Florida’s Citizens Property Insurance May Be Immune From Bad Faith, But Is Not Immune From Consequential Damages
July 15, 2019 —
Michael S. Levine, Andrea DeField & Daniel Hentschel - Hunton Insurance Recovery BlogA coverage dispute arising as a result of property damage from Hurricane Frances, which occurred in 2004, will continue following a Florida appellate court decision in an action brought against Citizens Property Insurance Corp.
The insureds, Manor House, LLC, Ocean View, LLC, and Merrit, LLC, presented a claim to Citizens for damage sustained at nine apartment buildings as a result of Hurricane Florence. After payments for a portion of the property damage were sustained, Citizens continued to dispute the full amount due. Meanwhile, the insureds suffered lost rental income because of the delay. Ultimately, the insureds filed suit against Citizens alleging, among other things, breach of contract and fraud, and sought to recover extra-contractual damages for loss of rental income due to the delay in adjusting and repairing the damaged property.
The trial court granted Citizens’ motion for partial summary judgment on several issues, including Citizens’ motion for partial summary judgment regarding appraiser and umpire fees; motion for partial summary judgment to prevent the insureds from pursuing a claim for extra-contractual, consequential damages; and motion for judgment on the pleadings on the insured’s claim for fraud.
Reprinted courtesy of Hunton Andrews Kurth attorneys
Michael S. Levine,
Andrea DeField and
Daniel Hentschel
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. DeField may be contacted at adefield@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Hawaii Court Finds No Bad Faith, But Negligent Misrepresentation Claim Survives Summary Judgment in Construction Defect Action
November 06, 2013 —
Tred Eyerly — Insurance Law HawaiiJudge Mollway, U.S. District Court Judge for the District of Hawaii, found the insurer was not in bad faith for allegedly leading its insured to believe that construction defects would be covered under the policy. The court, however, allowed the insured's negligent misrepresentation claim to survive summary judgment. Ill Nat'l Ins. Co v. Nordic PCL Constr., 2013 U.S. Dist. LEXIS 151748 (D. Haw. Oct. 22, 2013).
The insurer denied coverage when Nordic was sued for construction defects related to its construction of two Safeway stores in Honolulu. Prior to the issuance of the policies the Ninth Circuit had issued its opinion in Burlington Ins. Co. v .Oceanic Design & Constr., Inc., 398 F.3d 940 (9th Cir. 2004), which predicted that Hawaii appellate courts would rule that construction defects were not "occurrences." Nevertheless, Nordic's witnesses contended when the policies were purchased, they believed construction defects were covered. Specifically, Nordic thought the policies provided completed operations coverage for property damage arising out of Nordic's subcontractors' work.
Nordic further contended that only after the Hawaii Intermediate Court of Appeals decided in Group Builders, Inc. v. Admiral Ins .Co., 123 Haw. 142 (Haw. Ct. App. 2010) that construction defect claims did not constitute an "occurrence" did the insurer change its position and decide the policies did not cover construction defects.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
More Construction Defects for San Francisco’s Eastern Bay Bridge Expansion
October 01, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to SF Gate, almost “every one of the 423 steel rods that anchor the tower of the new Bay Bridge eastern span to its base has been sitting in potentially corrosive water, Caltrans officials said Tuesday — one of the most serious construction defects found yet on the $6.4 billion project.”
About a year ago, “steel rods crucial to seismic-stabilizing structures on the bridge snapped when they were tensioned.” Fixing those rods cost $25 million, while an additional $20 million had been spent determing if “additional rods and bolts are at risk of failing.”
In regards to the latest construction defects discovered, Caltrans’ chief engineer on the project, Brian Maroney, stated, “It’s not acceptable, and we’re going to fix it.”
Read the court decisionRead the full story...Reprinted courtesy of
Henderson Engineers Tests AI for Building Systems Design with Torch.AI
September 26, 2022 —
Aarni Heiskanen - AEC BusinessTorch.AI is testing a new artificial intelligence application with Henderson Engineers, a national building systems design firm, to unlock the creative and problem solving potential of the firm’s more than 1,000 employees.
Henderson Engineers is a building systems design and engineering firm that works on projects across the business, community, health, retail, and venue sectors. Their projects include many high-profile projects, such as SoFi Stadium, host site for the 2022 Super Bowl. They know how the industry relies on highly complex information contained in equally complex unstructured data: drawings, images, PDFs, handwriting, raw text.
Earlier this year, Henderson began testing new artificial intelligence from
Torch.AI that could learn to read complex construction and engineering documents and diagrams.
“When Kevin Lewis, Henderson’s CEO, and I got together to first discuss the partnership, I could tell they were already thinking way ahead of everyone else,” says Brian Weaver, Chairman and CEO of Torch.AI. “As an engineering firm they are meticulous, thoughtful, strategic. We quickly saw the potential impact these new AI systems could have for their amazingly talented teams and are excited to continue growing our relationship.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Update Regarding New York City’s Climate Mobilization Act (CMA) and the Reduction of Carbon Emissions in New York City
July 05, 2021 —
Caroline A. Harcourt, Natalie S. Starkman & Nika Bederman - Gravel2Gavel Construction & Real Estate Law BlogIn a previous post, we described how the New York City Climate Mobilization Act, 2019 (the CMA, or Local Laws 92, 94, 95, 96, 97, and 147 enacted in 2019) was passed with the goal of reducing New York City’s carbon emissions by 40 percent by 2030 and by 80 percent by 2050 (as against a 2005 baseline as provided for in item 3 of Local Law 97). It is the most ambitious building emissions law to be enacted by any city in the world. The CMA impacts “Covered Buildings” (described below) and, besides contemplating the retrofitting of Covered Buildings to achieve energy efficiency and establishing a monitoring program for Covered Buildings, the CMA contemplates compliance by means of the purchase of carbon offset credits or renewable energy. (Note the new NYC Accelerator program, launched in 2012 by the Mayor’s Office of Sustainability, provides guidance regarding energy-efficient upgrades to properties and emission reductions.)
Pursuant to the CMA:
- Beginning in 2024, Covered Buildings will have to meet the first emission targets, which are calculated by multiplying the gross floor area of each Covered Building by the occupancy classification as set forth in Local Law 97; and
- In 2025, owners of Covered Buildings will need to establish compliance by submitting a report establishing such compliance (prepared by a certified design professional) to the newly created Office of Building Energy and Emissions Performance.
Read the court decisionRead the full story...Reprinted courtesy of
Caroline A. Harcourt, PillsburyMs. Harcourt may be contacted at
caroline.harcourt@pillsburylaw.com
Points on Negotiating Construction Claims
December 30, 2013 —
CDJ STAFFEugene Heady of Smith Currie and Hancock offers some pointers on the effective negotiation of construction claims. He notes that “claims and disputes in the construction industry are commonplace,” but that “settlement usually comes after much pain, suffering, and expense.” He offers nine points to consider when negotiating construction claims.
His first two points are to develop a claim position and then document that claim. He says that “the facts underlying the claim should be nonnegotiable.” The documentation “suggests to your opponent that you have done your homework and are serious about the pursuit of your claim.” He also notes that you need to understand the strengths and weaknesses of your position.
On the other side, you need to “understand your opponent’s positions,” and also “your opponent’s strengths.” He points out that “an appreciation for what is truly important to your opponent is the starting point for the development of creative solutions to the dispute.
Further, bargaining should be done in good faith, negotiation should be done on the merits, and you are well advised to “choose a seasoned and skilful negotiator. “A prolonged and expensive legal battle is not likely to change the outcome,” he warns.
Read the court decisionRead the full story...Reprinted courtesy of
Rio Olympic Infrastructure Costs of $2.3 Billion Are Set to Rise
January 31, 2014 —
Tariq Panja and David Biller – BloombergBrazilian authorities announced 5.6 billion reais ($2.3 billion) will be spent on infrastructure directly related to the 2016 Rio de Janeiro Olympic Games and those costs will rise as projects are added.
Yesterday’s announcement comes months behind schedule, and after pressure on public bodies to reveal exactly how much it will cost for Rio to be the first South American city to host the quadrennial showpiece. Delays and cost overruns to several projects related to this year’s soccer World Cup have sharpened the focus on the Olympics.
“We are committed to being on schedule,” Sports Minister Aldo Rebelo said at a press conference in Rio to announce the spending plans. “It is the first time we have a consortium of three levels of government. It is in an effort to ensure the success and execution of all the commitments to deliver the Olympics in Rio in 2016.”
Mr. Panja may be contacted at tpanja@bloomberg.net and Mr. Biller may be contacted at dbiller1@bloomberg.net.
Read the court decisionRead the full story...Reprinted courtesy of
Tariq Panja and David Biller, Bloomberg
Traub Lieberman Partners Ryan Jones and Scot Samis Obtain Affirmation of Final Summary Judgment
February 28, 2022 —
C. Ryan Jones & Scot E. Samis - Traub LiebermanTraub Lieberman Partners Ryan Jones and Scot Samis recently obtained affirmation of final summary judgment in favor of a windstorm and general insurance provider (“Insurer”) in the Florida First District Court of Appeal. The Appellant, a restoration service provider (“Restoration Service”), provided emergency mitigation services in the wake of hurricane damage to a residential home that was covered by an insurance policy issued by the Insurer. The Restoration Service invoiced the Insurer and, following an investigation, the Insurer paid a portion of the invoiced amount and invoked the policy’s appraisal clause to resolve the dispute over the difference. The Restoration Service brought suit against the Insurer, arguing that the appraisal process did not apply to mitigation services. The Insurer countered that it was entitled to resolve the claim by appraisal and, following arguments, the Court determined that the appraisal provision applied to mitigation services.
Reprinted courtesy of
C. Ryan Jones, Traub Lieberman and
Scot E. Samis, Traub Lieberman