Revisiting the CMO; Are We Overusing the Mediation Privilege?
November 19, 2021 —
Michael T. Kennedy Jr. - BERDING|WEILOne of the most common features in construction defect cases is the Case Management Order (“CMO”) or Pre-Trial Order (“PTO”) to govern pre-trial and mediation procedures. CMOs and PTOs arose in the days when the HOA would sue the developer, the developer would cross-complaint against the subcontractors, and each defendant and cross-defendant might have 2 or 3 insurance carriers defending, each of whom may retain their own panel counsel. In a large case there may have been 20 parties and 30 defense attorneys. In order to avoid the cost and chaos of all of those parties propounding their own discovery, and in order to prepare these cases for mediation well before trial and the associated costs, it became standard practice in California to include provisions in the CMO to stay all discovery until just before trial.
Plaintiff would provide a Defect List or Statement of Claims and the parties experts would meet and exchange information as part of the mediation process. All of the information exchanged would be subject to mediation privileges and inadmissible at trial. The benefit of this practice was that the parties (and carriers) would avoid the cost of formal discovery and allow the experts to discuss compromised scopes of repair to help settle the case while being able to take a more aggressive position at trial. The disadvantages are that each party uses its privileged initial expert reports to stake out negotiating positions more extreme than what they would put on at trial, with each side losing credibility with the other in assessing the value of the case, and for those cases that did not settle, the parties would be faced with having to do all of the depositions and discovery in the last 60 days, or delaying trial, or both.
Over the last 10 or 15 years with the advent of wrap-up insurance policies, these cases now usually involve 2 sides instead of 20; only the HOA and the developer remain in the case. However, old habits die hard, and the standard CMO/PTO hasn’t evolved with other aspects of these cases. The practice of staying all discovery and exchanging information only under mediation privileges remains, and as a result insurance carriers don’t receive the admissible evidence that they need to determine coverage and evaluate the real settlement value of the case until just before trial. On the plaintiff’s side, if most of the experts’ work is done under the guise of mediation privilege, those costs may not be recoverable. Outside the context of mediation, costs incurred in investigation of the defects and preparation of a scope and cost of repair are recoverable.
This reflexive claim of mediation privilege over all information exchanged during the case has outlived its usefulness. The CMO can and should remain to regulate formal discovery and to help the parties prepare for mediation, but regulated discovery should be opened early in the case. In California, the SB800 process already provides for the exchange of admissible information during the prelitigation right to repair process. Continuing that exchange during the early litigation allows the parties to continue to prepare for mediation, but waiving privileges had advantages for both sides.
A senior claims manager once commented that Plaintiff’s mediation-protected Statement of Claims “might as well be a stack of blank paper” for all of its usefulness to the carrier in assessing the value of the case. If the Plaintiff and it expects are free to inflate their claims early in the case without having to worry about every supporting those claims in front of a jury, they have little or no credibility. And if those claims are inflated or not “real,” not only can the carrier not properly assess the verdict range and settlement value of the case, but it may also be hampered in making a coverage determination. Simply put, if the exchange of real information through formal discovery is put off until just before trial, the defense cannot be ready to settle until then. Worse, the cost of defense goes through the roof in the last 60 days before trial as the lawyers’ scramble to take all of the depositions and to all of the other work that had been stayed for the previous year or two.
The Plaintiff is faced with the same question of credibility of defense experts where they are free to take a “low ball” negotiating position without having to support that position through cross-examination in front of the jury. Just as the carrier behind the defense attorney needs the Plaintiff’s “real” evidence to assess the claim, so does the HIOA Board of Directors behind the Plaintiff’s counsel. Additionally, in California as in most states, the cost of experts’ preparation for mediation may not be recoverable as costs or damages, but investigation of the defects and preparation of the scope and cost of repair is recoverable.
The biggest challenge is resolving construction defect claims for both sides is how to resolve these cases quickly while keeping costs under control. Practices that worked 20 years ago are no longer applicable with changes in insurance, and in light of some of the bad habits that arise when all of the information exchanged was confidential.
The CMO/PTO process can still be useful to regulate the discovery and mediation schedule given the volume of documents and other information to be exchanged but exchanging “real” information in a form that may come into evidence at trial should foster earlier resolution, resulting in cost savings for the parties. The CMO can provide for the parties to respond to controlled discovery, and the exchange of expert reports and potentially depositions can and should be done earlier in the case, well before the eve of trial. The parties can then assess the true value of each case and prepare for more substantive mediation without waiting until they are on the figurative courthouse steps.
Construction defect cases have a pattern, and it is tempting for busy lawyers to just put each case through the same algorithms that they have used for years. However, these cases have evolved and those of us handling these cases need to reevaluate our approach to these cases. Taking aggressive negotiating positions that no longer have any credibility with the other side has become counterproductive, and the exchange of real evidence earlier in the case would better serve our clients and carriers.
BERDING|WEIL is the largest and most experienced construction defect and common interest development law firm in California. For more information, please visit https://www.berding-weil.com
Read the court decisionRead the full story...Reprinted courtesy of
Michael T. Kennedy Jr., BERDING|WEILMr. Kennedy may be contacted at
mkennedy@berdingweil.com
Coverage Denied Where Occurrence Takes Place Outside Coverage Territory
December 11, 2018 —
Tred R. Eyerly - Insurance Law HawaiiThe court held there was no coverage for construction defect claims that occurred outside the coverage territory. Foremost Signature Ins. Co. v. Silverboys, 2018 U.S. Dist. LEXIS 154524 (S.D. Fla. Sept. 11, 2018).
Solo Design, LLC, a Miami-based design company, entered into a contract with Silverboys, LLC (Owner) to provide interior design services in conjunction with the renovation of the Owner's vacation home in the Bahamas. Solo retained Whittingham, a Bahamian architect, as a subcontractor to serve as project manager.
Owner sued Solo, Whittingham and others in Florida for breach of contract, fraud, conversion and negligence when the project did not go as planned. The underlying complaint alleged intentional misconduct, lying about qualifications and the progress of the project, submitting false invoices, requesting money for services that were not performed, etc. Owner alleged that the damages included: (a) the cost to repair substandard work; (b) loss of use of the home due to delay; and (c) overcharges for furnishings, contract fees, and expenses. The underlying complaint set forth only a few instances of physical injury to the home, including mold on the ceiling in the master shower, faulty millwork on the children's playroom bookshelf, and a defective front door and resysta facade.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Ahlers Cressman & Sleight PLLC Recognized Among The Top 50 Construction Law Firms TM of 2024 by Construction Executive
July 15, 2024 —
Ahlers Cressman & Sleight PLLCACS is proud to announce that it has once again been ranked among The Top 50 Construction Law Firms in the Construction Executive 2023 rankings.
Since its first publication in 2003, Construction Executive magazine has served as the leading source for news, market developments, and business issues impacting the construction industry, and its articles are designed to help owners and top managers run a more profitable and productive construction business.
Construction Executive established the rankings by asking over 600 hundred U.S. construction law firms to complete a survey. Constructive Executive’s data collection includes: 2023 revenues from the firm’s construction practice, the number of attorneys in the firm’s construction practice, percentage of the firm’s total revenues derived from its construction practice, the number of states in which the firm is licensed to practice, the year in which the construction practice was established, and the number of construction industry clients served during the fiscal year 2023.
Read the court decisionRead the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
Contractor Sues Supplier over Defective Products
June 28, 2011 —
CDJ STAFFFast Track Specialties has sued RJF International after needing to remove wall protection units at Methodist West Houston Hospital, according to an article in the Houston Chronicle. Fast Track claims that contractors had to disconnect gas, water, and electric from the area to facilitate removal of corner guards, handrails, and crash guards from the hospital. This cost the contractor more than $135,000.
Fast Track is claiming that RJD International has committed breach of contract, breach of warranty, and negligent representation.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Boston Team Secures Summary Judgment Dismissal on Client’s Behalf in Serious Personal Injury Case
October 21, 2024 —
Lewis Brisbois NewsroomBoston, Mass. (October 14, 2024) - Boston Managing Partner Kenneth B. Walton and Partner Matthew M. O' Leary recently secured summary judgment on behalf of a civil engineering firm in a serious personal injury matter arising from a trip-and-fall incident in a mall parking lot.
The client was retained to provide site civil engineering design for the parking lot of a local mall. The design included multiple bioretention areas known as rain gardens. In November of 2019, a woman tripped and fell while attempting to cross a rain garden to reach her car. She suffered significant bodily injuries, including a fracture of the cervical spine that resulted in partial paralysis.
The woman and her husband sued the mall's owner for negligence and loss of consortium in June 2021. The owner, in turn, impleaded Lewis Brisbois' client and the lot's builder, asserting third-party claims for contribution, contractual and common law indemnity, and breach of contract. In addition, the builder cross-claimed against Lewis Brisbois' client for contribution and common law indemnity.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Another Defect Found on the Bay Bridge: Water Leakage
February 11, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to the San Francisco Chronicle, the eastern span of the Bay Bridge has dealt with alleged “defective welds” and “cracked steel rods,” and now there are reports of leakage. The Chronicle stated that rainwater “is dripping into the steel structure beneath the road deck on the suspension stretch of the span, which,” according to Caltrans “is supposed to be watertight.”
Water corrosion on a bridge could cost $6.4 billion, the San Francisco Chronicle claimed. Caltrans said that they “are going to have teams of engineers and inspectors there this weekend to assess the problem.”
Read the court decisionRead the full story...Reprinted courtesy of
Home Construction Slows in Las Vegas
November 27, 2013 —
CDJ STAFFAlthough home builders in the Las Vegas area are doing better than they were in 2012, growth is still slow and October saw a decline in the sale of new homes. However, as with other areas, the average home price actually increased over prior months, despite the cooling off the actual number of sales.
Taken as a whole though, 2013 looks a lot better than 2012, with 44% more homes sold this year. Dennis Smith, the president of Home Builders Research said that 2013 “will be remembered as ‘the year of recovery,’” but added that “there is still a long path ahead for everyone to feel a sense of comfort.”
Read the court decisionRead the full story...Reprinted courtesy of
In Pricey California, Renters Near Respite From Landlord Gouging
September 16, 2019 —
Noah Buhayar - BloombergThe housing crisis engulfing California has state lawmakers racing to pass bills that would boost construction and stop corporate landlords from egregiously jacking up rents.
The bills overcame key hurdles last week and are due for final votes before the legislature adjourns on Sept. 13. The hardest-fought measure would set a higher standard for evictions and cap annual rent increases at 5% plus the rate of inflation. While that’s below the typical pace of lease hikes -- and the bill has many caveats for landlords -- it would still mark the state’s most significant new protection for tenants in decades.
Read the court decisionRead the full story...Reprinted courtesy of
Noah Buhayar, Bloomberg