The Importance of Preliminary Notices on Private Works Projects
September 03, 2019 —
William L. Porter - Porter Law GroupTime and time again I receive calls from subcontractors and suppliers who find themselves faced with a customer who is either unwilling or unable to pay for labor or materials supplied for a private works project. As an attorney, the first question I usually ask is “did you serve a Preliminary Notice?” The second question I usually ask is “did you serve the Notice within twenty (20) days after first furnishing labor, service, equipment or materials to the job site?” The answers to these questions will often determine the ability to collect on the claim.
The excuses for failing to serve the Preliminary Notice range from “for the last ten years the customer has always paid on time” to “I didn’t want to imply the contractor was not going to pay me” to “it is too much trouble to do on every job” or, simply, “I forgot”. Contractors and suppliers are well advised that any subcontractor or supplier who fails to properly and timely serve a Preliminary Notice is depriving itself of the most powerful tool available for compelling payment of construction related debt on a private works project. For all but the smallest contracts failure to serve the Preliminary Notice is also a violation of contractors’ license law and constitutes grounds for discipline by the Contractor State License Board, up to and including suspension of the contractor’s license.
Most of these rules are found in California Civil Code Section 8200-8216. The requirements of these sections are far too numerous to itemize here. Suffice it to say every contractor, subcontractor and construction material supplier to private construction projects should be familiar with these sections of the California Civil Code. They set forth most of the rules which relate to Preliminary Notices on private construction projects. Some of the most important features are as follows:
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Drought Dogs Developers in California's Soaring Housing Market
September 17, 2015 —
John Gittelsohn – BloombergCalifornia’s already tight housing market is facing another long-term complication: drought.
The state’s dry spell is creating challenges for developers at a time when home prices are soaring because of limited inventory. The metropolitan areas of San Jose, San Francisco and San Diego had the nation’s biggest gap between the number of new jobs and residential building permits from 2012 to 2014, according to a report Wednesday by the National Association of Realtors. Now the drought, into its fourth year, stands to curb affordability further.
“It’s contributing to price appreciation by restricting supply,” said Mark Boud, founder of Real Estate Economics, a housing-consulting firm based in Irvine, California.
Read the court decisionRead the full story...Reprinted courtesy of
John Gittelsohn, Bloomberg
Appreciate The Risks You Are Assuming In Your Contract
February 10, 2020 —
David Adelstein - Florida Construction Legal UpdatesAPPRECIATE THE RISKS YOU ARE ASSUMING IN YOUR CONTRACT. Otherwise, those risks will come back and bite you in the butt. This language is not capitalized for naught. Regardless of the type of contract you are entering into, there are risks you will be assuming. You need to appreciate those risks because there may be insurance you can obtain to cover that risk.
For instance, exculpatory provisions (or get-out-of-jail provisions) in contracts are enforceable if they are unambiguous. “Such provisions are deemed to be unambiguous and enforceable when the language unequivocally demonstrates a clear and understandable intention for the defendant to be relieved from liability such that an ordinary and knowledgeable person will know what he or she is contracting away.” Pillay v. Public Storage, Inc., 44 Fla.L.Weekly D2744c (Fla. 4th DCA 2019).
An example of an exculpatory provision can be found in the public storage rental contract found in Pillay that read:
(1) ALL PERSONAL PROPERTY IS STORED BY OCCUPANT AT OCCUPANT’S SOLE RISK.
(2) Owner and Owner’s agents . . . will not be responsible for, and Tenant releases Owner and Owner’s agents from any responsibility for, any loss, liability, claim, expense, damage to property . . . including without limitation any Loss arising from the active or passive acts, omission or negligence of Owner or Owner’s agents.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
New York Court Holds Insurer Can Recover Before Insured Is Made Whole
October 24, 2023 —
Gus Sara - The Subrogation StrategistIn State Farm Fire & Cas. Co. v. Tamagawa, Index No. 510977/2021, 2023 N.Y. Misc. Lexis 5434, the Supreme Court of New York considered whether an insurance carrier can settle its property subrogation lawsuit with the defendant, and discontinue the lawsuit, while the carrier’s insured still had pending claims with the carrier and claims for uninsured losses against the defendant. The court held that the carrier’s claims for the amount paid are divisible and independent of the insured’s claims and that the carrier’s settlement did not affect the insured’s right to sue for any unreimbursed losses. The court’s decision reminds us that, in New York, a carrier can resolve its subrogation claim before the insured is made whole.
In June 2018, a water loss occurred in an apartment owned by Malik Graves-Pryor (Graves-Pryor). Graves-Pryor reported a claim to his property insurance carrier, State Farm Fire & Casualty Company (Carrier). Investigation into the water loss revealed that the water originated from failed plumbing pipes in another apartment unit owned by Taku Tamagawa (Tamagawa). Carrier paid its insured over $600,000 for repairs. In May 2021, Carrier filed a subrogation lawsuit against Tamagawa, alleging improper maintenance of the plumbing pipes.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Classify Workers Properly to Avoid Expensive Penalties
April 25, 2022 —
Martin C. McCarthy - Construction ExecutiveBusiness owners must carefully consider how the people working for them are classified. There is a fine line between being identified as a contractor or employee on the job. Owners must know the difference to avoid being penalized.
Worker classification determines if an employer must withhold income taxes and pay Social Security, Medicare taxes and unemployment tax on wages paid to an employee. Businesses do not have to withhold or pay any taxes on payments to independent contractors. The earnings of a person working as an independent contractor are subject to self-employment tax.
There are federal and state rules for determining if a person is an employee or contractor. Employers must follow both sets of guidelines when classifying workers.
Reprinted courtesy of
Martin C. McCarthy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. McCarthy may be contacted at marty.mccarthy@mcc-cpas.com
Read the court decisionRead the full story...Reprinted courtesy of
Residential Contractors, Be Sure to Have these Clauses in Your Contracts
May 16, 2018 —
Christopher G. Hill - Construction Law MusingsI have often “mused” on the need to have a good solid construction contract at the beginning of a project. While this is always true, it is particularly true in residential contracting where a homeowner may or may not know the construction process or have experience with large scale construction. Often you, as a construction general contractor, are providing the first large scale construction that the homeowner has experienced. For this reason, through meetings and the construction contract, setting expectations early and often is key.
As a side note to this need to set expectations, the Virginia Department of Professional and Occupational Regulation (DPOR) and the Virginia General Assembly require certain clauses to be in every residential construction contract. DPOR strictly enforces these contractual items and failure to put them in your contracts can lead to fines, penalties and possibly even revocation of a contractor’s license.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Revisiting the CMO; Are We Overusing the Mediation Privilege?
November 19, 2021 —
Michael T. Kennedy Jr. - BERDING|WEILOne of the most common features in construction defect cases is the Case Management Order (“CMO”) or Pre-Trial Order (“PTO”) to govern pre-trial and mediation procedures. CMOs and PTOs arose in the days when the HOA would sue the developer, the developer would cross-complaint against the subcontractors, and each defendant and cross-defendant might have 2 or 3 insurance carriers defending, each of whom may retain their own panel counsel. In a large case there may have been 20 parties and 30 defense attorneys. In order to avoid the cost and chaos of all of those parties propounding their own discovery, and in order to prepare these cases for mediation well before trial and the associated costs, it became standard practice in California to include provisions in the CMO to stay all discovery until just before trial.
Plaintiff would provide a Defect List or Statement of Claims and the parties experts would meet and exchange information as part of the mediation process. All of the information exchanged would be subject to mediation privileges and inadmissible at trial. The benefit of this practice was that the parties (and carriers) would avoid the cost of formal discovery and allow the experts to discuss compromised scopes of repair to help settle the case while being able to take a more aggressive position at trial. The disadvantages are that each party uses its privileged initial expert reports to stake out negotiating positions more extreme than what they would put on at trial, with each side losing credibility with the other in assessing the value of the case, and for those cases that did not settle, the parties would be faced with having to do all of the depositions and discovery in the last 60 days, or delaying trial, or both.
Over the last 10 or 15 years with the advent of wrap-up insurance policies, these cases now usually involve 2 sides instead of 20; only the HOA and the developer remain in the case. However, old habits die hard, and the standard CMO/PTO hasn’t evolved with other aspects of these cases. The practice of staying all discovery and exchanging information only under mediation privileges remains, and as a result insurance carriers don’t receive the admissible evidence that they need to determine coverage and evaluate the real settlement value of the case until just before trial. On the plaintiff’s side, if most of the experts’ work is done under the guise of mediation privilege, those costs may not be recoverable. Outside the context of mediation, costs incurred in investigation of the defects and preparation of a scope and cost of repair are recoverable.
This reflexive claim of mediation privilege over all information exchanged during the case has outlived its usefulness. The CMO can and should remain to regulate formal discovery and to help the parties prepare for mediation, but regulated discovery should be opened early in the case. In California, the SB800 process already provides for the exchange of admissible information during the prelitigation right to repair process. Continuing that exchange during the early litigation allows the parties to continue to prepare for mediation, but waiving privileges had advantages for both sides.
A senior claims manager once commented that Plaintiff’s mediation-protected Statement of Claims “might as well be a stack of blank paper” for all of its usefulness to the carrier in assessing the value of the case. If the Plaintiff and it expects are free to inflate their claims early in the case without having to worry about every supporting those claims in front of a jury, they have little or no credibility. And if those claims are inflated or not “real,” not only can the carrier not properly assess the verdict range and settlement value of the case, but it may also be hampered in making a coverage determination. Simply put, if the exchange of real information through formal discovery is put off until just before trial, the defense cannot be ready to settle until then. Worse, the cost of defense goes through the roof in the last 60 days before trial as the lawyers’ scramble to take all of the depositions and to all of the other work that had been stayed for the previous year or two.
The Plaintiff is faced with the same question of credibility of defense experts where they are free to take a “low ball” negotiating position without having to support that position through cross-examination in front of the jury. Just as the carrier behind the defense attorney needs the Plaintiff’s “real” evidence to assess the claim, so does the HIOA Board of Directors behind the Plaintiff’s counsel. Additionally, in California as in most states, the cost of experts’ preparation for mediation may not be recoverable as costs or damages, but investigation of the defects and preparation of the scope and cost of repair is recoverable.
The biggest challenge is resolving construction defect claims for both sides is how to resolve these cases quickly while keeping costs under control. Practices that worked 20 years ago are no longer applicable with changes in insurance, and in light of some of the bad habits that arise when all of the information exchanged was confidential.
The CMO/PTO process can still be useful to regulate the discovery and mediation schedule given the volume of documents and other information to be exchanged but exchanging “real” information in a form that may come into evidence at trial should foster earlier resolution, resulting in cost savings for the parties. The CMO can provide for the parties to respond to controlled discovery, and the exchange of expert reports and potentially depositions can and should be done earlier in the case, well before the eve of trial. The parties can then assess the true value of each case and prepare for more substantive mediation without waiting until they are on the figurative courthouse steps.
Construction defect cases have a pattern, and it is tempting for busy lawyers to just put each case through the same algorithms that they have used for years. However, these cases have evolved and those of us handling these cases need to reevaluate our approach to these cases. Taking aggressive negotiating positions that no longer have any credibility with the other side has become counterproductive, and the exchange of real evidence earlier in the case would better serve our clients and carriers.
BERDING|WEIL is the largest and most experienced construction defect and common interest development law firm in California. For more information, please visit https://www.berding-weil.com
Read the court decisionRead the full story...Reprinted courtesy of
Michael T. Kennedy Jr., BERDING|WEILMr. Kennedy may be contacted at
mkennedy@berdingweil.com
Failure to Timely File Suit in Federal Court for Flood Loss is Fatal
June 29, 2017 —
Tred R. Eyerly - Insurance Law HawaiiAlthough the insureds timely filed their suit for denial of flood benefits in state court, the Fourth Circuit found the lawsuit against the Insurer was untimely because it was not filed in federal district court. Woodson v. Allstate Ins. Co., 2017 U. S. App. LEXIS 7862 (4th Cir. May 3 , 2917).
Hurricane Irene struck the insureds' house in August 27, 2011. Their property was flooded and for several hours, subjected to wave action, allegedly causing further damage to the home. The insureds contacted Allstate, who retained Rimkus Consulting Group, Inc. to inspect the property. Rimkus found that, other than a substantial loss of soil washed away around the supporting portion of the house, there was no damage to the structure of the house. Rimkus recommended reimbursement of $1200 for the washed out soil.
The insureds retained House Engineering, P.C., which submitted a report describing substantial damage caused by the hurricane, including movement to the pilings that caused the house to no longer be level. The insureds claimed $228,822 in damages.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com