Hurricane Laura: Implications for Insurers in Louisiana
October 19, 2020 —
Jennifer Michel & Tabitha Durbin - Lewis BrisboisJust two days before the 15th Anniversary of Hurricane Katrina, Category 4 Hurricane Laura made landfall near Cameron, Louisiana. Although the “unsurvivable” 20-foot storm surge, which had been predicted ahead of the storm, thankfully was significantly less, the impact of Laura on the Southwest Coast of Louisiana and Southeast Coast of Texas and its neighboring parishes and counties, most notably Cameron Parish, was quite severe. Lake Charles, Louisiana suffered widespread flooding and sustained catastrophic wind damage. Although the storm moved quickly, it retained its strength longer than expected such that even areas well inland sustained considerable damage. Preliminary estimates for insured losses from storm surge, flooding, and winds range from $8 to $12 billion for residential and commercial properties. Insurers providing residential or commercial property insurance in Louisiana should keep the following statutory claims handling requirements in mind.
Louisiana Statutory Provisions
Under Louisiana law, an insurer is expected to comply with certain statutory requirements in investigating and handling claims submitted by its insureds and third-party claimants. The majority of these requirements, and the consequences of their violation, are codified by La. R.S. 22:1892, which governs the payment and adjustment of claims, and La. R.S. 22:1973, which delineates an insurer’s duty of good faith. Together, the statutes impose three requirements on insurers: timely initiation of loss adjustment, timely payment of claims, and a duty of good faith and fairness in the adjustment and payment of said claims.
Reprinted courtesy of
Jennifer Michel, Lewis Brisbois and
Tabitha Durbin, Lewis Brisbois
Ms. Michel may be contacted at Jenny.Michel@lewisbrisbois.com
Ms. Durbin may be contacted at Tabitha.Durbin@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Virginia Decision Emphasizes Importance of Naming All Necessary Parties
June 17, 2015 —
Beverley BevenFlorez-CDJ STAFFNate Budde on the Construction Payment Blog, discussed the potential of mechanics liens, and the pitfalls that occur when not all necessary parties are named. Budde analyzed the case Johnson Controls Inc. v. Norair Eng’g Corp. that involved a “claimant’s failure to name all the necessary parties in his claim against a bond,” resulting “in the claimant losing his claim against the bond, and with it, an opportunity to get paid.”
Budde concluded, “Unfortunately, as was the case here, when the bond claim is not handled correctly procedurally, a party can be left with no recourse for payment. It’s important to understand which of the parties involved should be named in both mechanics lien claims and bond claims.”
Read the court decisionRead the full story...Reprinted courtesy of
The U.S. Flooded One of Houston’s Richest Neighborhoods to Save Everyone Else
December 01, 2017 —
Shannon Sims - Bloomberg“Next contestant, come on down.” On Oct. 6, in a bright courtroom in downtown Houston, Susan Braden, chief justice of the U.S. Court of Federal Claims, opens a preliminary hearing with a joke, beckoning a lawyer forward. Braden has flown in from Washington to oversee disputes involving the homes and businesses flooded in West Houston after Hurricane Harvey made landfall over Texas in late August. She has summoned attorneys interested in suing, to get their thoughts on how the proceedings should unfold.
Almost 100 lawyers are present, combed and buzzing in anticipation of what promises to be some of the most complex and expensive litigation ever brought against the federal government. Observers speculate that thousands of plaintiffs could eventually join in, and that the total damages claimed could reach $10 billion or more, especially if the big energy and oil companies—whose presence in one section of West Houston gave it the nickname the Energy Corridor—sue over their flooded headquarters. Eighty suits, 11 of which are seeking class-action status, have been filed by homeowners against the federal government, though many of the Energy Corridor’s approximately 9,500 residents are still weighing their options, speed-dating lawyers by phone and at community meetings.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon Sims, Bloomberg
Haight has been named a Metropolitan Los Angeles Tier 1 “Best Law Firm” in four practice areas and Tier 2 in one practice area by U.S. News – Best Lawyers® “Best Law Firms” in 2020
December 09, 2019 —
Haight Brown & Bonesteel LLPHaight Brown & Bonesteel LLP is listed in the U.S. News – Best Lawyers® (2020 Edition) “Best Law Firms” list with five metro rankings in the following areas:
Los Angeles
- Tier 1
- Insurance Law
- Personal Injury Litigation – Defendants
- Product Liability Litigation – Defendants
- Product Liability Litigation – Plaintiffs
- Tier 2
- Personal Injury Litigation – Plaintiffs
Read the court decision
Read the full story...
Reprinted courtesy of Haight Brown & Bonesteel LLP
U.S. Department of Defense Institutes New Cybersecurity Maturity Model Certification
July 13, 2020 — Joseph N. Frost - Peckar & Abramson
Contractors doing business with the Federal Government, particularly with the Department of Defense (“DoD”), commonly handle sensitive information that is not intended to be disseminated. Controlled Unclassified Information (“CUI”) is one such type and is more specifically defined as “information that requires safeguarding or dissemination controls pursuant to and consistent with laws, regulations and government-wide policies.”1 Because some DoD contracts require contractors to handle CUI, certain safeguards have been put in place to ensure its security. This article briefly touches on the current cybersecurity protocols, followed by a discussion of the new system being developed by the DoD, and what contractors most need to know about the new system.
The Defense Federal Acquisition Regulation Supplement (“DFARS”) has long required contractors to comply with certain cybersecurity standards, as published by the National Institute of Standards and Technology (“NIST”). Specifically, DFARS sought to implement the cybersecurity framework found in NIST Special Publication (“SP”) 800-171, entitled “Protecting Controlled Unclassified Information in Nonfederal Systems and Organizations.” NIST SP 800-171 sets forth fourteen (14) families of recommended security requirements for protecting the confidentiality of CUI in nonfederal systems and organizations, including, among others, access control, audit and accountability, incident response, personnel security, and system and information integrity. However, after a series of data breaches, the DoD reassessed the efficacy of the continued use of NIST SP 800-171 and ultimately decided to institute a new methodology to ensure the security of CUI. Read the court decision
Read the full story...
Reprinted courtesy of Joseph N. Frost, Peckar & Abramson
Mr. Frost may be contacted at jfrost@pecklaw.com
FIFA May Reduce World Cup Stadiums in Russia on Economic Concern
July 16, 2014 — Tariq Panja – Bloomberg
FIFA may reduce the number of stadiums used to host the 2018 World Cup in Russia on concern that their economic viability after the monthlong event ends.
FIFA President Sepp Blatter said a day after Germany’s 1-0 win over Argentina in the final that a delegation from soccer’s governing body will meet Russian tournament organizers in September to discuss plans for the next edition.
Blatter gave a mark of 9.25 out of 10 to an “exceptional” Brazil World Cup, which cost $11 billion to stage. The tournament is a difficult challenge for organizers, Blatter said, illustrated by construction delays at almost all of the 12 arenas used for the 64 games in Brazil.
“The World Cup has taken such a dimension that the organization is hard work for the organizing country and also for FIFA,” Blatter told reporters at Rio de Janeiro’s Maracana stadium, where Germany claimed a fourth title and became the first European country to win the tournament in South America.
Read the court decision
Read the full story...
Reprinted courtesy of Tariq Panja, Bloomberg
Mr. Panja may be contacted at tpanja@bloomberg.net
No Coverage Under Installation Policy When Read Together with Insurance Application
January 16, 2024 — David Adelstein - Florida Construction Legal Updates
A recent case out of the Eleventh Circuit denied an underground contractor’s claim under what appears to be a commercial property installation floater policy (inland marine coverage) that covers the contractor’s materials. Whereas a builder’s risk policy is more expansive, an installation floater is narrower and can provide protection to a contractor for materials and equipment in transit, stored, or being installed subject to the terms of the installation floater policy. It can provide coverage to a trade subcontractor for materials that aren’t covered by builder’s risk.
In Travelers Property Casualty Company of America v. Talcon Group, LLC, 2023 WL 8798053 (11th Cir. 2023), an underground utility contractor that had a general contractor’s license had an installation policy that provided coverage “only for underground utility operations and the site development work tied to those operations.” Talcon Group, supra, at *1. The utility contractor was constructing two residential homes that was on land owned by an affiliated family entity. During construction of the residential homes, a wildfire destroyed the homes prior to the issuance of certificates of occupancy. The utility contractor submitted a notice of loss to its insurance carrier that provided the installation policy. The carrier denied the claim because the construction of the homes was NOT the same type of work as the installation of underground utilities which was covered. An insurance coverage lawsuit ensued. Read the court decision
Read the full story...
Reprinted courtesy of David Adelstein, Kirwin Norris, P.A.
Mr. Adelstein may be contacted at dma@kirwinnorris.com
Bremer Whyte Brown & O’Meara LLP Attorneys to Speak at the 2016 National Construction Claims Conference
September 01, 2016 — Beverley BevenFlorez-CDJ STAFF
Bremer Whyte Brown & O’Meara, LLP (BWBO), announced that Keith G. Bremer, Founding Partner and John H. Toohey, Partner, will be speaking at the CLM National Construction Claims Conference being held September 28-30th this year. More than 500 professionals will gather at the conference location, the Manchester Grand Hyatt in San Diego, California.
According to BWBO’s release, “the CLM will hold the most comprehensive construction claims conference ever. In addition to addressing construction defect claims, conference sessions will also address facets of construction-related claims including construction site accidents/injuries, coverage issues, subcontractor issues, and new technologies. Sessions will also address issues on the national, regional, and state levels.”
Read the court decision
Read the full story...
Reprinted courtesy of