CGL Insurer’s Duty to Defend Insured During Pre-Suit 558 Process: Maybe?
December 20, 2017 —
David Adelstein - Florida Construction Legal UpdatesIn earlier postings, I discussed the issue of whether Florida Statutes Chapter 558′s pre-suit construction defects process triggers a CGL insurer’s duty to defend. The issue was whether Florida’s 558 pre-suit notice of a construction defect and repair process met the definition of “suit” within a standard CGL policy.
A standard CGL policy defines the term “suit” as:
“Suit” means a civil proceeding in which damages because of “bodily injury,” “property damage” or “personal and advertising injury” to which this insurance applies are alleged. “Suit” includes:
a. An arbitration proceeding in which such damages are claimed and to which the insured must submit or does submit with our consent; or
b. Any other alternative dispute resolution proceeding in which such damages are claimed and to which the insured submits with our consent.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Busting Major Alternative-Lending Myths
July 22, 2024 —
Warren Miller - Construction ExecutiveAlternative capital is a broad term for financing provided by institutions or firms that typically fall outside of the purview of the larger, regulated institutions (i.e., not traditional banks). While these funding sources may not always be the first option for many businesses, alternative lending is a perfect option for many small and mid-sized capital-intensive companies, like construction companies, which often require fast access to capital that is incompatible with the stringent and laborious processes imposed by traditional banks.
Construction companies should take a closer look at alternative financing, understand its benefits, and evaluate its usefulness for achieving their unique funding requirements.
REALITY 1: ALTERNATIVE LENDING IS SAFE AND PROVEN
Private lending has been around for a long time, and has become increasingly common since the 1990s, when major consolidation took place in the banking industry. As the large, consolidated banks set their sights on providing loans to large enterprises, they left a gap in the small and mid-size market that was filled by alternative lenders. By 2000, alternative lenders had overtaken traditional banks for the majority of corporate loans. Stricter regulation of banks following the Global Financial Crisis of 2007 intensified underwriting standards for bank loans and further diminished banks’ appetites for SMB lending.
Reprinted courtesy of
Warren Miller, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury Attorneys Featured in 2021 Best Lawyers in America and Best Lawyers: Ones To Watch!
September 28, 2020 —
Wilke Fleury LLPWilke Fleury congratulates attorneys
David Frenznick,
Adriana Cervantes and
Dan Egan on their inclusion in the 2021 Edition of Best Lawyers in America!
Since it was first published in 1983, Best Lawyers® has become universally regarded as the definitive guide to legal excellence. Best Lawyers lists are compiled based on an exhaustive peer-review evaluation. Almost 108,000 industry leading lawyers are eligible to vote (from around the world), and they have received over 13 million evaluations on the legal abilities of other lawyers based on their specific practice areas around the world. For the 2021 Edition of The Best Lawyers in America©, 9.4 million votes were analyzed.
Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury
Hunton Insurance Group Advises Policyholders on Issues That Arise With Wildfire Claims and Coverage – A Seven-Part Wildfire Insurance Coverage Series
June 27, 2022 —
Scott P. DeVries & Yosef Itkin - Hunton Insurance Recovery BlogWildfires destroy millions of acres a year in the United States, spewing smoke across much of the nation. The cost of damage alone over the past several years soars into the hundreds of billions. As wildfires continue to spread, particularly as we enter wildfire season, policyholders’ claims will rise and with that, so too will wildfire insurance coverage issues. Many believe that when a fire damages their property and/or interrupts their business operations, a claim gets submitted and is automatically paid; sadly, this is often not the case.
In a seven-part series delving into issues relating to wildfire insurance coverage, the Hunton insurance group provides a comprehensive understanding of the types of policies that may be available, legal and factual issues that may arise, and steps policyholders can take – both in advance and during the claims process – to maximize recovery. The following issues will be addressed:
- Part One: Types of Wildfire-Related Losses and the Policies That May Provide Coverage
- Part Two: Coverage for Smoke-Related Damages
- Part Three: Standard Form Policy Exclusions
- Part Four: Coverage for Supply Chain Related Losses
- Part Five: Valuation of Loss, Sublimits, and Amount of Potential Recovery
- Part Six: Ensuring Availability of Insurance and State Regulations
- Part Seven: How to Successfully Prepare, Submit and Negotiate the Claim
Reprinted courtesy of
Scott P. DeVries, Hunton Andrews Kurth and
Yosef Itkin, Hunton Andrews Kurth
Mr. DeVries may be contacted at sdevries@HuntonAK.com
Mr. Itkin may be contacted at yitkin@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
N.J. Governor Fires Staff at Authority Roiled by Patronage Hires
August 20, 2019 —
Elise Young, BloombergNew Jersey Governor Phil Murphy’s administration fired 30 employees of a state authority that finances local school construction after an independent review found that his former appointee stacked it with friends, family and political contacts who were unqualified for their jobs.
All but three of those dismissed Tuesday from the Schools Development Authority had been hired by Lizette Delgado-Polanco, the former chief executive officer who resigned in April amid media scrutiny of her oversight. A review by an outside law firm faulted the agency for “patronage-type hires” that undermined its work.
Read the court decisionRead the full story...Reprinted courtesy of
Elise Young - Bloomberg
New California "Construction" Legislation
November 08, 2018 —
Richard H. Glucksman, Esq. & Chelsea L. Zwart, Esq. - Chapman Glucksman Dean Roeb & BargerGovernor Jerry Brown signed two potentially impactful Senate Bills relating to the construction of apartment buildings late last month. These Bills, discussed further below, were introduced, in part, in response to the Berkeley balcony collapse in June 2015, which was determined by the California Contractors State License Board to be caused by the failure of severely rotted structural support joists the repair of which were deferred by the property manager, despite indications of water damage.
SENATE BILL 721 ESTABLISHES HEIGHTENED “LOAD-BEARING” INSPECTION REQUIREMENTS
On August 21, 2018, the California State Senate passed SB 721, one of two bills by Senator Jerry Hill introduced this year seeking to address the safety of multifamily rental residences. Now that the Governor has signed the Bill, a new section will be added to the California Health and Safety Code, requiring that every 6 years, destructive testing be performed on at least 15% of each type of load-bearing, wood framed exterior elevated element (such as balconies, walkways, and stair landings) in apartment buildings with 3 or more units. Interestingly, prior to being passed by the State Senate, SB 721 was revised in June 2018, such that the inspection requirements do not apply to common interest developments (i.e., condominiums).
As set forth in the new Health and Safety Code Section 17973:
"the purpose of the inspection is to determine that exterior elevated elements and their associated waterproofing elements are in a generally safe condition, adequate working order, and free from any hazardous condition caused by fungus, deterioration, decay, or improper alteration to the extent that the life, limb, health, property, safety, or welfare of the public or the occupants is not endangered."
The inspection must be paid for by the building owner and performed by a licensed contractor, architect, or civil or structural engineer, or a certified building inspector or building official from a recognized state, national, or international association. Emergency repairs identified by the inspector must be made immediately. For non-emergency repairs, a permit must be applied for within 120 days and the repair completed within 120 days of the permit’s issuance. If repairs are not completed within 180 days, civil penalties of $100-$500 per day may be imposed.
The required inspection must be completed by January 1, 2025 and every 6 years thereafter, unless an equivalent inspection was performed during the 3 years prior to January 1, 2019, the effective date of the new law. For a building converted to condominiums that will be sold after January 1, 2019, the inspection required by Health and Safety Code Section 17973, must be performed prior to the first close of escrow.
SENATE BILL 1465 SETS CONTRACTOR REPORTING REQUIREMENTS
The Governor also signed SB 1465, adding Sections 7071.20, 7071.21, and 7071.22 to the California Business and Professions Code. The new law requires that a contractor licensed with the Contractors’ State License Board "report to the registrar in writing within 90 days after the licensee has knowledge of any civil action resulting in a final judgment, executed settlement agreement, or final arbitration award in which the licensee is named as a defendant or crossdefendant, filed on or after January 1, 2019," that meets certain and specific criteria, including that it is over $1 million and arises out of an action for damages to a property or person allegedly caused by specified construction activities of the contractor on a multifamily rental residential structure.
Where more than one contractor was named as a defendant or cross-defendant, each of the contractors apportioned more than $15,000 in liability must report the action. Importantly, the new statute also imposes similar reporting requirements on insurers of contractors. SB 1465 also addresses an impacted party’s failure to comply with the reporting requirements.
COMMENT
Both SB 721 and SB 1465 are potentially significant and seek “legislative reform” to address construction issues by placing a greater burden on apartment owners as well as builders and subcontractors. How pragmatic and what impact they will have on the industry is obviously developing. If you are interested in receiving further detail concerning the Bills, please contact us. We are analyzing the new legislation and its intent and will be providing our ongoing comments.
Read the court decisionRead the full story...Reprinted courtesy of
RICHARD H. GLUCKSMAN, ESQ. CHELSEA L. ZWART, ESQ., CGDRBChelsea L. Zwart may be contacted at
czwart@cgdrblaw.com
Construction Termination Issues Part 6: This is the End (Tips for The Design Professional)
September 25, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaWhether your role is in helping analyze the contractor’s work on the project to certify a
contractor’s termination for cause, or you are
being shown the door yourself, and everything in between, termination is a subject that is ripe with potential problems.
Consider these summary tips as part of your practice, every time the termination idea arises:
- Remember that you are the neutral and must be impartial between Owner and Contractor
- After you have made a fair decision, document your decision to the Owner and Contractor
- Provide options less nuclear for Owners– stop work; removing scopes of work; etc.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Kumagai Drops Most in 4 Months on Building Defect: Tokyo Mover
June 11, 2014 —
Kathleen Chu and Kevin Buckland - BloombergKumagai Gumi Co. (1861), a Japanese construction company, fell the most in four months after saying an apartment complex it had built has defects.
The shares dropped 5.7 percent to 264 yen at the close of trading in Tokyo, the biggest decline since Feb. 4. Construction flaws in supporting pillars were found in the building completed in March 2003 in Yokohama City, south of Tokyo, the company said in a statement through the stock exchange today. The residents have been asked to relocate to temporary shelters and further investigation is required, it said.
“This is a big negative for Kumagai’s reputation and it may hurt the company’s future earnings,” said Yoji Otani, an analyst at Deutsche Bank AG in Tokyo.
The latest defect comes after Mitsubishi Estate Co. (8802) said in March it will rebuild a residential complex, constructed by Kajima Corp. (1812), in central Tokyo, after defects were found. Mitsui Fudosan Co. (8801) said it would repair some parts of an apartment building in Kawasaki City after the builder Shimizu Corp. (1803) found cracks in the concrete of some columns in April.
Ms. Chu may be contacted at kchu2@bloomberg.net; Mr. Buckland may be contacted at kbuckland1@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Kathleen Chu and Kevin Buckland, Bloomberg