Background Owner of Property Cannot Be Compelled to Arbitrate Construction Defects
November 07, 2012 —
CDJ STAFFIn Truppi v. Pasco Engineering, John Quattro sued Property Management Contractors, Inc. over construction defects in William Truppi’s home. All parties are named in the suit. The California Court of Appeals ruled that Property Management Contractors, Inc. (PMCI) could not compel Mr. Quattro to arbitration.
The background of the case involves two houses built in Encinitas, California by PCMI: one for Mr. Truppi at 560 Neptune, and one for Mr. Quattro at 566 Neptune. Both contracts contained an arbitration provision. Mr. Quattro signed the contract for his residence and Mr. Truppi signed the other. Mr. Quattro then sued PCMI and its principal, William Gregory. Mr. Quattro claimed to be the true contracting party for the 560 Neptune residence and a third party beneficiary of the contract Mr. Truppi signed, and stated that PCMI was aware of this.
PCMI in a demurrer stated that Quattro “had only a ‘prospective beneficial interest in the property upon its eventual sale or lease.’” Mr. Quattro amended his complaint to account for the issues raised by PCMI. The court rejected PCMI’s demurrer to the amended complaint.
Finally, PCMI and Gregory asserted that Quattro was “not the real party in interest” and could not sue. PCMI continues to assert that Quattro lacks standing, but their attorney sent Quattro an e-mail stating, “While my client disputes that you are a party, and that you lack standing to assert the claim, to the extent you do so I believe you are obligated to proceed by way of arbitration.”
The court did not cover the issue of Quattro’s standing in the case, only if he could be compelled to arbitration. The court affirmed the lower court’s finding that Quattro could not be compelled to arbitrate the construction defect claim as neither he nor Gregory signed the contract in an individual capacity. Further, the court noted that PCMI and Gregory “denied the existence of an agreement between themselves and Quattro on the 560 contract,” and cannot compel arbitration on a non-existent agreement. And while non-signatories can, in some situations be compelled to arbitrate, the court found that “these cases are inapplicable because here they seek to have the alleged third party beneficiary (Quattro) compelled by a nonsignatory (Gregory).” The arbitration clause in question “expressly limited its application to persons or entities that signed the 560 contract.”
As Mr. Quattro was not a signatory to that agreement, the court found that he could not be held to its arbitration provision.
Read the court decisionRead the full story...Reprinted courtesy of
Get Creative to Solve Your Construction Company's Staffing Challenges
February 25, 2024 —
Kit Dickinson - Construction ExecutiveConstruction projects are on the rise due to a generational investment in infrastructure spending. The Infrastructure Investment and Jobs Act passed by Congress in August 2021 includes around $550 billion in new federal investment in America’s roads and bridges, water infrastructure and more to be allocated over the next five years.
Because of the influx of federal funds for infrastructure, construction firms that previously focused on local, private sector clients are incentivized to pursue public projects in other states and regions. There are a couple of bumps in the road, however. Payroll becomes more complex when you’re paying across multiple jurisdictions and at different pay rates, and reporting requirements for government work make managing projects and controlling costs trickier. Add to this the changes in the Davis-Bacon Act prevailing wage rules which went into effect on October 23, 2023. To capture this business and make it worthwhile, construction professionals need technology built specifically for the industry.
Reprinted courtesy of
Kit Dickinson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Executive Insights 2024: Leaders in Construction Law
August 05, 2024 —
Construction ExecutiveThe key risks that should always be taken into account when a contract is signed are risks associated with uncompensated delays and cost increases. Provisions relating to the scope of work deserve significant attention to help minimize these risks. Defining the scope of work is often put on the backburner while parties focus on negotiating the rest of the terms and conditions of the contract. And when these scopes are inserted, they are often not closely reviewed by attorneys who tend to defer to project personnel on scope. These situations can lead to costly disputes.
Instead, make sure: (1) the correct plans and specifications have been referenced in the contract; (2) an attorney or his/her business counterpart is familiar with relevant specifications; (3) the exhibit containing the assumptions and clarifications is clearly written, has been coordinated with language in the body of the contract and can be clearly understood by attorneys and business people beyond the preconstruction personnel who drafted them; and (4) the contract addresses the order of precedence in the event of a conflict between or among contract provisions (including exhibits). With regard to specifications referenced above, an attorney review is advised because many specification sections, including submittal sections, change order sections, payment provisions and construction progress documentation sections, regularly vary from the negotiated sections of the actual contract. Contractors also unwittingly accept design risk through performance specifications, and the accompanying obligations and risks are underestimated by those tasked with the initial review of those documents. In sum, a clear scope is as important as clear terms and conditions.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Developer’s Fraudulent Statements Are His Responsibility Alone in Construction Defect Case
February 10, 2012 —
CDJ STAFFThe Texas Court of Appeals ruled on December 21 in the case of Helm v Kingston, a construction defect case. After purchasing what was described as “an extremely well-built” two-bedroom townhouse, Mr. Kingston made complaints of construction defects. Greenway Development did not repair the defects to Kingston’s satisfaction, and he filed notice of suit. In his suit, he claimed that GDI and its president, John Helm, had committed fraud and negligent misrepresentation. Kingston claimed that Helm “fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of workmanship was atrocious.” Helms brought a counterclaim that Kingston’s suit was frivolous.
About four years after Kingston purchased the townhome, the suit proceeded to trial. The trial court determined that Helm was not “liable in his individual capacity,” but this was reversed at appeal.
A second trial was held ten years later on the question of whether Kingston’s unit was a townhome or an apartment. A jury found that Helm “engaged in a false, misleading or deceptive act or practice that Kingston relied on to his detriment.” Kingston was awarded $75,862.29 and an additional $95,000 in attorney fees by the jury. Helms made an unsuccessful appeal to the Appeals Court, after which Kingston was awarded an additional $10,000. Helms then made an unsuccessful appeal to the Texas Supreme Court, which lead to an additional $3,000 for Kingston. There was also a verdict of $48,770.09 in pre-judgment interest and “five percent post-judgment interest accruing from the date of the judgment until the time the judgment is paid. Helm appealed.
In his appeal, Helm raised seven issues, which the court reorganized into five Kingston raised one issue on cross-appeal.
Helms’ first claim was that Kingston “failed to satisfy the requirement of” Texas’s Residential Construction Liability Act and that by not filing under the RCLA, Kingston’s fraud and misrepresentation claims were preempted. Further Helms claimed that the RCLA limited Kingston’s damages. The court rejected this, as the RCLA deals with complaints made to a contractor and not only did Helm fail to “conclusively establish” his “status as a ‘contractor’ under the statutory definition,” Helm testified that he was “not a contactor” at the pre-trial hearing.
Helms’s second claim was that Kingston’s later claim of a misconstructed firewall should be barred, claiming that Kingston “‘had knowledge of a defect in the firewall’ as early as 1997 but did not assert them until 2007.” The court rejected this because Kingston’s claim was that “Helm ‘fraudulently induced Kingston to believe that the townhouse evidenced the highest quality of workmanship when in fact the quality of the workmanship was atrocious.’”
Helms also challenged whether his statements that the residence was of “good quality” constituted fraud and misrepresentation under Texas’s Deceptive Trade Practices-Consumer Protection Act. The court concluded that Helm was in a position to make knowledgeable statements and further that “residential housing units are not artistic works for which quality is inherently a matter of subjective judgment.” Helm also claimed that Kingston could have avoided certain repair expenses through the “exercise of reasonable care.” Helms argued that the repairs could have been made for $6,400. The court disagreed, as these claims were cited only to invoke the DTPA, and that later petitions established additional defects.
Helms’s next claim was that he was not allowed to designate responsible third parties. The court rejected this because there GDI represented matters concerning the residence only through Helm’s statements. The court noted that “Helm is correct that?third parties may be liable for fraud if they ‘participated in the fraudulent transactions and reaped the benefits,’” but they note that “Helm never specifically alleged that GDI or CREIC participated in Helm’s alleged fraudulent transactions.
The final issue in the decision was about court costs, and here the court denied claims on both sides. Helm argued that the award of legal fees were excessive, as they exceeded the actual damages. The court noted that they “may not substitute our judgment for that of the jury,” and also that “the ratio between the actual damages awarded and the attorney’s fees is not a factor that determines the reasonableness of the fees.” But the court also rejected Kingston’s claim for post-judgment interest on $10,312.30 that Helm had deposited in the trial court’s registry. The court noted that the monies were to be paid out upon final judgment, but the mandate did not include any reference to interest.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Court Slams the Privette Door on Independent Contractor’s Bodily Injury Claim
May 06, 2019 —
Brett G. Moore, Michael C. Parme, Lindsey N. Ursua & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPIn Johnson v. The Raytheon Company, Inc., Case No. B281411 (2019) WL 1090217, plaintiff Laurence Johnson (Johnson) was a maintenance engineer employed by an independent contractor that provided control room staff to defendant Raytheon Company, Inc. (“Raytheon”). Johnson was monitoring the computers in the control room when he received low water level alarms pertaining to the water cooling towers. Johnson went to the cooling tower wall in order to look over the wall and verify the water level. Johnson saw the upper half of an extension ladder leaning against the cooling tower’s wall. The ladder had a warning sign which said, “CAUTION” and “THIS LADDER SECTION IS NOT DESIGNED FOR SEPARATE USE.” Despite these warnings, Johnson used the ladder. As he was climbing the ladder it slid out causing him to fall and suffer injuries.
Johnson sued Raytheon, the hirer of the independent contractor, arguing the ladder, among other things, was unsafe and lead to Johnson’s injuries. Johnson believed that Raytheon’s course of conduct of leaving a platform ladder (as opposed to the extension ladder) at the wall constituted an implied agreement to always have one present, on which the independent contractor’s employees relied. Johnson further argued that Raytheon was negligent in providing a dangerous extension ladder, as opposed to a platform ladder, at the wall on the night of the accident.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Brett G. Moore,
Michael C. Parme,
Lindsey N. Ursua and
Lawrence S. Zucker II
Mr. Moore may be contacted at bmoore@hbblaw.com
Mr. Parme may be contacted at mparme@hbblaw.com
Ms. Lindsey may be contacted at lursua@hbblaw.com
Mr. Lawrence may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Business Risk Exclusions Bar Coverage for Construction Defect Claims
June 28, 2013 —
Tred EyerlyThe federal district court assumed there was "property damage" caused by an "occurrence," but found the business risk exclusions barred coverage for construction defect claims. Hubbell v. Carney Bros. Constr., 2013 U.S. Dist. LEXIS 68331 (D. Colo. May 13, 2013).
The plaintiffs entered a construction contract with the insured general contractor to build a home. After the project was one-third completed, plaintiffs terminated the contract. Experts hired by plaintiffs found a failure to properly site the residence, as the house was constructed 48 feet from the intended location; violations of county height restrictions; failure to follow building plans, which were themselves deficient; and an improperly poured foundation. The experts estimated that the costs of repairing the property to be between $1.3 and $1.5 million, and that the cost of demolishing the structure and rebuilding it would be between $1.1 and $1.3 million.
After plaintiff filed suit, a stipulated judgment of $1.952 million was entered.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Nevada Construction Defect Lawyers Dead in Possible Suicides
March 28, 2012 —
CDJ STAFFA number of news sources have reported on the recent death of Nevada construction defect attorney, Nancy Quon. Ms. Quon was implicated in a recent scandal in which a group conspired to control homeowner associations in order to divert construction defect lawsuits to the members of the conspiracy.
Ms. Quon was found dead in her bathtub. The details are still under investigations. She and her boyfriend were accused of a failed arson/suicide scheme in 2010. Ms. Quon survived an attempt to burn down her home. Subsequently, her boyfriend obtained some gamma-hydroxybutyric acid (GBH) for her, as part of another failed suicide attempt.
Subsequent to Ms. Quon’s death, David Amesbury was found in California dead by hanging. Mr. Amesbury took a plea deal in the case, and he had admitted his role in providing legal and construction contracts to firms in the conspiracy. He was accused of fixing HOA elections.
Read the full story…
Read the full story…
Read the full story…
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Court Orders House to be Demolished or Relocated
April 26, 2011 —
Beverley BevenFlorezCDJ STAFFDecision Affirmed in Central Arkansas Foundation Homes, LLC v. Rebecca Choate
The Arkansas Court of Appeals affirmed the decision by the trial court in Central Arkansas Foundation Homes, LLC v. Rebecca Choate. In the trial case, Central Arkansas Foundation Homes (CAFH) sought payment for a home built for Choate, while Choate alleged that the builders committed multiple construction defects including using the wrong foundation materials and positioning the house in the wrong direction.
After the house was built, CAFH contacted Choate regarding payment, however, Choate alleged that the finished product did not match the contract. “ After CAFH completed construction, it obtained permanent home financing for Choate and tried to contact her to close the transaction. Choate did not respond until October 2005, when she sent CAFH a list of alleged construction defects, including that the house was facing in the wrong direction; that it was not built on a slab; and that the fireplace, garbage disposal, driveway, and storage area were missing. CAFH replied to Choate in writing, telling her that she had until January 6, 2006, to close on the house or CAFH would sell it. The correspondence enclosed worksheets showing that the amount Choate would owe at closing exceeded $94,000, which included interest that had accrued on the as-yet unpaid construction loan.”
Initially, the court found in favor of CAFH. “On April 18, 2007, Choate’s attorney withdrew from representing her. Soon thereafter, CAFH’s attorney asked the court to set a final hearing on the case. The attorney purportedly sent Choate a letter by regular mail on May 15, 2007, advising her that the case was set for trial on July 9, 2007. Choate, however, did not appear. CAFH did appear, and its general manager, John Oldner, testified to events leading up to the case and the amount of damages claimed. According to Oldner, the interest on the construction loan had accrued to the point that CAFH now sought $104,965.88 from Choate. The court found in favor of CAFH and entered judgment for that amount, plus attorney fees, on July 18, 2007. The court ruled that CAFH could sell the house and either remit any excess to Choate or look to Choate for the deficiency if the sales price did not cover the judgment.”
However, Choate successfully argued that she did not receive notice of the trial. A new trial was ordered, and the outcome was quite different. “On June 6, 2008, the circuit court entered judgment for Choate, ruling that the house was not in substantial compliance with the parties’ contract and that the contract should be rescinded. The court found that the house suffered from numerous construction defects, that the contract contemplated a slab rather than a concrete-pier foundation, and that CAFH ignored Choate’s complaints that the house was facing the wrong way. The judgment directed CAFH to hold Choate harmless on the construction loan, to deed Choate’s two acres back to her, and to remove the house from Choate’s property.”
The Court of Appeals “found that Choate would be unjustly enriched by retaining the benefit of the septic systems and utility lines that CAFH installed on her land. The court therefore awarded $5340 to CAFH as a quantum-meruit recovery for the value of that work. CAFH contends that the award is not sufficient, but we see no clear error.” In the end, the Court of Appeals provided this reason for declining to reverse the trial court’s decision: “The court in this case apparently concluded that the house constructed by CAFH was so fundamentally at odds with Choate’s contractual expectations that she was not unjustly enriched and should simply be, as nearly as possible, returned to the status quo ante. Accordingly, the court ordered the house removed from her property and permitted CAFH to either relocate the house or salvage the house’s materials and unused appliances. We decline to reverse the court’s weighing of the equities in this manner.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of