Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThe Biden administration will use infrastructure funds to upgrade 85 airports across the U.S., The Affordable New York tax provision expires, homebuyers in China refuse to pay mortgages, and more.
- Hines, a Houston-based real estate giant, set a target of its 1,530 properties in 28 countries being net-zero operational carbon by 2040. (John Egan, Innovation Map)
- The Biden administration announced it will spend roughly $1 billion from the infrastructure package to upgrade 85 airports across the country, including terminals and other facilities. (Jeff Mordock, The Washington Post)
- The Affordable New York tax provision, which offered a property tax exemption for housing projects that include a percentage earmarked for lower-income renters, expired in June, creating an unsettled future for the city’s multifamily development. (Rebecca Picciotto, The Wall Street Journal)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Washington Trial Court Narrows Definition of First Party Claimant, Clarifies Available Causes of Action in Commercial Property Loss Context
January 04, 2021 —
Kathleen A. Nelson & Jonathan R. Missen - Lewis BrisboisThe law in the State of Washington, albeit clear on issues regarding first party claimants, was recently challenged in the matter of Eye Associates Northwest, P.C. v. Sedgwick et. al. However, despite this challenge of first impression, the court limited the application of the term “first party claimant” (a term of art akin to “insured”) based upon the wording of a loss payee clause, as well as taking into consideration and harmonizing the wording of the leases, other provisions in the policy regarding tenant improvements, and the simple fact that Eye Associates was not named in the policy whatsoever.
In Eye Associates, the plaintiff leased office space in a high-rise medical office building, insured by three separate insurance companies. A water loss caused damage to the plaintiff’s leased space, and the plaintiff brought suit against the owner of the building, its insurers, the property manager, a third-party administrator (TPA), and two individual adjusters assigned to inspect and adjust the water loss claim.
Reprinted courtesy of
Kathleen A. Nelson, Lewis Brisbois and
Jonathan R. Missen, Lewis Brisbois
Ms. Nelson may be contacted at Kathleen.Nelson@lewisbrisbois.com
Mr. Missen may be contacted at Jonathan.Missen@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Engineers Found ‘Hundreds’ of Cracks in California Bridge
January 24, 2014 —
James Nash – Bloomberg NewsEngineers spotted “hundreds” of cracks in welds on parts produced for the San Francisco-Oakland Bay Bridge in 2008 and were encouraged to stay quiet rather than delay the $6.4 billion project, according to a California Senate committee report.
James Merrill, then a senior engineer with a quality assurance company known as Mactec, told Senate investigators that his complaints about work done at Shanghai Zhenhua Heavy Industry Co. Ltd. (900947), known as ZPMC, were rebuffed by managers of the California Department of Transportation as “too rigorous,” according to the report released yesterday.
Read the court decisionRead the full story...Reprinted courtesy of
James Nash, Bloomberg NewsMr. Nash may be contacted at
jnash24@bloomberg.net
Nobody Knows What Lies Beneath New York City
August 10, 2017 —
Greg Milner - BloombergBefore a single raindrop fell, Alan Leidner knew the waters could rise and throw the city into darkness. On this point, the maps were as clear as a crystal ball. All you had to do was look.
It was 2010, and Leidner was consulting for the government services company Booz Allen Hamilton Inc., contracted by the U.S. Department of Homeland Security to identify potential threats and vulnerabilities in the nation’s critical infrastructure. Leidner was examining a region that included New York and New Jersey. One day he was thinking about the area’s electrical power grid. He consulted some flood projection maps the Federal Emergency Management Agency had prepared. Then he stared at a map of the grid maintained by Consolidated Edison Inc., the region’s power supplier. And it just jumped out at him: The substation at East 13th Street, on the banks of the East River, was smack in the middle of a flood zone.
Leidner voiced his concerns with utilities, hospitals, and other major facilities. “The reaction was mostly, ‘Eh,’ ” he recalls, as we sit in the Tribeca offices of the Fund for the City of New York, where he directs the nonprofit organization’s Center for Geospatial Innovation.
Read the court decisionRead the full story...Reprinted courtesy of
Greg Milner, Bloomberg
Corrective Action Protest Grounds for GSA Schedule Federal Construction Contractors
September 09, 2024 —
Marissa L. Downs - The Dispute ResolverA contract awarded, protested, terminated, appealed, then reinstated. It’s no secret that federal construction procurements are plagued with uncertainty. From delays, constructive suspensions, compromised supply chains, the litigation-laden critical path method, and the mandate for all construction materials used in federally funded projects for infrastructure to be produced in the United States under the Build America, Buy America Act (BABAA) (to name just a few traditional and emerging favorites), just one of these issues could fill the rest of anyone’s month with substantive research. To add one more, which is entirely unique to bid protests, federal contractors–including construction contractors–listed in a General Service Administration (GSA) Schedule may have new grounds to have a contract award reinstated that was terminated by a federal agency pending a GAO decision.
GAO Protest
An initial GAO protest filed by Deloitte & Touche LLP (Deloitte) argued that the National Geo-Spatial Intelligence Agency (Agency) wrongfully made an award to Kearney & Company, P.C. (Kearney) when the Agency: (1) improperly evaluated quotes; and (2) failed to conduct a proper best-value tradeoff analysis. At issue was a competed task order with Kearney under a GSA FSS multiple-award contract. Before the GAO issued an opinion, however, it held an unrecorded predictive-outcome conference with Deloitte and Kearney where the only mutual consensus was the likely ineligibility of all offerors for the relevant award. The Agency subsequently elected to take corrective action, terminating Kearney’s contract award for convenience, amending the solicitation to avoid issues (including undisputed issues) addressed in the GAO protest. After the Agency adopted their corrective action, the GAO protest was dismissed as academic and moot.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
No Coverage for Repairs Made Before Suit Filed
August 22, 2022 —
Tred R. Eyerly - Insurance Law HawaiiAfter a hurricane damaged the building the insured was constructing, there was no coverage under the CGL policy for repairs the insured made in the absence of a suit being filed. Planet Construction J2911 LLC. v. Gemini Ins. Co., 2022 U.S. Dist. LEXIS 105468 (W.D. La. June 13, 2022).
Planet Construction was a general contractor hired to build a fitness club. On August 27, 2020, Hurricane Laura struck the area. After the storm, a pipe in the sprinkler system broke, allegedly due to faulty materials and workmanship by a subcontractor, S&S Sprinkler. Planet Construction sought coverage under its policy with Gemini as well as under S&S's policy with Zurich. Both insurers denied coverage and Planet Construction filed suit.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
LEEDigation: A Different Take
June 22, 2020 —
Christopher G. Hill - Construction Law MusingsThis weeks Guest Post Friday at Musings is a real treat. Sara Sweeney is a registered architect, LEED AP and GreenFaith Fellow in religious environmental leadership. Her 18-year architectural career reflects her passion and commitment to sustainable building design and stewardship of our natural environment. She is the founder of EcoVision LLC, a solutions-based research and consulting firm, grounded in sustainable design practices, environmental stewardship, and building science.
Dude
Every so often I come across a word that drives me nuts. A few years ago it was ‘Dude.’ Lately, it is ‘LEEDigation.’ It’s a new term to “describe green building litigation” coined by Chris Cheatham, a fine person and very knowledgeable attorney in construction law and a LEED AP as well. Per his definition, LEEDigation “could involve disputes arising from green building certification, could arise if a project fails to obtain government incentives or satisfy mandates for green building construction, or could simply result from improperly designed or constructed green building strategies. It all makes sense. So why does it drive me nuts?
Round Peg. Square Hole.
Although I fully understand why the term was coined, such a term keeps us in flat world, that is, the world of conventional design and construction. Designing and building to LEED standards, or rather, just designing and building sustainably in general, whether to meet a third party standard or not, is a different way than what we have been used to. Period. Whereas our conventional way is focused on first costs, and sees the building more as a commodity than the human imprint and legacy on Earth, sustainable design and building is a process which, at its best, considers the economic impacts of NOT building responsibly. It is a more holistic way of building and balances long-term costs and implications with short term costs.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Eyerly may be contacted at
te@hawaiilawyer.com
Pennsylvania Reconstruction Project Beset by Problems
October 15, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Pittsburgh Post-Gazette reported that “[t]he Penn Avenue reconstruction project in Garfield, described as ‘a comedy of errors’ by one neighborhood leader, remains months behind schedule and has gone well over budget.”
The $4.7 million construction budget has increased “by at least $800,000,” according to the Pittsburgh post-Gazette. Problems included the underground utilities not on maps or mapped inaccurately, water lines breaking, and old streetcar tracks were discovered to have contaminated soil.
Rick Swartz, executive director of the Bloomfield-Garfield Corp., told the Gazette that the project has been “plagued with problems and poor communication from the very start.”
Read the court decisionRead the full story...Reprinted courtesy of