New California "Construction" Legislation
November 08, 2018 —
Richard H. Glucksman, Esq. & Chelsea L. Zwart, Esq. - Chapman Glucksman Dean Roeb & BargerGovernor Jerry Brown signed two potentially impactful Senate Bills relating to the construction of apartment buildings late last month. These Bills, discussed further below, were introduced, in part, in response to the Berkeley balcony collapse in June 2015, which was determined by the California Contractors State License Board to be caused by the failure of severely rotted structural support joists the repair of which were deferred by the property manager, despite indications of water damage.
SENATE BILL 721 ESTABLISHES HEIGHTENED “LOAD-BEARING” INSPECTION REQUIREMENTS
On August 21, 2018, the California State Senate passed SB 721, one of two bills by Senator Jerry Hill introduced this year seeking to address the safety of multifamily rental residences. Now that the Governor has signed the Bill, a new section will be added to the California Health and Safety Code, requiring that every 6 years, destructive testing be performed on at least 15% of each type of load-bearing, wood framed exterior elevated element (such as balconies, walkways, and stair landings) in apartment buildings with 3 or more units. Interestingly, prior to being passed by the State Senate, SB 721 was revised in June 2018, such that the inspection requirements do not apply to common interest developments (i.e., condominiums).
As set forth in the new Health and Safety Code Section 17973:
"the purpose of the inspection is to determine that exterior elevated elements and their associated waterproofing elements are in a generally safe condition, adequate working order, and free from any hazardous condition caused by fungus, deterioration, decay, or improper alteration to the extent that the life, limb, health, property, safety, or welfare of the public or the occupants is not endangered."
The inspection must be paid for by the building owner and performed by a licensed contractor, architect, or civil or structural engineer, or a certified building inspector or building official from a recognized state, national, or international association. Emergency repairs identified by the inspector must be made immediately. For non-emergency repairs, a permit must be applied for within 120 days and the repair completed within 120 days of the permit’s issuance. If repairs are not completed within 180 days, civil penalties of $100-$500 per day may be imposed.
The required inspection must be completed by January 1, 2025 and every 6 years thereafter, unless an equivalent inspection was performed during the 3 years prior to January 1, 2019, the effective date of the new law. For a building converted to condominiums that will be sold after January 1, 2019, the inspection required by Health and Safety Code Section 17973, must be performed prior to the first close of escrow.
SENATE BILL 1465 SETS CONTRACTOR REPORTING REQUIREMENTS
The Governor also signed SB 1465, adding Sections 7071.20, 7071.21, and 7071.22 to the California Business and Professions Code. The new law requires that a contractor licensed with the Contractors’ State License Board "report to the registrar in writing within 90 days after the licensee has knowledge of any civil action resulting in a final judgment, executed settlement agreement, or final arbitration award in which the licensee is named as a defendant or crossdefendant, filed on or after January 1, 2019," that meets certain and specific criteria, including that it is over $1 million and arises out of an action for damages to a property or person allegedly caused by specified construction activities of the contractor on a multifamily rental residential structure.
Where more than one contractor was named as a defendant or cross-defendant, each of the contractors apportioned more than $15,000 in liability must report the action. Importantly, the new statute also imposes similar reporting requirements on insurers of contractors. SB 1465 also addresses an impacted party’s failure to comply with the reporting requirements.
COMMENT
Both SB 721 and SB 1465 are potentially significant and seek “legislative reform” to address construction issues by placing a greater burden on apartment owners as well as builders and subcontractors. How pragmatic and what impact they will have on the industry is obviously developing. If you are interested in receiving further detail concerning the Bills, please contact us. We are analyzing the new legislation and its intent and will be providing our ongoing comments.
Read the court decisionRead the full story...Reprinted courtesy of
RICHARD H. GLUCKSMAN, ESQ. CHELSEA L. ZWART, ESQ., CGDRBChelsea L. Zwart may be contacted at
czwart@cgdrblaw.com
Remodel Leaves Guitarist’s Home Leaky and Moldy
October 03, 2013 —
CDJ STAFFThe entertainment site TMZ reports that Eddie Van Halen is suing the contractor who remodeled his home. Mr. Van Halen claims that the contractor’s poor workmanship lead to water intrusion. According to the lawsuit, the roof and chimney leaked, and gutters and flashing were poorly installed. As a result, parts of the home suffered from mold damage. The lawsuit claims that Mr. Val Halen spent more than $1 million to repair his home after the remodel.
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Discretion in Determining Prevailing Party for Purposes of Attorney’s Fees
January 25, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn prior articles I have discussed that courts apply the significant issues test to determine the prevailing party for purposes of being entitled to attorney’s fees. A party that recovers an affirmative judgement is NOT the de facto prevailing party for purposes of an entitlement to attorney’s fees in a breach of contract action (or a construction lien foreclosure action). This was the issue in a recent appeal discussed here where the party that recovered an affirmative judgment on a breach of contract case was not deemed the prevailing party for purposes of attorney’s fees. While the party prevailed on one of its claims, it did not prevail on others, and it recovered less than half of the damages it originally sought. The appellate court, affirming the trial court, held that the trial court has discretion to determine that the party that recovered an affirmative judgement was not the prevailing party entitled to its attorney’s fees under the signifiant issues test. This was not what the party was expecting when the attorney’s fees it expended far exceeded the judgment it recovered.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Sinking S.F. Tower Prompts More Lawsuits
January 19, 2017 —
JT Long - Engineering News-RecordHomeowners on Jan. 6 added another lawsuit to the list pending against Millennium Partners, developer of the 645-ft-tall Millennium Tower, located in San Francisco’s South-of-Market district. The suit alleges that, as early as 2009, the developers knew the $350-million condo building was sinking faster than expected.
Read the court decisionRead the full story...Reprinted courtesy of
JT Long, ENRENR may be contacted at
ENR.com@bnpmedia.com
California Supreme Court Rejects Third Exception to Privette Doctrine
July 03, 2022 —
Lewis BrisboisWalnut Creek, Calif. (May 25, 2022) - In Gonzalez v. Mathis (August 19, 2021) 12 Cal. 5th 29, the California Supreme Court considered whether to create a third exception to the Privette Doctrine specific to known hazards on a worksite, when a contractor cannot remedy the hazard by taking reasonable safety precautions to protect against it.
Privette Background
Under the Privette Doctrine, the hirer of an independent contractor generally cannot be liable for injuries sustained by the independent contractor or its employees while on the job. This is due to the “strong presumption” that the hirer delegates all responsibility for workplace safety to the independent contractor. See Privette v. Superior Court (1993) 5 Cal. 4th 689. Since the Privette ruling in 1993, the California Supreme Court has identified two circumstances in which the presumption may be overcome. First, the hirer may be liable when it retains control over any part of the independent contractor’s work and negligently exercises that retained control in a manner that affirmatively contributes to the injury. Hooker v. Dept. of Transportation (2002) 27 Cal. 4th 198, 213. Second, a landowner who hires an independent contractor may be liable if the landowner knew, or should have known, of a concealed hazard to the property that the contractor did not know of and could not have reasonably discovered, and the landowner failed to warn the contractor of the hazard. Kinsman v. Unocal Corp. (2005) 37 Cal. 4th 659, 664. Here, in the Gonzalez case, the court considered whether a landowner could be liable for known hazards on the property.
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Denver Airport Terminates P3 Contract For Main Terminal Renovation
November 12, 2019 —
Mark Shaw - Engineering News-RecordIn a move that stunned transportation planners around the country, Denver International Airport terminated the contractor team working on a $650-million terminal renovation. The move also ended the airport’s $1.8-billion public-private partnership with Great Hall Partners, a consortium led by Ferrovial Airports, with partners Saunders/JLC Infrastructure.
Mark Shaw, Engineering News-Record
Mr. Shaw may be contacted at shawm@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part II
March 28, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Part II of this three-part series compares and analyzes important contract sections in the AIA 201 (2007 and 2017 versions) and ConsensusDocs (2014 and 2017 versions), including Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR.
Part I covered Financial Assurances, Design Risk, Project Management and Contract Administration. Part III will cover Insurance and Indemnification and Payment.
SCHEDULE/TIME
Relevant Sections:
- 2007 & 2017 A201: Section 3.10.1
- 2014 & 2017 ConsensusDocs: Section 6.2
AIA:
- Section 3.10.1 of the 2007 A201 requires that the Contractor promptly after being awarded the Contract, prepare and submit a construction schedule providing for Work to be completed within the time limits required in the Contract Documents.
- This schedule shall be revised at appropriate intervals.
- The 2017 edition breaks down the schedule to contain date of commencement, interim milestone dates, date of substantial completion, apportionment of Work by trade or building system, and the time required for completion of each portion of the Work.
- Under section 3.10.2 of the 2007 and 2017 versions, if the Contractor fails to provide a submittal schedule, the Contractor is not entitled to any additional compensation or a time extension based on the Owner’s or the Architect’s slow processing of submittals, regardless of how long they take.
ConsensusDocs 200:
- The 2017 Contract replaces the term Contract Time and instead requires a “Schedule of the Work…formatted in detailed precedence-style critical path method that (a) provides a graphic representation of all activities and events, including float values that will affect the critical path of the Work and (b) identifies dates that are critical to ensure timely and orderly completion of the Work.”
- The Constructor must submit an initial schedule to the Owner only before, “first application for payment” and thereafter on a monthly basis. (Section 6.2.1).
- The Owner is allowed to change the sequences provided in the schedule as long as it does not “unreasonably interfere with the Work.” (Section 6.2.2).
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Read the court decisionRead the full story...Reprinted courtesy of
When is a Contract not a Contract?
January 21, 2019 —
Christopher G. Hill - Construction Law MusingsAs I’ve stated numerous times here at Musings, in Virginia the contract is king. The courts of Virginia will read a contract as written and where there is a contract (read as foreshadowing), the courts will assume the parties knew what they were doing and enforce it by its terms. However, there has to be a contract in the first place.
When can something look like a contract but still not be a contract? When there isn’t mutual assent according to the case of Knox Energy, LLC v. Gasco Drilling, Inc. In the Knox case, along with a ruling on discovery abuse that is a topic of other blogs, considered a jury instruction on mutual assent given by the district court in a case where Knox contended that it inadvertently sent an unexecuted drilling contract form to Gasco and then inadvertently executed it when Gasco returned it. While this would not normally cause this series of events to be a non-contract, Knox also contended that Gasco knew that Knox had no intention to enter into the drilling contract and that Gasco jumped at the deal.
Read the court decisionRead the full story...Reprinted courtesy of