Court of Appeals Rules that HOA Lien is not Spurious, Despite Claim that Annexation was Invalid
March 27, 2019 —
Jesse Howard Witt - The Witt Law FirmToday, the Colorado Court of appeals reversed a order that had deemed a homeowner association’s lien to be spurious.
The case arose after a developer approved a property owner’s application to annex additional real estate to a community in 1999. Several years later, the developer repurchased the property through a foreclosure sale. Despite its prior approval of the annexation, the developer refused to pay community maintenance assessments, which prompted the association to record a lien under its covenants and a statutory provision of the Colorado Common Interest Ownership Act (CCIOA).
The parties remained in a standoff until 2016, when the Colorado Supreme Court announced two decisions that adopted a stricter standard for annexing property into communities subject to CCIOA. Relying on this new authority, the developer at Stroh Ranch argued that the 1999 annexation was no longer valid. The district court agreed and declared the association’s lien to be spurious.
Reprinted courtesy of
Jesse Howard Witt, Acerbic Witt
Mr. Witt may be contacted at www.witt.law
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Renee Zellweger Selling Connecticut Country Home
August 06, 2014 —
Emily Heffter – BloombergYou had me at seven fireplaces (and a bread oven).
Actress Renee Zellweger’s Connecticut country home, on the market for $1.6 million, is hardly roughing it.
The luxury farmhouse, built in 1770 and updated in 2004, is a stylish and luxurious country getaway. Set on 38 acres overlooking the Quinebaug River in rural Pomfret Center, the retreat at 96 Cotton Rd is 3,463 square feet with a top-of-the-line kitchen, a bread oven in the family room and a swimming pool.
Read the court decisionRead the full story...Reprinted courtesy of
Emily Heffter, Zillow
Design-Build Contracting: Is the Shine Off the Apple?
March 09, 2020 —
John P. Ahlers - Ahlers Cressman & Sleight PLLCThe design-build delivery method offers many benefits to owners. Among the cited benefits are that projects are generally completed faster, at a lower cost, by allowing innovative approaches through early and continual contractor involvement in the design process. The design contractor serves as a single point of contact responsible for both the design and construction of the project.
The Washington State Department of Transportation (“WSDOT”) utilized the design-build procurement method on the largest project ($2 billion) of its type in the state of Washington: the Highway 99 Tunnel, which was finished almost three years late after the tunnel-boring machine (“Bertha”) broke down six years ago. The sorted tale of the SR-99 Tunnel Project was the source of many of this firm’s blog articles.[1] The State of Washington staunchly maintained that the design-build contract protected its taxpayers from covering the repair costs to the tunnel-boring machine when it broke down in 2013. Bertha did not resume tunneling for almost two years, putting on hold removal of the Alaska Way viaduct and rebuilding of the Seattle Waterfront without an elevated highway.
In December 2013, the contractor for the project, Seattle Tunnel Partners (“STP”), contended that a 110-foot long 8” steel pipe which Bertha hit caused the breakdown. That pipe had been installed for groundwater testing by WSDOT in 2002 during its preliminary engineering for the viaduct replacement project. The project’s Dispute Review Board (“DRB”) composed of three tunneling experts found that the pipe constituted a “differing site condition” for which the State was responsible to disclose to contractors. The Board, whose views were non-binding, did not opine about how much damage the undisclosed pipe cost.[2] In other words, the mere fact that a differing site condition occurred did not establish that there was a causal connection between the damages which STP was seeking (in excess of $600 million) and the differing site condition (the 8” steel pipe which WSDOT lawyers at trial derisively referred to as “nothing more than a toothpick for Bertha’s massive cutter head”). STP maintained that Bertha had made steady progress except for three days immediately after hitting the pipe. It didn’t help the contractors’ case that during the discovery phase of the two-month trial, WSDOT lawyers uncovered documents showing that the contractor’s tunnel workers encountered and logged the pipe before digging began.[3]
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers Cressman & Sleight PLLCMr. Ahlers may be contacted at
john.ahlers@acslawyers.com
More Charges Anticipated in Las Vegas HOA Scam
February 28, 2013 —
CDJ STAFFWith almost forty people already charged in the conspiracy to take over Las Vegas homeowners associations in order to profit from construction defect claims, more charges are likely to come, according to an article in the Las Vegas Review Journal. The article also notes that the trial against Leon Benzer will involve millions of pages of documents. It is alleged that Benzer found straw purchasers for condominiums in order to control homeowner boards. Benzer’s firm, Silver Lining Construction, would then receive contracts to repair construction defects.
The Justice Department will be seeking restitution for the victims, which may total $25 million. Four individuals with connections to the conspiracy have died since investigations began. At least three of these deaths were suicides, and included Nancy Quon, who with Benzer are thought to be the main figures in the scam.
Read the court decisionRead the full story...Reprinted courtesy of
Construction Contract’s Scope of Work Should Be Written With Clarity
March 06, 2023 —
David Adelstein - Florida Construction Legal UpdatesThe scope of work section in your construction contract should never be overlooked. In numerous instances, it is overlooked which leads to a dispute as to the precise nature of the scope of work. This dispute could be the result of an ambiguity in the scope of work section. Or it could be the result of an omission. Or it could be the result of a lack of clarification. Or it could be the result of not properly reviewing and vetting the scope of work section. This is a section—whether included in the body of your contract or attached as an exhibit—you absolutely, positively want clarity. Otherwise, you are potentially setting yourself up for a future dispute that could include (i) an additional work / change order dispute, (ii) an incomplete work dispute, or (iii) a failure to properly perform your work dispute. These are all disputes you want to avoid, and many times can avoid, by going through and negotiating the scope of work section to bring clarity to this section. Remember, clarity is a positive. Ambiguity or uncertainty is a negative.
An example of such an avoidable scope of work dispute can be found in All Year Cooling and Heating, Inc. v. Burkett Properties, Inc., 2023 WL 2000991 (Fla. 4th DCA 2023). Here, an air conditioning contractor was hired to install six new split air conditioning systems. The scope of work provided that there were currently “two split systems that are currently existing, working perfectly and are not to be replaced as part of this contract.” The property manager claimed the air conditioning contractor was required to bring these two existing split air conditioning systems up to code as the contract provided that notwithstanding anything to the contrary, the contractor “will certify and shall ensure that all split systems in the building, upon completion of all the work, will be fully compliant with all codes and regulations and shall be responsible for any costs relates to the implementation and/or remediation of same.”
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
OSHA Issues New Rules on Injury Record Keeping
August 19, 2015 —
Craig Martin – Construction Contractor AdvisorOn July 28, 2015, OSHA issued proposed rules seeking to clarify an employer’s ongoing obligation to make and maintain accurate records of work-related injuries and illness. The new rules were drafted in response to the U.S. Court of Appeals decision in AKM LLC, d/b/a Volks Constructors v. Secretary of Labor, in which a contractor successfully argued that OSHA’s citation was issued well beyond the six month limitation period.
OSHA’s Injury Record Keeping Obligations
The Occupational Safety and Health Act requires each employer to make, keep and preserve records of workplace injuries and illnesses. 29 U.S.C. § 658(c). OSHA has promulgated a set of regulations which require employers to record information about work-related injuries and illnesses in three ways. Employers must prepare an incident report and a separate injury log “within seven (7) calendar days of receiving information that a recordable injury or illness has occurred,” 29 C.F.R. § 1904.29(b)(3), and must also prepare a year-end summary report of all recordable injuries during the calendar year, id. § 1904.32(a)(2). An employer “must save” all of these documents for five years from the end of the calendar year those records cover. 29 C.F.R. § 1904.33(a).
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Building Resiliency: Withstanding Wildfires and Other Natural Disasters
September 25, 2023 —
Bill Creedon - Construction ExecutiveAccording to the National Fire Protection Association, between 2016 and 2020 an estimated average of 4,300 fires per year plagued structures under construction, adding up to about $376 million in annual property damage. More recently, the National Centers for Environmental Information reported that wildfires accounted for more than $3.2 billion in damages across the United States. These figures alone point to the heightened awareness that all companies—particularly construction companies—should maintain surrounding the unique challenges and risks that wildfires can present and how they could potentially impact the integrity of projects and the associated safety of their workers.
As North America grapples with the increasing frequency and severity of wildfires, hurricanes and additional severe weather events, numerous industries have had to adapt and implement proactive measures to minimize their risks and associated exposures. The impact of these natural disasters on the construction industry is indisputable, necessitating proactive measures that construction companies should seriously consider adopting to effectively mitigate those risks, efficiently navigate insurance complexities and seamlessly integrate data-driven solutions alongside modern tools like AI and predictive modeling.
Reprinted courtesy of
Bill Creedon, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Creedon may be contacted at
bill.creedon@wtwco.com
New York Court of Appeals Finds a Proximate Cause Standard in Additional Insured Endorsements
June 15, 2017 —
Geoffrey Miller - Saxe Doernberger & Vita, P.C.In The Burlington Insurance Company v. NYC Transit Authority, et al., No. 2016-00096, the New York Court of Appeals issued a landmark decision with regard to the meaning of “caused, in whole or in part, by” in the additional insured context. In a split decision, the court rejected Burlington Insurance Company’s argument that the language implied a “negligence” standard, but held that coverage was provided to the additional insured only where the named insured’s acts or omissions were the proximate cause of the injury:
While we [the majority] agree with the dissent that interpreting the phrases differently does not compel the conclusion that the endorsement incorporates a negligence requirement, it does compel us to interpret ‘caused, in whole or in part’ to mean more than ‘but for’ causation. That interpretation, coupled with the endorsement’s application to acts or omissions that result in liability, supports our conclusion that proximate cause is required here.[1]
Read the court decisionRead the full story...Reprinted courtesy of