Contractor Not Liable for Flooding House
October 02, 2013 —
CDJ STAFFKnife River Corp was hired by the town of Post Falls, Idaho to do road and sewer construction work. In the process, they interrupted a 6-inch water supply line, sending the water into a wastewater line. From there, the water flooded a home in Post Fall. The city paid more than $7,800 in damages.
Post Falls sued Knife River’s insurer for coverage. The city has lost its lawsuit and is responsible for $18,500 in attorneys’ fees. Despite all this, the city administrator says that the city still has a good working relationship with Knife River.
Read the court decisionRead the full story...Reprinted courtesy of
Traub Lieberman Partner Lisa M. Rolle Wins Summary Judgment in Favor of Third-Party Defendant
May 06, 2024 —
Traub LiebermanTraub Lieberman Partner Lisa M. Rolle won summary judgment in favor of Third-Party Defendant, a general contracting company (the “Contracting Company”), in a personal injury action brought in Suffolk County. In the underlying matter, the Plaintiff—an employee of the Contracting Company—alleged that they sustained injuries from an incident which occurred when they were struck by a skid-steer loader owned by the Co-Defendant masonry company (the “Masonry Company”) and operated by the president and owner of the Co-Defendant/Third-Party Plaintiff construction company (the “Construction Company”). The Plaintiff brought claims against the Defendant companies for common law negligence and violations of Labor Law § § 200, 240, and 241, as well as Industrial code (12 NYCRR) subpart 23-2.
Reprinted courtesy of
Lisa Rolle, Traub Lieberman
Ms. Rolle may be contacted at lrolle@tlsslaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Second Circuit Certifies Question Impacting "Bellefonte Rule"
December 15, 2016 —
Ellen Burrows – White and Williams LLPCalling into question the continued validity of the so-called “Bellefonte Rule,” on December 8, 2016, the United States Court of Appeals for the Second Circuit certified to the New York Court of Appeals the question whether a facultative reinsurance contract limit is presumptively all-inclusive and “caps” the reinsurer’s total exposure even where the reinsured policy pays defense costs in addition to the limit. Global Reinsurance Corporation v. Century Indemnity Company Docket No. 15-2164-cv (December 8, 2016).[1]
In Bellefonte Reinsurance Company v. Aetna 903 F.2d 910 (2d Cir. 1990), the court ruled that a reinsurer was not liable to pay defense costs above the stated reinsurance contract limit. Although litigants argued that this ruling was dependent on the fact that the reinsured policy limits were defense cost-inclusive, a later panel of the Second Circuit applied the “cap” ruling in Bellefonte to a situation where the reinsured policy limit was not cost-inclusive and where the insurer was obligated to pay defense costs in addition to the policy limit. Unigard Security Insurance Company v. North River Insurance Company 4 F.3d 1049 (2d Cir. 1993).
Read the court decisionRead the full story...Reprinted courtesy of
Ellen Burrows, White and Williams LLPMs. Burrows may be contacted at
burrowse@whiteandwilliams.com
The Importance of a Notice of Completion to Contractors, Subcontractors and Suppliers
August 12, 2024 —
William L. Porter - Porter Law GroupThe recording of a valid “Notice of Completion” with the County Recorder is an event of significance to owners, contractors, subcontractors and suppliers alike. The recording of a Notice of Completion is one of several methods used to trigger the time period for the recording of mechanics liens and service of stop payment notices. Although the recording of a Notice of Completion is not absolutely required on any given project, all those working in the construction industry should understand its significance.
When a valid Notice of Completion has not been recorded in relation to a construction project, a contractor, subcontractor, or supplier might from ninety to one hundred fifty days after completion of the project to record a mechanics lien or serve a stop payment notice to secure payment for their services on the project, depending on the facts. However, if a valid Notice of Completion is recorded, then the deadline under most circumstances accelerates and subcontractors and suppliers must record a mechanics lien or serve a stop payment notice within only thirty days thereafter. Under the same circumstances, a prime contractor has only sixty days after the recording of a valid Notice of Completion to record a mechanics’ lien. Failure to meet these deadlines often results in loss of the right to a mechanics lien or stop payment notice. There are limited exceptions to these general deadlines, depending on the facts. If you believe you may have missed an important deadline to seek collection of a construction debt, you should consult with a construction attorney immediately to secure your avenues of collection, including the mechanics lien and stop payment notice remedies, if still available.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
BOOK CLUB SERIES: Everything You Want to Know About Construction Arbitration But Were Afraid to Ask
October 30, 2023 —
Marissa L. Downs - The Dispute ResolverI recently had the pleasure of speaking with construction law notables John Foust and Andy Ness to discuss the release of their new book—
Construction Arbitration: The Advocate’s Practical Guide. The goal of their book: to teach attorneys what they need to know to maximize their effectiveness in the arbitration context. To that end, the book covers every aspect of the arbitration process including motion practice, conduct as an advocate, presentation of the case, and post-hearing submissions. Read on for Andy and John’s candid, behind-the-scenes take on how this book came to be and why you should get your copy now, while supplies last!
Q: Who is the target audience for this book?
Andy: In the editing process (and in writing my own chapter on Navigating an International Construction Arbitration) I pretended that I was speaking with a construction lawyer who was a few years out of law school, with some litigation experience, who was getting ready to take on a significant and complex construction arbitration for the first time. The book presupposes knowledge of the basics and tries to anticipate the questions that would be asked when you are trying to think through the whole arbitration process from start to finish. What should my pleadings look like? How much discovery am I likely to be able to obtain? How should my demeanor be different from what I would do in a courtroom? How much should I object during the hearing? In a nutshell, it’s “What do I need to know to maximize my chances of success in the arbitration setting?”
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Professional Services Exclusion Bars Coverage After Carbon Monoxide Leak
September 09, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe Illinois Appellate Court affirmed the trial court's dismissal of the insured's complaint after damage caused by a leak of carbon monoxide caused bodily injury. Allied Design Consultants, Inc. v. Pekin Ins. Co., et al., 2024 Ill. Ct. App. LEXIS 1433 (June 18, 2024).
Carbon monoxide leaked in a building addition to a middle school, prompting 23 lawsuits to be filed against the insured, Allied Design Consultants, Inc. Allied was retained to perform certain architectural services to the building addition. Pekin Insurance Company had issued a business owners liability policy and a commercial umbrella liability policy to Allied. Pekin denied a defense to Allied based upon the policies' professional services exclusions.
Allied filed suit for declaratory relief against Pekin. Pekin filed a counterclaim, seeking a declaratory judgment that it had no duty to defend. The parties filed cross-motions for summary judgment. The parties agreed the allegations in the personal injury complaint filed by Ferguson were typical and representative of the allegations in the other 22 underlying lawsuits.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Supreme Court Adopts Vertical Exhaustion for Long-Tail Claims
June 15, 2020 —
Tred R. Eyerly - Insurance Law HawaiiIn another round of litigation involving coverage issues between Montrose Chemical Corporation and its insurers, the California Supreme Court ruled in favor of Montrose, adopting vertical exhaustion of excess policies. Montrose Chem. Corp. of Calif. v. The Superior Court of Los Angeles County, 9 Ca. 5th 215 (2020).
In 1990, the United States and the State of California sued Montrose for contamination from 1947 to 1982 caused by Montrose's facility manufacturing insecticides. Montrose had primary and excess liability policies from defendant insurers between 1961 and 1985. Forty insurers collectively issued more than 115 excess policies, which collectively provided coverage sufficient to indemnify Montrose's anticipate total liability.
Primary coverage was exhausted. Each excess policy provided that Montrose had to exhaust the limits of its underlying coverage before there would be excess coverage. Which excess carrier could be called on first was the issued before the California Supreme Court.
Montrose proposed a rule of "vertical exhaustion" or "elective stacking," whereby it could access any excess policy once it exhausted other policies with lower attachment points in the same policy period. The insurers, in contract, argued for "horizontal exhaustion," whereby Montrose could access an excess policy only after it exhausted other policies with lower attachment points from every policy period in which the environmental damage resulting in liability occurred.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Wilke Fleury Attorneys Featured in 2021 Best Lawyers in America and Best Lawyers: Ones To Watch!
September 28, 2020 —
Wilke Fleury LLPWilke Fleury congratulates attorneys
David Frenznick,
Adriana Cervantes and
Dan Egan on their inclusion in the 2021 Edition of Best Lawyers in America!
Since it was first published in 1983, Best Lawyers® has become universally regarded as the definitive guide to legal excellence. Best Lawyers lists are compiled based on an exhaustive peer-review evaluation. Almost 108,000 industry leading lawyers are eligible to vote (from around the world), and they have received over 13 million evaluations on the legal abilities of other lawyers based on their specific practice areas around the world. For the 2021 Edition of The Best Lawyers in America©, 9.4 million votes were analyzed.
Read the court decisionRead the full story...Reprinted courtesy of
Wilke Fleury