Tred R. Eyerly – Insurance Law HawaiiThe court found the contractor did not have coverage as an additional insured under the subcontractor's policy. Walton Constr. v. First Fin. Ins. Co., 2015 US. Dist. LEXIS 30710 (E.D. La. March 12, 2015).
John Maestri was injured while working on a construction project for the Jefferson Parish School Board. Maestri was a commercial glazier for A-1 Glass Services Inc. A-1 was a subcontractor for Walton Construction. While Maestri was installing glass on the project, a high-voltage power line maintained by Entergy Louisiana, LLC electrocuted him, causing burns on his body.
Maestri sued Entergy. Entergy filed a third-party complaint against A-1 and Walton, alleging that the Louisiana Overhead Power Line Safety Act had been violated by failing to give advance notice that their workers would be working near the power lines. Entergy argued that under the statute, A-1 and Walton are liable for any damages that Entergy had to pay Maestri.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Sales of U.S. Existing Homes Rise to One-Year High
October 22, 2014 —
Michelle Jamrisko – BloombergSales of previously owned homes climbed in September to the highest level in a year, pointing to growing confidence in the U.S. economy as employment firms.
Purchases advanced 2.4 percent to a 5.17 million annual rate, the National Association of Realtors reported today in Washington. Demand was up 1.9 percent compared with the same month last year before adjusting for seasonal patterns.
Americans are returning to the real-estate market as employers have added 2 million workers to payrolls so far this year. Sales stand to get an additional boost in the final months of 2014 as the drop in mortgage rates caused by slowing growth in Europe and emerging nations makes properties more affordable for first-time buyers.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko, BloombergMs. Jamrisko may be contacted at
mjamrisko@bloomberg.net
Unjust Enrichment Claims When There Is No Binding Contract
December 04, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent appellate opinion starts off, “This is a typical South Florida construction dispute.” (See case citation at the bottom) Let’s see, is it? No. It’s a garden variety payment dispute where the parties did NOT have a binding contract. Why? That’s for a different day (because the smart practice is ALWAYS to have a contract!) but it touches on the equitable, unjust enrichment claim. And it touches on competing unjust enrichment claims and the apportionment of those claims. In other words, can both parties be right on their unjust enrichment claims?
An owner hired a general contractor for home renovations. Work started but the relationship soured and the general contractor did not complete the work. The general contractor filed a payment dispute against the owner based on unpaid invoices. It pled alternative theories of recovery against the owner: breach of contract and unjust enrichment. The owner filed a counterclaim against the general contractor for the same claims. During the non-jury trial, the general contractor presented unpaid invoices along with testimony that the invoices represented the value of services rendered. The owner presented evidence of the completion of work damages.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Back to Basics – Differing Site Conditions
December 19, 2018 —
Tracey W. Pruiett - Smith CurrieEncountering an unexpected site condition is one of the more common risks on a construction project. A “differing site condition”, or it is sometimes called a “changed condition”, is generally understood to be a physical condition that is discovered while performing work and that was not visible or otherwise expected at the time of bidding. Often, the condition could not have been discovered by a reasonable site investigation. Examples of common differing site conditions include: soil with inadequate bearing capacity to support the building being constructed, soil that cannot be reused as structural fill, unanticipated groundwater, quicksand, mud, rock formations, or other artificial subsurface obstructions. Differing site conditions may also occur within the walls or ceilings of a renovation project such as the renovation of a hospital or historic building.
Read the court decisionRead the full story...Reprinted courtesy of
Tracey W. Pruiett, Smith CurrieMs. Pruiett may be contacted at
twpruiett@smithcurrie.com
PPP Loan Extension Ending Aug. 8
August 03, 2020 —
Construction ExecutiveThere is just over one week left to apply for the extended period of the Paycheck Protection Program, which will accept new applications through Aug. 8. Congress extended the legislation by unanimous consent on June 30 and President Trump signed the bill into law on July 4, 2020, allowing approximately $131.9 billion in funding to remain accessible to small businesses affected by the COVID-19 pandemic.
Associated Builders and Contractors has expressed support for several changes to the PPP, but submitted comments on July 27, 2020, to the U.S. Department of the Treasury and U.S. Small Business Administration regarding changes to an interim final rule altering loan forgiveness and loan review procedures. ABC urges the government agencies to:
- Provide further guidance on when businesses should apply for loan forgiveness and when they are notified of their forgiveness status.
- Issue further guidance on the PPP audit process.
- Increase flexibility for employee retention requirements and loan forgiveness.
- Provide further clarification of non-payroll costs.
- Refocus efforts to deliver PPP funds to underserved communities and minority businesses.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Attorneys Recognized in the 2024 Edition of The Best Lawyers in America®
September 06, 2023 —
Traub LiebermanRelated Attorneys:
Lisa L. Shrewsberry,
Brian C. Bassett,
Rina Clemens,
Lauren S. Curtis,
Scot E. Samis,
Anthony Hatzilabrou,
Adam P. Joffe,
Heather Jones,
Ashley Kellgren,
Jessica N. Kull,
Ryan S. Parker,
Nicole E. Shapiro
Traub Lieberman is pleased to announce that five Partners have been selected by their peers for inclusion in the 2024 edition of The Best Lawyers in America®. In addition, seven attorneys have been included in the 2024 Best Lawyers®: Ones to Watch list. These recognitions include attorneys from the firm’s Hawthorne, NY; Chicago, IL; Palm Beach Gardens, FL; and St. Petersburg, FL offices.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
Despite Feds' Raised Bar, 2.8B Massachusetts Offshore Wind Project Presses On
November 04, 2019 —
Mary B. Powers - Engineering News-RecordDevelopers of the 800-MW, 84-turbine Vineyard Wind offshore wind energy farm in Massachusetts, set to be the first and largest commercial-scale project in the U.S., say they are committed to pushing through its $2.8-billion construction despite a sudden Trump administration permitting setback.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record
ENR may be contacted at ENR.com@bnpmedia.com
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Response: Recent Executive Orders Present Opportunities for Businesses Seeking Regulatory and Enforcement Relief and Expedited Project Development
June 15, 2020 —
Karen C. Bennett, Jane C. Luxton & Amanda L. Tharpe - Lewis BrisboisWashington, D.C. (June 8, 2020) - Two recent Executive Orders (EO) aimed at promoting economic recovery from the COVID-19 crisis offer regulatory and enforcement relief and encourage agencies to expedite infrastructure project approvals. The May 19, 2020 EO 13924, “Regulatory Relief to Support Economic Recovery,” directs agencies to determine whether previous regulatory reforms would promote economic recovery if made permanent and encourages compliance assistance through exercising enforcement discretion, including declining enforcement. And the June 4, 2020 EO 13927, “Accelerating the Nation’s Economic Recovery from the COVID-19 Emergency by Expediting Infrastructure Investments and Other Activities,” aims to speed up the permitting process for infrastructure projects to strengthen the national economy. As businesses look to move forward and recover from the COVID-19 pandemic, they should closely review these EOs for opportunities to take advantage of streamlined treatment and faster project approvals.
EO 13294 supplements the Administration’s efforts to address the economic crisis brought on by the COVID-19 pandemic by encouraging federal agencies to rescind, modify, waive, or provide exemptions from federal regulations that may inhibit economic recovery and to provide guidance to businesses, particularly small businesses, on what is required of them under federal law for reopening. Specifically, the EO directs agency heads to identify regulatory standards that may inhibit economic recovery and consider rescinding or waiving those regulations, exempting regulated entities from compliance, exercising enforcement discretion, or extending regulatory compliance and enforcement deadlines. It also allows for compliance assistance through accelerated regulatory procedures to receive a pre-enforcement ruling and directs agencies to assess previous regulatory reforms to determine whether making them permanent would promote economic recovery. Since taking office, the Trump Administration has made regulatory reform a cornerstone of its agenda. This Executive Order is a continuation of the aggressive steps taken by the Administration to reduce the regulatory burden faced by American businesses that many argue increases operating costs, inhibits job creation, and stifles economic growth.
Reprinted courtesy of Lewis Brisbois attorneys
Karen C. Bennett,
Jane C. Luxton and
Amanda L. Tharpe
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Ms. Tharpe may be contacted at Amanda.Tharpe@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of