Liability policy covers negligent construction: GA high court
October 31, 2010 —
Michael Bradford in Business InsuranceATLANTA—Negligent construction that results in damage to surrounding property constitutes an occurrence under a commercial general liability policy, the Georgia Supreme Court has ruled.
In a 6-1 opinion Monday in
American Empire Surplus Lines Insurance Co. Inc. vs. Hathaway Development Co. Inc., the Georgia high court upheld a lower court ruling that the general contractor’s claim for damage caused by a subcontractor’s faulty plumbing work was covered.
The ruling on construction defects is the latest in number of such cases across the United States
Read Full Story...
Reprinted courtesy of Michael Bradford of Business Insurance.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Attorneys Recognized in the 2023 Edition of The Best Lawyers in America®
September 19, 2022 —
Traub LiebermanTraub Lieberman is pleased to announce that five Partners have been selected by their peers for inclusion in the 2023 edition of The Best Lawyers in America®. In addition, four attorneys have been included in the 2023 Best Lawyers®: Ones to Watch list. These recognitions include attorneys from the firm’s Hawthorne, NY; Chicago, IL; Palm Beach Gardens, FL; and St. Petersburg, FL offices.
2023 Best Lawyers®
Hawthorne, NY
- Lisa L. Shrewsberry – Commercial Litigation
Chicago, IL
- Brian C. Bassett – Insurance Law
Palm Beach Gardens, FL
- Rina Clemens – Personal Injury Litigation – Defendants
St. Petersburg, FL
- Scot E. Samis – Appellate Practice
- Lauren S. Curtis – Insurance Law
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman
The Future for Tall Buildings Could Be Greener
October 01, 2013 —
CDJ STAFFSkidmore, Owens and Merrill made its reputation by creating iconic structures of steel, concrete, and glass, but in a new report, the firm puts forth ways in which the first item would be wood. Building codes in many cities stipulate that buildings taller than four stories be built of steel and concrete, but the firm says that it has come up with a way of building structures of 30 stories or more using wood.
The tallest wood-framed building currently is only ten stories tall. In order to calculate a comparison, Skidmore, Owens and Merrill designed a forty-two story building based on the design of an existing apartment building. Actually building it would require almost 4 million board-feet of wood. Unlike a typical single-family home (and its 20,000 board-feet of wood), these building would use glue-laminated timber and slabs.
The study found that the building would weigh less than half as much, allowing a less massive foundation. If the wood came from sustainable sources, its environmental impact would be drastically reduced. They calculated that instead of 9,500 tons of CO2 emissions for the conventional tower, the wood structure would be responsible for only 2,100 tons of emissions.
Skyscrapers will continue to be a feature of large cities. But instead of urban canyons of steel and concrete, in the future those towering buildings might be made of wood.
Read the court decisionRead the full story...Reprinted courtesy of
Doing Construction Lead Programs the Right Way
October 16, 2018 —
Natalie Craigmile - Construction InformerRunning a construction business takes hard work. When you are working on a job, it can be difficult to find time to spend on marketing and advertising. If you are short on time, buying leads through construction lead programs could be a good way to meet new customers, grow your business, and find your next job. Keep reading to learn more about some of the pros and cons of buying leads.
A construction lead generation service exists solely to connect home owners with local home improvement contractors. They market across different construction specialties and reach customers who are looking for construction companies. Once they capture the ‘lead’, which is essentially the contact information and a few project details of that potential customer, they sell the lead to one or more local contractors in their network.
Read the court decisionRead the full story...Reprinted courtesy of
Natalie Craigmile, Construction Informer
New York Court of Appeals Addresses Choice of Law Challenges
August 20, 2018 —
Grace V. Hebbel - Saxe Doernberger & Vita, P.C.In June, the New York Court of Appeals examined the application of a New York Choice of Law provision in a contract – a determinative issue for the case. In Ontario, Inc. v. Samsung C&T Corp., the issue was whether the plaintiff’s claims were subject to Ontario, Canada’s 2-year statute of limitations or New York’s 6-year statute of limitations for breach of contract where the contract contained a broad New York Choice of Law provision. The court found that pursuant to New York’s borrowing statute, Ontario’s more restrictive statute of limitations applied. The action was dismissed as time-barred, serving as a harsh reminder of the potential effects of choice of law and limitations periods.
The suit arose out of the following facts. In 2008, an Ontario renewable energy developer, SkyPower Corp. (“SkyPower”), entered into a Non-Disclosure Agreement (NDA) with the defendants which allowed the defendants to review SkyPower’s confidential and proprietary information. The review was conditioned on restricted disclosure and the requirement that the information would be destroyed after review.
Read the court decisionRead the full story...Reprinted courtesy of
Grace V. Hebbel, Saxe Doernberger & Vita, P.C.Ms. Hebbel may be contacted at
gvh@sdvlaw.com
White and Williams Obtains Reversal on Appeal of $2.5 Million Verdict Against Electric Utility Company
September 03, 2014 —
Edward Koch, Mark Paladino, Luke Repici, & Andrew Susko – White and Williams LLPPPL Electric Utilities successfully argued on appeal that the $2.5 million plaintiff’s molded verdict awarded to an injured painting subcontractor should be vacated because the alleged evidence was legally insufficient and therefore the utility was not liable.
In Nertavich v. PPL Electric Utilities, the plaintiff argued that although the utility was a landowner out of possession of the worksite, the utility was liable because it controlled the work of the subcontractor both by contract and by conduct. PPL argued on appeal before the Superior Court of Pennsylvania that the alleged evidence of the utility company’s control was insufficient as a matter of law to constitute control over the means and methods of the subcontractor’s work, and thus, PPL was not liable as a landowner out of possession.
Reprinted courtesy of White and Williams LLP attorneys
Edward Koch,
Mark Paladino,
Luke Repici and
Andrew Susko
Mr. Koch may be contacted at koche@whiteandwilliams.com;
Mr. Paladino may be contacted at paladinom@whiteandwilliams.com;
Mr. Repici may be contacted at repicil@whiteandwilliams.com;
and Mr. Susko may be contacted at suskoa@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
California Trial Court Clarifies Application of SB800 Roofing Standards and Expert’s Opinions
February 18, 2020 —
Scott Calkins & Anthony Gaeta - Collinsworth, Specht, Calkins & Giampaoli; Mark Chapman - Bert L. Howe & Associates, Inc.Collinsworth, Specht, Calkins & Giampaoli partners Scott Calkins and Anthony Gaeta obtained a trial victory when the jury returned a 12-0 defense verdict against one plaintiff homeowner, and awarded the other homeowner less than $2,000, an amount well below the defendant’s pre-trial CCP 998 Offers to Compromise. One of the main issues in the case was the application of SB800 roofing standards. Plaintiffs’ roofing expert testified in deposition no water entered the structure or passed through a moisture barrier [Civ. Code §896(a)(4)], and no materials had fallen off the roof [§896(g)(11)]. In an attempt to circumvent the applicable performance standards, Plaintiffs argued Civ. Code §869(g)(3)(A), also known as the ‘useful life’ exception, applied because the various components of the roof (nailing pattern, tiles, vents, etc.) were installed in such a manner so as to reduce the useful life of the roof. Following pre-trial motions and objections made during Plaintiffs’ direct examination, the Court ruled Section 896(g)(3)(A) did not apply to a conventional roof, as it is not a “manufactured product” as defined in §896(g)(3)(C). Plaintiffs’ roofing claims were summarily dismissed and Plaintiffs’ expert was prevented from testifying.
In contrast, the defense expert, Mark Chapman, was allowed to testify regarding his expert opinions as to the appropriate SB800 standard relative to each alleged defect and whether the standards were violated. The SB800 performance standards were included on the jury verdict form, and the jury found Mr. Chapman’s testimony compelling, which was a substantial factor in awarding only minor damages to one Plaintiff.
For more information, contact
Scott Calkins (scalkins@cslawoffices.com),
Anthony Gaeta (ageta@cslawoffices.com) or
Mark Chapman (mchapman@berthowe.com).
Read the court decisionRead the full story...Reprinted courtesy of
Following Pennsylvania Trend, Federal Court Finds No Coverage For Construction Defect
December 08, 2016 —
Tred R. Eyerly – Insurance Law HawaiiBound by Pennsylvania law, the federal district court found there was no coverage for defects in the installation of a roof. State Farm Fire & Cas. Co. v. Kim's Asia Constr., 2016 U.S. Dist. LEXIS 138915 (E.D. Pa. Oct. 5, 2016).
Kim's Asia Construction contracted to remove and dispose of Powerline Imports, Inc.'s roof, and then install a new roof. After completion of the project, Powerline sued, alleging that Kim's Asia's negligent construction of the roof caused the roof to leak, even in minor rain storms. Kim's Asia made additional repairs, but the leaks continued. Powerline had to hire a new contractor to remove and dispose of the roof and install another roof. Powerline then sued Kim's Asia.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at