Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Repeated Use of Defective Fireplace Triggers Duty to Defend Even if Active Fire Does Not Break Out Until After End of Policy Period
November 30, 2016 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Tidwell Enterprises v. Financial Pacific Ins. Co. (No. C078665, filed 11/29/16), a California appeals court held that that even though a house fire occurred after the policy period, there was nonetheless a possibility of coverage because the fire might have been the result of ongoing damage to the wood in the chimney chase during the policy period, due to the exposure of that wood to excessive heat from the chimney every time a fire was burned in the fireplace.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Home Building Mergers and Acquisitions 2014 Predictions
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFJohn McManus, writing for Big Builder, discusses the various predictions for mergers and acquisitions in the home building field for 2014. While predictions vary between individuals, it seems to hover between 15 and 30.
McManus lists several home building seller motivations, such as a “[n]eed for cash infusion to buy and develop new lot pipeline” and “[s]uccession planning.”
Finally, McManus points out that not every merger and acquisition discussion will lead to a deal: “We've recently seen a combination or three flounder on the issue of price. This occurs partly as the home builder buyer community becomes more discriminating as to what truly fits their program, and partly as smaller builders attain options as regional and national lenders awaken and look to reenter project financing in a bigger way.”
Read the court decisionRead the full story...Reprinted courtesy of
More (and Simpler) Options Under New Oregon Retention Law
October 21, 2024 —
Michael Yelle - Ahlers Cressman & Sleight PLLCSimilar to the changes made by the Washington Legislature last year, the Oregon Legislature recently changed its retention law. Oregon public works agencies and large commercial project owners are now required to accept surety bonds in lieu of withholding retainage on construction projects. There is also no longer a requirement to deposit retention funds in an interest-bearing escrow account.
The owner or public agency must accept the bond in lieu of retainage unless specific grounds exist. For example, public agencies must find there is “good cause” for rejection of the bond based on the “unique project circumstances. Private owners have less discretion to reject a bond and if the bond meets the statutory requirements, per ORS 701.435(1)(a) “the owner and lender shall accept” the bond “in lieu of all or any portion of the retainage…”
Courts have not analyzed when “good cause” exists for public agencies to reject bonds or exactly what will allow a private owner to reject a bond. However, an agency or owner cannot have a general policy to reject retention bonds. The statute does not provide next steps if the contractor disagrees with a decision to reject the bond. It may be necessary to proceed under the contract’s dispute resolution procedure or it may be more appropriate to take the issue directly to the courts.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Yelle, Ahlers Cressman & Sleight PLLCMr. Yelle may be contacted at
michael.yelle@acslawyers.com
Urban Retrofits, Tall Buildings, and Sustainability
January 14, 2025 —
Christopher G. Hill - Construction Law MusingsAs I took a small break between cases and contract reviews, an article in the November 2, 2009 issue of ENR Magazine caught my eye. The article discusses the efforts of a Chicago architect to create a holistic approach to the renovation and “de-carbonization” of the Chicago Loop area. The plan involves large scale energy retrofits and sustainable reuse of Chicago’s tall buildings.
Another interesting aspect of this article points out that tall buildings in general have hit the construction skids in the US and Latin America, this is not the case in Europe and the Middle East. However, those buildings that are going up (and up and up) are trying to go “green.” Several of the worlds tallest buildings, or soon to be so, are seeking LEED gold or platinum certification.
These two trends, in my view, are healthy. First of all, much like the goal of Build2Sustain, the Chicago effort is a move toward sustainable reuse and retrofit/renovation. I see this as a great trend and a way to perform the “Three R’s” (Reduce, Reuse, Recycle), by reusing existing building materials and footprints without the cost and use of newer materials from tear downs and rebuilds.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Don’t Put All Your Eggs in the Silent-Cyber Basket
August 07, 2022 —
William P. Sowers, Jr. & Michael S. Levine - Hunton Insurance Recovery BlogThe Eastern District of Pennsylvania recently gave another reminder why cyber insurance should be part of any comprehensive insurance portfolio. In Construction Financial Administration Services, LLC v. Federal Insurance Company, No. 19-0020 (E.D. Pa. June 9, 2022), the court rejected a policyholder’s attempt to find coverage under its professional liability insurance for a social engineering incident that defrauded over $1 million.
Construction Financial Administrative Services, which goes by CFAS, disburses funds to contractors. One of its clients, SWF Constructors, was hacked, and a bad actor posing as the client asked CFAS to distribute $600,000 to a sham third party. John Follmer, an executive at CFAS and the only person authorized to approve distribution of funds, approved it. The next day, the bad actor, again posing as the client, asked Follmer to transfer an additional $700,000. Follmer approved that distribution too.
Reprinted courtesy of
William P. Sowers, Jr., Hunton Andrews Kurth and
Michael S. Levine, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Infrastructure Money Comes With Labor Law Strings Attached
July 25, 2022 —
Cheryl Behymer, Patrick M. Dalin & Collin Cook - Construction ExecutiveThe federal government has committed to spending $1 trillion under the Infrastructure Investment and Jobs Act on nationwide construction, alteration and repair projects. Billions of dollars have already been deployed on projects to improve highways, bridges, airports, electrical infrastructure and drinking water distribution, and the government is poised to spend the remaining funds on a massive infrastructure build-out over the next five years. While federal government contracts may provide a lucrative and reliable stream of revenue for construction companies, contractors must be prepared to comply with special requirements, particularly under the labor and employment laws enforced by the U.S. Department of Labor (USDOL).
1. The Davis Bacon Act Requires Payment of Prevailing Wages and Fringe Benefits
The Davis Bacon Act (DBA) applies to most federally funded and federally assisted projects for construction, alteration or repair work. This law requires all contractors and subcontractors on a covered project to pay all “laborers or mechanics” the wages and fringe benefits that “prevail” in the locality where the work is being performed. The USDOL determines what the prevailing wages and fringe benefits are for each trade and publishes them in wage determinations that should be issued to all contractors on the project.
Reprinted courtesy of
Cheryl Behymer, Patrick M. Dalin & Collin Cook, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Sometimes a Reminder is in Order. . .
June 21, 2021 —
Christopher G. Hill - Construction Law MusingsRecently, I was talking with my friend Matt Hundley about a recent case he had in the Charlottesville, VA Circuit Court. It was a relatively straightforward (or so he and I would have thought) breach of contract matter involving a fixed price contract between his (and an associate of his Laura Hooe) client James River Stucco and the Montecello Overlook Owners’ Association. I believe that you will see the reason for the title of the post once you hear the facts and read the opinion.
In James River Stucco, Inc. v. Monticello Overlook Owners’ Ass’n, the Court considered Janes River Stucco’s Motion for Summary Judgment countering two arguments made by the Association. The first Association argument was that the word “employ” in the contract meant that James River Stucco was required to use its own forces (as opposed to subcontractors) to perform the work. The second argument was that James River overcharged for the work. This second argument was made without any allegation of fraud or that the work was not 100% performed.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at