Massachusetts Judge Holds That Insurer Breached Its Duty To Defend Lawsuit After Chemical Spill
October 16, 2018 —
Lawrence J. Bracken, II & Alexander D. Russo - Hunton Insurance Recovery BlogA District Court Judge for the District of Massachusetts recently ruled that Ace Property and Casualty Insurance Co. breached its duty to defend its insured in a lawsuit brought by Plaistow Project, LLC, after a family owned laundromat leaked chemicals onto Plaistow Project’s property. Plaistow Project, LLC v. ACE Prop. & Cas. Ins. Co., No. 16-CV-11385-IT, 2018 WL 4357480, (D. Mass. Sept. 13, 2018). Plaistow Project sued State Line Laundry Services in state court, and ACE denied coverage under the pollution exclusion in State Line Laundry’s insurance policy. Plaistow Project then settled with State Line Laundry. Under the settlement terms, Plaistow Project was assigned State Line Laundry’s rights against ACE.
In the subsequent coverage litigation, Plaistow Project alleged that ACE had breached its duty to defend State Line Laundry under its insurance policy. ACE argued that (1) the burden was on the policyholder to demonstrate that the policy’s “sudden and accidental” exception applied to the policy’s pollution exclusion; and (2) the policyholder could not show the “sudden and accidental” exception applied based on the complaint.
Reprinted courtesy of
Lawrence J. Bracken, II, Hunton Andrews Kurth and
Alexander D. Russo, Hunton Andrews Kurth
Mr. Bracken, may be contacted at lbracken@HuntonAK.com
Mr. Russo may be contacted at arusso@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Wendel Rosen’s Construction Practice Group Welcomes Quinlan Tom
January 06, 2016 —
Garret Murai – California Construction Law BlogThere’s been more cheer than usual at Wendel Rosen’s Construction Practice Group this holiday season.
Earlier this month, Quinlan Tom, a construction and business attorney, joined us from McInerney & Dillon, a venerable and well-respected construction boutique firm (we know a lot of folks there) with local roots like us in Oakland, California. We’ve all known Quinlan for a while, so when he decided to join our band of merry legal practitioners, we were quite thrilled.
Being lawyers though, and better at asking than answering questions, we decided to pose a few questions to Quinlan:
Q. So, you’ve just been sworn to tell the truth, the whole truth, and nothing but the truth, under penalty of perjury. So, tell us about your practice.
A. Let me just start with it’s quite an honor to appear in your blog; I’ve been a reader for a while (in secret of course before I got to Wendel Rosen). I’m also excited to join you and the other members of Wendel Rosen’s Construction Practice Group; as you mention, I’ve known each of you professionally for quite some time and respect each of you tremendously.
I started as a construction litigator right out of law school. I completed three years of mechanical engineering at UC Davis and put that on my resume when I was looking for a job after law school. (In addition, my dad retired after 40 years in the trenches as a union electrician). McInerney & Dillon (“M&D”) and a couple of other firms found that interesting and I ended up starting with M&D. I did find that my engineering studies helped with my acclimation to construction disputes. While I never pretend to be an engineer, it has provided me with a foundation of how the construction process works and how the projects are designed. 26 years later, I continue to enjoy counseling my clients in their construction disputes/issues and still find each construction project I am involved with fascinating.
I have tried, arbitrated and litigated cases for 26 years, from the United States District Court to the California Superior Court and the California Office of Administrative Hearings. I have argued cases before the Ninth Circuit Court of Appeals and the California Court of Appeal. I counsel my clients into hopefully making the best business decisions available melding the knowledge I have gleaned from my litigation experience with their financial and personal goals.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Fourth Circuit Issues New Ruling on Point Sources Under the CWA
October 02, 2018 —
Anthony B. Cavender - Gravel2GavelThe Clean Water Act (CWA) authorizes citizen suits to enforce the provisions of the law which requires a permit to discharge a pollutant from a point source into navigable waters. Earlier this year, the U.S. Court of Appeals for the Fourth Circuit, in Upstate Forever v. Kinder Morgan Energy Partners, held that discharges into groundwater, not surface water, could also trigger the regulatory authority of the CWA if there was a hydrological connection between the groundwater and the navigable, surface, waters. In its a closely-watched case, Sierra Club v. Virginia Electric & Power Company (“VEPCO”), which also involved discharges into groundwater, the Fourth Circuit was bound by this this new and controversial precedent (a Supreme Court review is very likely), but the plaintiffs in the VEPCO case could not establish that the landfill and the settling ponds used by VEPCO were “point sources”—another important element that must be established.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Revamp to Nationwide Permits Impacting Oil and Gas Pipeline, Utility and Telecom Line Work
March 29, 2021 —
Alex P. Prochaska, Jones Walker LLP - ConsensusDocsTo avoid delay costs and penalties, contractors involved in pipeline and utilities construction maintenance, repair and removal need to understand how the 43 year old Nationwide Permit (NWP) regime has changed specific to the NWP 12 and what is now required for compliance. This change is important for contractors who construct, maintain, or repair pipelines that cross or impact waters of the United States, including wetlands. NWPs are a useful tool to streamline construction of a pipeline project, but it is important for contractors to know when certain terms and conditions still apply to the particular NWP and those that have been eliminated.
On January 13, 2021, the United States Army Corps of Engineers (the Corps) published a final rule that reissued and modified twelve existing NWPs and issued four new NWPs that will take effect on March 15, 2021.1 The remaining 40 NWPs that were not reissued or modified under this rule will continue under the general conditions and definitions of the January 6, 2017 final rule.
Read the court decisionRead the full story...Reprinted courtesy of
Alex P. Prochaska, Jones Walker LLPMr. Prochaska may be contacted at
aprochaska@joneswalker.com
Contractors May be Entitled to Both Prompt Payment Act Relief and Prejudgment Interest for a Cumulative 24%!
August 22, 2022 —
Margarita Kutsin - Ahlers Cressman & SleightThe Washington Prompt Payment Act, in Ch. 39.76 RCW and in RCW 39.04.250, ensures that contractors and subcontractors are promptly paid for their performance on public works contracts. Where a government entity or a prime contractor wrongfully withholds undisputed amounts due, that government entity or prime contractor must pay interest at a rate of 12% per annum.
Separately, prejudgment interest is awarded “based on the principle that a defendant ‘who retains money which he ought to pay to another should be charged interest upon it.’” Hansen v. Rothaus, 107 Wn.2d 468, 472, 730 P.2d 662 (1986) (quoting Prier v. Refrigeration Eng’g Co., 74 Wn.2d 25, 34, 442 P.2d 621 (1968)). The purpose is to “compensate the plaintiff for the use value of the money representing liquidated or determinable damages.” Id.
Read the court decisionRead the full story...Reprinted courtesy of
Margarita Kutsin, Ahlers Cressman & SleightMs. Kutsin may be contacted at
margarita.kutsin@acslawyers.com
Sellers of South Florida Mansion Failed to Disclose Construction Defects
October 08, 2014 —
Beverley BevenFlorez-CDJ STAFFA couple who reportedly sold their custom, beach-front home on Golden Beach for more money than any other home in that town previously, may have failed to disclose construction defects, according to Daily Business Review.
The original owners, reported Daily Business Review, claimed (according to court documents) that “they were ‘unable to spend even one night because an overwhelming smell of mold in the home triggered a severe reaction in Mrs. Hochberg.’" They also alleged the new home had “cracked walls, drafty doors, leaky windows, poorly cut marble and peeling stucco.” The owners sued the subcontractors, but lost due to not filing within the four-year statute of limitations.
While water leaks were disclosed during the sale with a notation that all leaks had been repaired, “the extent of the home's repair history was not discussed during nearly eight months of haggling over the property, the buyer's broker said.”
Read the court decisionRead the full story...Reprinted courtesy of
CDJ’s #6 Topic of the Year: Does Colorado Need Construction Defect Legislation to Spur Affordable Home Development?
December 31, 2014 —
Beverley BevenFlorez-CDJ STAFFThe question involves whether a Colorado law passed in 2005 has made it too easy for homeowners to sue developers for construction defects, allegedly causing a decline in condominium building in the state. The Construction Defect Journal became a forum for this lively debate with two prominent, Colorado, construction defect attorneys providing their views on the subject:
Jesse Howard Witt, of the Witt Law Firm, published “Colorado Mayors Should Not Sacrifice Homeowners to Lure Condo Developers.”
Read the full story...
In response, James M. Mulligan of Snell & Wilmer, LLP presented his perspective in, “Are Construction Defect Laws Inhibiting the Development of Attached Ownership Housing in Colorado?”
Read the full story...
The city of Lakewood did not wait for the state, but instead passed its own ordinance, which “gives developers and builders a ‘right to repair’ defects before facing litigation and would require condominium association boards to get consent from a majority of homeowners — rather than just the majority of the board — before filing suit,” according to John Aguilar’s piece in The Denver Post.
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Nuclear Fusion Pushes to Reach Commercial Power Plant Stage
August 05, 2024 —
Mary B. Powers, Debra K. Rubin, Peter Reina & David Godkin - Engineering News-RecordThe quest to develop nuclear fusion—the process that energizes the sun and other stars—as an earth-based power source dates back more than a century when Albert Einstein and other scientists theorized how enormous amounts of energy could be produced when atoms fuse. That research was partly diverted for wartime weapons priorities but later targeted to develop fusion for commercial-scale energy—what sector proponents have called the “holy grail” for decades since.
Reprinted courtesy of
Mary B. Powers, Engineering News-Record,
Debra K. Rubin, Engineering News-Record,
Peter Reina, Engineering News-Record and
David Godkin, Engineering News-Record
Ms. Rubin may be contacted at rubind@enr.com
Mr. Reina may be contacted at reina@btinternet.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of