Architects Should Not Make Initial Decisions on Construction Disputes
July 05, 2023 —
Bill Wilson - Construction Law ZoneA common provision often deleted from the standard form AIA documents is the provision in the AIA A201 General Conditions requiring an Initial Decision Maker (IDM) for claims between the contractor and owner. In the A201, the contracting parties have the option of naming their own IDM for the project. If an IDM is not selected (which is typically the case) the architect serves this role by default. While it is in all parties’ best interests to resolve disputes quickly and efficiently, using the architect as the IDM is not the best way to achieve such a resolution.
Several reasons work against using the architect as the IDM. Contractors typically don’t trust architects to be impartial in resolving disputes because the architect is paid by the owner. Most architects don’t have the temperament or any training to facilitate dispute resolution. An architect’s “initial decision” could even drive the parties further apart and lead to further issues later in the project. The architect may also be perceived to be part of the problem that led to the dispute in the first place. Also, many architects simply prefer to avoid serving the thankless role of an IDM altogether. Lastly, inserting the architect into the dispute resolution process as a required IDM adds an additional unnecessary step to dispute resolution, which can delay the overall procedure.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
Wyncrest Commons: Commonly Used Progress Payments in Construction Contracts Do Not Render Them Installment Contracts
December 11, 2023 —
Benjamin J. Hochberg - Peckar & Abramson, P.C.In BIL-JIM Construction Company, Inc. v. Wyncrest Commons, LP, 2023 WL 7276637 (Unpublished, decided November 3, 2023), the New Jersey Appellate Division was asked to consider two issues regarding the interpretation and application of a construction contract that utilized the standard form American Institute of Architects owner/contractor agreement (AIA Document A101-2007) (the “AIA Contract”). Specifically, it was asked to consider: 1) whether a modified AIA Contract was an “installment contract,” whereby each progress payment was subject to its own statute of limitations; and 2) whether and when work had been approved in the context of New Jersey’s Municipal Land Use Law. While the decision is presently unpublished, it provides guidance as to how form contracts utilizing the same or similar terms will be treated by New Jersey’s courts and is a reminder that the potential for future claims must be considered during contract negotiations.
Discussion
The primary issue in Wyncrest was whether an AIA Contract was an “installment contract,” and the remaining issues turned on the resolution of this question. Wyncrest, the owner for the project at issue, did not dispute that its contractor, BIL-JIM Construction Company, Inc., had not been fully paid for work that it had performed in connection with a construction project located in Ocean County, New Jersey. Instead, Wyncrest argued that because its AIA Contract with BIL-JIM required that invoices be presented and paid monthly, it constituted an “installment contract.” As such, older payments would be treated as individual transactions and were time barred by the applicable statute of limitations. The trial court agreed with Wyncrest’s characterization of the AIA Contract as an “installment contract,” and found that BIL-JIM’s invoices were each subject to their own statute of limitations. However, the trial court disagreed with Wyncrest’s argument that BIL-JIM’s claim for retainage—which was submitted at the end of its work at the project—was time barred.
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin J. Hochberg, Peckar & Abramson, P.C.Mr. Hochberg may be contacted at
bhochberg@pecklaw.com
UPDATE - McMillin Albany LLC v. Superior Court
June 05, 2017 —
Richard H. Glucksman, Glenn T. Barger, & David A. Napper - CGDRB News & PublicationsThe matter has been fully briefed since last year and the construction industry anxiously awaits the California Supreme Court's highly anticipated decision regarding McMillin Albany LLC v. Superior Court (2015) 239 Cal.App.4th 1132. Numerous amicus briefs have also been filed including one by the Association of Southern California Defense Counsel, with the immediate past president of the organization, CGDRB's Glenn T. Barger, Esq., listed as the attorney of record. The Supreme Court will consider the issue of whether the Right to Repair Act (SB800) is the exclusive remedy for all defect claims arising out of new residential construction sold on or after January 1, 2003, thereby resolving the split of authority presented by the Fifth Appellate District's holding in McMillin Albany, which outright rejected the Fourth Appellate District's holding in Liberty Mutual Insurance Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98, on this particular issue. Oral argument is still pending and CGDRB will continue to closely monitor the progress of this case. Stay tuned.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Glenn T. Barger and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Barger may be contacted at gbarger@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Definitions Matter in Illinois: Tenant Held Liable Only for Damage to Apartment Unit
September 09, 2024 —
Gus Sara - The Subrogation StrategistIn Phila. Indem. Ins. Co. v. Gonzalez, No. 1-23-0833, 2024 Ill. App. Unpub. LEXIS 1372, the Appellate Court of Illinois considered whether the terms of a lease agreement limited a tenant’s liability for fire damages, a fire caused by her negligence, to her apartment unit only. The plaintiff insured the subject apartment building, which incurred damage to several units as result of a fire in the tenant’s unit. The lease defined “Premises” as the specific apartment unit occupied by the tenant and held the tenant responsible for damage caused to the Premises. While the court found that the lease permitted the plaintiff to subrogate against the tenant, it held that the lease terms limited the damages to the tenant’s apartment unit only.
In Gonzalez, the plaintiff’s insured owned a multi-unit apartment building in Chicago. In September 2019, the building owner entered into a lease agreement with the defendant for apartment Unit 601. The lease stated that Unit 601 was the “Leased Address (Premises).” Another provision stated that building owner “hereby leases to Tenant(s) and Tenant(s) hereby leases from Landlord(s) for use as a private dwelling only, the Premises, together with the fixtures and appliances (if any) in the premises…” The lease also stated that “Tenant shall be liable for any damage done to the premises as a result of Tenant’s or Tenant’s invitees, guests or others authorized to reside in the Premises [sic] direct action, negligence, or failure to inform Landlord of repairs necessary to prevent damage to the Premises.”
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
Client Alert: Expert Testimony in Indemnity Action Not Limited to Opinions Presented in Underlying Matter
February 18, 2015 —
R. Bryan Martin and Kristian B. Moriarty – Haight Brown & Bonesteel, LLPIn National Union Fire Insurance Co. of Pittsburgh Pa. v. Tokio Marine and Nichido Fire Insurance Co. (filed 2/4/2015, B24899 and B247258), the California Court of Appeal, Second District, held that the insurer of Costco Wholesale Corporation, in a subsequent indemnity action, could offer expert opinions which were not developed by the third-party plaintiff’s experts in an underlying dispute.
Jack Daer filed suit against Costco and Yokohama Tire Corporation, alleging a tire manufactured by Yokohama (and sold by Costco), was defective and caused an accident resulting in Mr. Daer’s injuries. The case proceeded through expert discovery and depositions. On the first day of trial, Costco settled with Daer for $5.5 million, and Yokohama settled for $1.1 million.
Reprinted courtesy of
R. Bryan Martin, Haight Brown & Bonesteel LLP and
Kristian B. Moriarty, Haight Brown & Bonesteel LLP
Mr. Martin may be contacted at bmartin@hbblaw.com, Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Pollution Exclusion Prevents Coverage for Injury Caused by Insulation
March 30, 2016 —
Tred R. Eyerly – Insurance Law HawaiiIn a per curiam decision, the Fifth Circuit affirmed the district court's holding that the pollution exclusion barred coverage for bodily injury caused by the insured's insulation. Evanston Ins. Co. v. Lapolla Industries, Inc., 2015 U.S. App. LEXIS 22552 (5th Cir. Dec. 23, 2015).
The homeowners' contractors installed spray polyurethane foam (SPF) insulation as part of a renovation project in the home. Lapolla manufactured the SPF. Shortly after the insulation was installed, the homeowners smelled strong odors and suffered respiratory distress, causing them to leave the home. The homeowners sued the contractor and various subcontractors for negligence and breach of contract. A third party complaint was filed against Lapolla. The homeowners also amended their complaint to assert a products-liability claim against Lapolla.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Putting for a Cure: Don’t Forget to Visit BHA’s Booth at WCC to Support Charity
April 28, 2016 —
Beverley BevenFlorez-CDJ STAFFBert L. Howe & Associates, Inc., (BHA) is excited to announce the return of their very popular
Sink a Putt for Charity at the 2016
West Coast Casualty Construction Defect Seminar. This year, participant’s efforts
on the green will help benefit the Susan G. Komen Race for the Cure. As in years past, sink a putt in the BHA golf challenge and win a $25 gift card, and for every successful putt made, BHA will make a $25 cash donation in the golfer’s name to the Susan G. Komen Foundation.
But it doesn’t stop there. Breast cancer touches so many lives, with wives, mothers, sisters, aunts, cousins and daughters all affected by this insidious disease. To further assist in their noble fight, BHA is doubling down. During three Championship Rounds on Thursday morning, afternoon, and evening, BHA will up the ante. For every putt ATTEMPTED (sink or miss), BHA will make a $50 donation to Susan G. Komen, and for every putt MADE, the golfer will also win a $50 gift card.
These Championship Rounds will occur during the Thursday morning break, the afternoon break, and during the first hour of the Thursday evening cocktail party. Bert L. Howe & Associates, Inc., strongly supports the goals and principles of the Susan G. Komen Race for the Cure, and is honored to assist in fulfilling its mission of supporting research, community health, global outreach and public policy initiatives.
While at the booth, don’t forget to test out BHA’s industry leading data collection and inspection analysis systems. BHA has recently added video overviews to their data collection process, as well as next-day viewing of inspection data via their secured BHA Client Access Portal. Discover meaningful cost improvements that translate to reduced billing while providing superior accuracy and credibility.
Attendees can also enter to win Dodger baseball tickets or one of three new iPad Pros! Other BHA giveaways include USB charging blocks, pocket tape measures, multi-tools, laser pointers, foam stress balls, and Callaway golf balls.
For more information on the Susan G. Komen Foundation, please visit their
website.
Read the court decisionRead the full story...Reprinted courtesy of
Appraisal Process Analyzed
August 19, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe California Court of Appeal offered a primer in the appraisal process in reversing the trial court's confirmation of the appraisal award. Lee v. California Capital Ins. Co., 2015 Cal. App. LEXIS 530 (Cal. Ct. App. June 18, 2015).
A fire damaged an apartment building owned by the insured. The fire started in unit 3 on the ground floor. The insurer argued the fire did not extend beyond unit 3. The insured claimed that the fire damaged six of the 12 apartments with fire or smoke.
The insured's public adjuster submitted a claim to the insurer that exceeded $800,000. The statement of loss included costs for cleaning, asbestos abatement, reconstruction of affected apartments, and loss of rent. The public adjuster said the loss consisted of burn damage to unit 3 and some damage to the "common" walls located between the apartments on the two floors above unit 3. All of the interior rooms of five apartments other than unit 3 would need to be completely dismantled and then replaced.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com