Do Not File a Miller Act Payment Bond Lawsuit After the One-Year Statute of Limitations
November 01, 2022 —
David Adelstein - Florida Construction Legal UpdatesUnder the Miller Act, a claim against a Miller Act payment bond must be commenced “no later than one year after the date on which the last of the labor was performed or material was supplied by the person bringing the action.” 40 U.S.C. s. 3133(b)(4). Stated another way, a claimant must file its lawsuit against the Miller Act payment bond within one year from its final furnishing on the project.
Filing a lawsuit too late, i.e., outside of the one-year statute of limitations, will be fatal to a Miller Act payment bond claim. This was the outcome in Diamond Services Corp. v. Travelers Casualty & Surety Company of America, 2022 WL 4990416 (5th Cir. 2022) where a claimant filed a Miller Act payment bond lawsuit four days late. That four days proved to be fatal to its Miller Act payment bond claim and lawsuit. Do not let this happen to you!
In Diamond Services Corp., the claimant submitted a claim to the Miller Act payment bond surety. The surety issued a claim form to the claimant that requested additional information. The claimant returned the surety’s claim form. The surety denied the claim a year and a couple of days after the claimant’s final furnishing. The claimant immediately filed its payment bond lawsuit four days after the year expired. The claimant argued that the surety should be equitably estopped from asserting the statute of limitations in light of the surety’s letter requesting additional information. (The claimant was basically arguing that the statute of limitations should be equitably tolled.) The trial court dismissed the Miller Act payment bond claim finding it was barred by the one-year statute of limitations and that equitable estoppel did not apply.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Misread of Other Insurance Clause Becomes Costly for Insurer
February 22, 2018 —
Tred R. Eyerly – Insurance Law HawaiiOne insurer's refusal to defend based upon its "other insurance" provision ultimately meant the insurer had to pay all of the insured's defense costs. Steadfast Ins. Co. v. Greenwich Ins. Co., 2018 Wis. App. LEXIS 51 (Wis. Ct. App. Jan. 17, 2018).
Milwaukee Metropolitan Sewerage District (MMSD) was a government agency that provided water reclamation and flood management services to the city. From March 1, 1998 to February 20, 2008, MMSD contracted with United Water Services Milwaukee LLC to operate the sewerage system. From March 1, 2008 on, MMSD contracted with Veolia Water North America-Central, LLC to operate the system.
Through agreements, both companies were obligated to indemnify MMSD for claims arising out of the operations and maintenance of the system and to obtain insurance to cover their indemnity obligations. Both companies complied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Buy Clean California Act Takes Effect on July 1, 2022
July 25, 2022 —
Garret Murai - California Construction Law BlogThe Buy Clean California Act (BCCA) – Public Contract Code section 3500 et seq. – requires state agencies to consider the carbon content of the following products when awarding contracts:
- Structural steel;
- Concrete reinforcing steel;
- Flat glass; and
- Mineral wool board insulation.
It is anticipated that additional products may be added through future legislation.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
How Long Does a Civil Lawsuit Take?
August 14, 2018 —
Bremer Whyte Brown & O’MearaHow long does a civil lawsuit take?
One common question among parties to a civil lawsuit, whether a plaintiff or defendant, is how long will it take to reach a resolution? The answer is tricky. The time it takes to resolve a civil lawsuit is highly dependent on various factors including the complexity of the matter and the parties’ willingness to settle.
At the outset, parties to a civil case may resolve the matter at any time by mutual agreement (i.e., settlement). In that case, the parties draft a Stipulation and Order outlining the terms of the agreed settlement and submit the document to the judge for approval. Absent of any glaring inequity in the terms of the Stipulation, the judge will typically approve of the parties’ settlement, and the matter will be deemed resolved (either in whole or in part, depending on the case, the terms of the settlement and indemnity agreement).
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara
Private Mediations Do Not Toll The Five-Year Prosecution Statute
April 28, 2016 —
Zachary P. Marks – Chapman Glucksman Dean Roeb & Barger In FocusIf you thought private mediation could toll the five-year period for case prosecution – think again. In a recent decision handed down by the Second District Court of Appeal, the court unequivocally held that voluntary, private mediations do not toll the five-year period before dismissal for failure to bring an action to trial.
California Code of Civil Procedure section 583.310 sets forth the applicable rule: “[a]n action shall be brought to trial within five years after the action is commenced against the defendant.” Section 1775.7(b) clarifies this rule, stating that the five-year period can be tolled if it is “submitted to mediation” within the final six months of the five-year period. However, the Code is silent with respect to the effect of tolling on public versus private mediations.
The Court of Appeal addressed this issue in its recent decision entitled Castillo v. DHL Express (USA) (2015) 243 Cal.App.4th 1186. Castillo was an employment class action brought by truck drivers against their employers. Plaintiffs argued that the case was “submitted to mediation” within the meaning of Section 1775.7(b) because the court’s Case Management Order reflected the fact that the parties agreed to pursue mediation. Conversely, defendants argued that the Case Management Statement clearly stated that the parties voluntarily agreed to a private mediation, not a court-ordered mediation.
Read the court decisionRead the full story...Reprinted courtesy of
Zachary P. Marks, Chapman Glucksman Dean Roeb & Barger In FocusMr. Marks may be contacted at
zmarks@cgdrblaw.com
Florida District Court Finds That “Unrelated” Design Errors Sufficient to Trigger “Related Claims” Provision in Architects & Engineers Policy
March 02, 2020 —
Jason Taylor - Traub LiebermanMost professional liability polices include some form of a “related claims” provision that generally provides where two or more claims or wrongful acts are causally or logically related, they will be deemed to constitute a single claim. Importantly, these provisions typically provide that those “claims” are then deemed to have been “first made” at the time the first claim or act was committed for purposes of the policy’s claims-made and reporting requirements. Understandably, these provisions provide insurers and insureds with some clarity over the number and timing of claims that could involve multiple errors or omissions, and potentially aggregate all related claims or acts into a single policy period. While reasonable in principle, application of such provisions, especially involving large scale design and construction projects, is not always so easy.
Nova Southeastern University, Inc. v. Continental Cas. Co., 18-cv-61842 (S.D. Fla. Dec. 27, 2019), involved such an insurance coverage dispute with a design project gone wrong. DeRose Design Consultants, Inc. (“DeRose”) was hired as a structural engineer to design “ice tanks” to store and chill water for an energy efficient air conditioning facility constructed on the campus of Nova Southeastern University (“NSU”). An early water test on one of the tanks determined the walls of the ice tank deflected, leaked, and cracked when the tank was filled with water. DeRose later discovered that the problems with the ice tank were caused by a structural design error.
The first errors were discovered in early 2009, and reported under DeRose’s professional liability policy with Evanston. DeRose then created a remedial design to repair the tanks, which involved strengthening repairs. Additional leaking and an early indication of corrosion involving the Remedial Design arose as early as October 25, 2009. Several field investigation reports were prepared in 2011 and 2012 confirming these issues with the Remedial Design. A third report in February 2012, however, identified a new error involving the concrete slab under the ice tanks also designed by DeRose. The third report concluded that the concreate slab was overstressed and could not handle the loads of the ice tanks. The report also concluded, however, that the design defects in the concrete slab were “unrelated” to the original design defect of the ice tank walls or Remedial Design.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Homebuilders Offer Hope for U.K. Economy
August 20, 2014 —
Mark Gilbert – BloombergThe two elements of the U.K. economy that the Bank of England currently finds most worrying are the overheating housing market and the paucity of wage growth. Earnings reports this week from two of the nation's biggest homebuilders make for cheery reading on both counts.
Persimmon Plc, the U.K.'s largest homebuilder by market value, said today it completed 6,408 new homes in the first half of the year, a 28 percent increase from the year-earlier period. Bovis Homes Group, which mostly builds what it calls "traditional" family homes in the south of England outside London, said it sold 1,487 new homes in the first six months, a gain of 54 percent.
"The government has told us that we need 230,000 new homes per annum, and far be it for us to disagree with that," Bovis Chief Executive Officer David Ritchie said on a conference call. He expects to build about 3,650 homes this year, and reckons that "5,000 to 6,000 homes per annum is a very sensible target for the business."
Read the court decisionRead the full story...Reprinted courtesy of
Mark Gilbert, BloombergMr. Gilbert may be contacted at
magilbert@bloomberg.net
OSHA Set to Tag More Firms as Severe Violators Under New Criteria
November 01, 2022 —
Richard Korman & Stephanie Loder - Engineering News-RecordIn announcing last month broadened criteria for classifying employers as severe safety violators, U.S. Occupational Safety and Health Administration official Douglas Parker singled out a steel fabricator near El Paso, Texas. The U.S. Labor Dept. assistant secretary for occupational safety and health, he posted a blog stating that OSHA had placed Kyoei Steel Ltd. in its severe violators program, which subjects the firm to numerous re-inspections until it is allowed to exit.
Reprinted courtesy of
Richard Korman, Engineering News-Record and
Stephanie Loder, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of