A Guide to Evaluating Snow & Ice Cases
December 13, 2021 —
Lewis BrisboisNew York, N.Y. (November 9, 2021) - As the winter season nears, defendant property owners are reminded that New York law imposes liability for sidewalk accidents resulting from slip and falls on snow and ice. Within the City of New York, Administrative Code § 7-210 imposes liability on the owners of real property (other than single-family dwellings) to maintain an abutting sidewalk in a reasonably safe condition, which includes the removal of snow and ice.
Some of the most important issues in this area of the law were recently reaffirmed by New York’s Appellate Division in Zamora v. David Caccavo, LLC, 190 A.D.3d 895 (2d Dept. 2021). In particular, that the Court of Appeals made clear in 2019 that the statutory non-delegable duty to remove snow and ice from sidewalks extends even to out-of-possession landowners, who, although they may shift the work of maintaining the sidewalk to another, "cannot shift the duty, nor exposure and liability for injuries caused by negligent maintenance, imposed under [Administrative Code §] 7-210." Xiang Fu He v. Troon Mgt., Inc., 34 N.Y.3d 167, 174 (2019). In other words, even if the defendant leases the property to a tenant who is obligated under the lease to maintain the property in every way, including snow and ice on sidewalks, the defendant cannot escape liability by claiming the tenant is solely responsible for the plaintiff’s loss. On the other hand, property owners are not strictly liable for all personal injuries that occur on the abutting sidewalks, because the statute "adopts a duty and standard of care that accords with traditional tort principles of negligence and causation." Xiang Fu He v. Troon Mgt., Inc., 34 N.Y.3d at 171.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
More Broad-Based Expansion for Construction Industry Expected in 2015
January 07, 2015 —
Garret Murai - California Construction Law BlogIt’s a short week for most of us this week.
Christmas is over and New Year’s is approaching.
So, what will 2015 bring us?
According Dodge Data & Analytics’s 2015 Dodge Construction Outlook: Continuing expansion of the construction sector, but one that is more broad-based than in recent years.
“The economic environment going forward carries several positives that will help to further lift total construction starts,” said Robert Murray, Chief Economist and Vice President at Dodge Data & Analytics. “Financing for construction projects is becoming more available, reflecting some easing of bank lending standards, a greater focus on real estate development by the investment community, and more construction bond measures getting passed. While federal funding for construction programs is still constrained, states are now picking up some of the slack. Interest rates for the near term should stay low, and market fundamentals (occupancies and rents) for commercial building and multifamily housing continue to strengthen.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Power Point Presentation on Nautilus v. Lexington Case
July 23, 2014 —
Tred R. Eyerly – Insurance Law HawaiiHere is our power point from today's presentation to the Hawaii State Bar Association's Litigation and Insurance Coverage Litigation sections. We discussed "other insurance" clauses as addressed by the Hawaii Supreme Court in Nautilus Ins. Co. v. Lexington Ins. Co., 132 Haw. 283, 321 P.3d 634 (2014).
Read the full story and view the Power Point presentation... Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Show Me the Money: The Good Faith Dispute Exception to Prompt Payment Penalties
March 13, 2023 —
Garret Murai - California Construction Law BlogCalifornia has a number of
prompt payment penalty statutes on the books. Among them is Civil Code section 8800 which requires project owners on private works projects to pay progress payments to direct contractors within 30 days after demand for payment pursuant to contract or be subject to prompt payment penalties of two percent (2%) per month on the amount wrongfully withheld. Like California’s other prompt payment penalty statutes, however, there is an important carve out: If there is a good faith dispute between the project owner and the direct contractor the project owner may withhold up to 150% of the dispute amount and not be subject to prompt payment penalties. And that, my friends, is a higher-tiered party’s “get out of jail free” card.
In a case of first impression, the 1st District Court of Appeals, in
Vought Construction Inc. v. Stock (2022) 84 Cal.App.5th 622, examined whether a project owner’s claim for liquidated damages constitutes a good faith dispute under Civil Code section 8800.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
The Choice Is Yours – Or Is It? Anti-Choice-of-Laws Statutes Applicable to Construction Contracts
October 03, 2022 —
Tiffany Raush & Tanya McGill - ConsensusDocsDuring contract negotiations and review, the parties make choices about what risks they are willing to accept and at what cost. But one often overlooked choice—the choice of law applicable to the contract—can undermine carefully negotiated construction contracts and expose contractors to risks they never intended to accept.
Choice-of-law provisions are standard provisions in most contracts. These provisions allow the parties to the contract to decide which state’s laws will apply to their contract. Often, choice-of-law in the construction contract is the law of the state where the project is located and there will be no issue. But, if the project is located in an unfamiliar, the owner or prime contractor may prefer the laws of the state where the owner or prime contractor is primarily located over the laws of the state where the project is located.
Generally, most states will enforce the parties’ choice of law in a contract. But that may not be the case for construction contracts. States like Texas, California, New York, Florida, Louisiana, and others may prohibit parties from agreeing to the application of another state’s law for construction projects in their states.
Reprinted courtesy of
Tiffany Raush, Jones Walker LLP (ConsensusDocs) and Tanya McGill, University of Mississippi School of Law Student, 2023 Graduate (ConsensusDocs)
Ms. Raush may be contacted at traush@joneswalker.com
Read the court decisionRead the full story...Reprinted courtesy of
Limitations: There is a Point of No Return
September 06, 2023 —
Amy Anderson - ConsensusDocsAfter nearly any event that causes inefficiency, delay, or extra cost on a project, there are some things you should always do: review the contract and document the inefficiency, delay, or cost. However, how you document the particular issue likely changes depending on what is in your contract, your position on the project, and the outcome you hope to reach. In reviewing the inefficiency, delay, or cost, one thing to always consider is how long you have to actually recoup damages you may incur if they were caused by another party on the project. In every jurisdiction (state or federal), there is likely to be some outer limit to when you can bring litigation or arbitration against an opposing party to recover damages another party causes to you. This is generally called a statute of limitations or statute of repose, although it goes by other names depending on your state.
The length of time will be specific to the locality. For example, in Texas, you have four years to bring a breach of contract claim but only two years to bring a negligence claim. Whether you fall under the two year or four year period may be highly fact intensive, depending on your claims. Do you have a contract directly with the party that is at fault? Is the claim based on your contract or some tort outside of the contract?
Read the court decisionRead the full story...Reprinted courtesy of
Amy Anderson, Jones Walker LLP (ConsensusDocs)Ms. Anderson may be contacted at
aanderson@joneswalker.com
Court of Appeals Upholds Default Judgment: Serves as Reminder to Respond to Lawsuits in a Timely Manner
October 02, 2023 —
Anna Basnaw - Ahlers Cressman & Sleight PLLCIn
Cyrus Way Partners, LLC. (“Cyrus”) v. Cadman, Inc. (“Cadman”), the primary issue on appeal was whether the trial court erred in denying Cadman’s motion to vacate the default judgment under Civil Rules 55 and 60. A default judgment is a legal ruling that can be entered in favor of the plaintiff when the defendant fails to respond to a lawsuit. If that happens, the court may resolve the lawsuit without hearing from the other side. In Washington, a party typically has 20 days to appear in a suit before being at risk for default judgment. If a default judgment is entered for the plaintiff, the defendant can move to vacate the default judgment, meaning the defendant hopes the court will set aside the default judgment as if it never happened. In this case, Cadman, the defendant, presents several ultimately unsuccessful arguments for why the default judgment in favor of Cyrus, the plaintiff, should be vacated.
Cyrus and Orca Beverage Inc. (“Orca”) are under common ownership. In 2018, Cyrus began a project to build a warehouse for Orca, which included the construction of a large concrete slab. Cadman was hired to supply the concrete. Cyrus hired Olympic Concrete Finishing Inc. (“Olympic”) to finish the concrete. On April 1, 2018, Cadman poured the concrete, and Olympic finished the slab. The next day, Cyrus noticed several problems with the slab, which experts hired by both Cyrus and Cadman opined were caused by an abnormally high air content in the concrete.
Read the court decisionRead the full story...Reprinted courtesy of
Ahlers Cressman & Sleight PLLC
No Jail Time for Disbarred Construction Defect Lawyer
May 10, 2013 —
CDJ STAFFThe New Mexico Supreme Court decided that a lawyer who defrauded clients will not be spending any time in jail, although they did disbar him in February. Bradley R. Sims brought a cashier’s check for $10,000 to repay his former client. Casa Bandera had hired Sims to sue over construction defects at apartment buildings it owned in Las Cruces, New Mexico. The court had found that Sims did not file the lawsuit but that created documents to convince his clients that he had.
Sims initially intended to repay Casa Bandera through monies owed him by Sundland Park, New Mexico. When that did not arrive at the court, Sims borrowed the money. He has yet to comply with a court order to turn over his client lists so that the disciplinary board can determine if he owes money to any other clients.