video or electronic record for reference. That’s why daily construction reports are so important.
Yet many contractors fail to create these reports. And those that do create them, may do it only at the beginning of a project or sporadically throughout the progress of a job, and generally only when they are reminded to do so. Daily reports only become truly effective when they are, in fact, done daily. Whether it is to help resolve a pending delay issue or clarify a job site access claim, or any number of other matters where what happened at the time is so critical, those daily construction reports should be completed daily.
Be Timely
The reason that daily reports are admissible in court (with corroborating testimony) is that they are interpreted as being recorded at or about the time the events in question occurred. Field managers should, therefore, write up these reports daily while the work is occurring or very soon thereafter to capture as accurate an account as possible. If these reports are not created until the end of the week or month, the information will not be as accurate and may not be as helpful in supporting a particular position.
Reprinted courtesy of
Patrick Barthet, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Barthet may be contacted at
pbarthet@barthet.com
Demanding a Reduction in Retainage
April 01, 2015 —
Craig Martin – Construction Contractor AdvisorOne of the attendees of the Goldleaf Surety presentation asked a great question about reducing retention under the Nebraska Construction Prompt Pay Act, Nebraska Revised Statutes, 45-1201-45-1211. He wanted to know whether there was any way to reduce and recover retainage during the project. The short answer is retainage should be reduced half way through the project, but there is no right to recover retainge for work performed during the first half of the project.
Retainage in Nebraska
Under section 45-1204 of the Prompt Pay Act, a contractor may withhold up to 10% retainage. A contract that allows for greater retainage is not enforceable.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Not Remotely Law as Usual: Don’t Settle for Delays – Settle at Remote Mediation
May 25, 2020 —
Victor J. Zarrilli, Robert G. Devine & Michael W. Horner - White and Williams LLPThe emergence and rapid spread of COVID-19 has created extraordinary circumstances that have significantly impacted how we go about living, working and interacting with one another. The practice of law is no exception.
While most cases have been postponed and some extended indefinitely, the issues and disputes that first triggered the litigation remain. In fact, the burdens created by social distancing and other responses to the COVID-19 outbreak have served to only increase these disputes and create an urgent need in some for quick resolution.
In our previous article, we summarized some of the best practices that should be applied when taking and defending depositions in a remote, virtual setting. That technology can also offer the same benefits for alternative dispute resolutions. If planned properly, the use of technology allows remote mediations to be conducted as seamlessly as in-person mediations and, in some circumstances, affords additional benefits that can achieve the best possible resolution for all sides.
This article summarizes the opportunities technology has created by which parties can attempt to resolve their disputes through alternative dispute resolution methods, even in a time of social distancing.
Reprinted courtesy of White and Williams LLP attorneys
Victor J. Zarrilli,
Robert G. Devine and
Michael W. Horner
Mr. Zarrilli may be contacted at zarrilliv@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Horner may be contacted at hornerm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Coffee Beans, Mars and the 50 States: Civil Code 1542 Waivers and Latent Defects
March 19, 2015 —
Garret Murai – California Construction Law BlogA few years ago, Pulitzer Prize-winning reporter Charles Duhigg wrote a book that was on the New York Times bestseller list for over 60 weeks,
The Power of Habit: Why We Do What We Do in Life and Business. As its title suggests, the book is about habits, but more importantly about how we can change our habits to make ourselves happier, healthier and more productive.
In his book, Duhigg talks about how habits are “encoded into the structures of our brain” and how this is an advantage because, as an example, “it would be awful if we had to relearn how to drive after every vacation.”
Duhigg’s driving example made me think about how much we assume as well, and how, from a practical perspective, it is almost essential that we do so. Using his car example, when we put our key into the ignition and turn it, we assume that the engine will start, and further assume that when we put our foot on the gas pedal that the car will move. If we didn’t or couldn’t assume this, and the many other things we assume in our daily lives, our brains would likely go into overload.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at