Hybrid Contracts for The Sale of Goods and Services and the Predominant Factor Test
February 15, 2021 —
David Adelstein - Florida Construction Legal UpdatesFlorida’s Uniform Commercial Code (also known as the UCC) applies to transactions for goods. “Goods” is defined by Article II of the UCC as “all things (including specially manufactured goods) which are movable at the time of identification to the contract for sale other than the money in which the price is to be paid, investment securities (chapter 678) and things in action.” Fla. Stat. s. 672.105(1).
The UCC does NOT apply to transactions for services. Transactions for services are governed by common law.
Oftentimes, transactions or contracts include BOTH goods and services. In this scenario, referred to as a hybrid contract, does the UCC or common law apply? In this scenario, courts apply the predominant factor test to determine whether the UCC or common law governs the transaction:
Whether the UCC or the common law applies to a particular hybrid contract depends on “whether the[ ] predominant factor, the [ ] thrust, the[ ] purpose [of the contract], reasonably stated, is the rendition of service, with goods incidentally involved (e.g., contract with artist for painting) or is a transaction of sale, with labor incidentally involved (e.g., installation of a water heater in a bathroom).” In such instances, the determination whether the “predominant factor” in the contract is for goods or for services is a factual inquiry unless the court can determine that the contract is exclusively for goods or services as a matter of law.
Allied Shelving & Equipment, Inc. v. National Deli, LLC, 154 So.3d 482, 484 (Fla. 3d DCA 2015) (citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
General Liability Alert: A Mixed Cause of Action with Protected and Non-Protected Activity Not Subject to Anti-SLAPP Motion
February 18, 2015 —
Valerie A. Moore, Lawrence S. Zucker II and Blythe Golay – Haight Brown & Bonesteel LLPIn Baral v. Schnitt (filed 2/5/2015, No. B253620), the California Court of Appeal, Second Appellate District, held that California’s anti-SLAPP statute does not authorize the striking of allegations of protected activity in a cause of action that also contains meritorious allegations of non-protected activity not within the purview of the statute. In so holding, the court attempted to resolve, or at least add its voice to, the growing conflict among appellate districts on the issue.
A SLAPP lawsuit (Strategic Lawsuit Against Public Participation) seeks to chill or punish the exercise of constitutional rights to free speech and to petition the government for redress of grievances. California’s Legislature enacted the anti-SLAPP statute to permit a defendant to file a special motion to strike as to any cause of action that arises out of an act in furtherance of such rights. In Baral, the plaintiff alleged that his business partner had violated fiduciary duties in usurping the plaintiff’s ownership and management interests in their jointly owned company, so that the defendant could benefit from a secret sale of the company. The complaint alleged that the defendant hired a public accounting firm and prevented the plaintiff from participating in its investigation in order to force the plaintiff's cooperation of the sale of the company. The defendant filed an anti-SLAPP motion, seeking to strike all references to the accounting firm's audit. The trial court denied the motion, on the ground that the anti-SLAPP statute applies to causes of action, not allegations.
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Valerie A. Moore,
Lawrence S. Zucker II and
Blythe Golay
Ms. Moore may be contacted at vmoore@hbblaw.com.
Mr. Zucker may be contacted at lzucker@hbblaw.com.
Ms. Golay may be contacted at bgolay@hbblaw.com.
Read the court decisionRead the full story...Reprinted courtesy of
Proposition 65: OEHHA to Consider Adding and Delisting Certain Chemicals of Concern
September 03, 2015 —
Lee Marshall & Jeffrey A. Vinnick – Haight Brown & Bonesteel LLPThe Office of Environmental Health Hazard Assessment (“OEHHA”), which is responsible for determining the chemicals that are included on its list of chemicals known to be carcinogenic or to cause reproductive harm, thereby requiring businesses to comply with the rules accorded under California’s Proposition 65, has announced the beginning of a 45-day public comment period on five chemicals:
- Nickel
- Pentachlorophenol
- Perfluorooctanoic acid (PFOA)
- Perfluorooctane sulfonate (PFOS)
- Tetrachloroethylene
Reprinted courtesy of Lee Marshall, Haight Brown & Bonesteel LLP and Jeffrey A. Vinnick, Haight Brown & Bonesteel LLP
Mr. Marshall may be contacted at lmarshall@hbblaw.com
Mr. Vinnick may be contacted at jvinnick@hbblaw.com
Read the court decision
Read the full story...
Reprinted courtesy of
Named Insured’s Liability Found Irrelevant to Additional Insured’s Coverage Under a Landlords and Lessors Additional Insured Endorsement
November 16, 2020 — Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLP
In Truck Ins. Exchange v. AMCO Ins. Co. (No. B298798, filed 10/26/20), a California appeals court held that even though the named insured restaurant-lessee was found not liable for premises liability to injured restaurant patrons, the respective liability of the named and additional insured was irrelevant to the landlord-lessor’s coverage for injuries “arising out of” the lessee’s “use” of the premises under a landlords, managers or lessors of premises additional insured endorsement on the lessee’s general liability policy.
In Truck v. AMCO, restaurant patrons were injured when a vehicle crashed into the restaurant while they were dining. The landlord was aware of a similar accident that happened several years before, but the current lessee operating the restaurant was not. The patrons sued the lessee, alleging negligence and premises liability for failing to take precautionary measures and safeguard the patrons. On learning of the prior incident, the patrons added the landlord, alleging that it should have protected the property from a recurrence by reinforcing the door and installing bollards by the street.
Reprinted courtesy of Christopher Kendrick, Haight Brown & Bonesteel LLP and Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com Read the court decision
Read the full story...
Reprinted courtesy of
Extreme Weather Events Show Why the Construction Supply Chain Needs a Risk-Management Transformation
July 24, 2023 — Brad Barth - Construction Executive
A perfect storm of recent extreme weather events has exposed the fragility of North America’s construction supply chains amid an increasingly fluctuating, fast-changing risk landscape. Supply chains that were already reeling from resurgent demand for raw materials coming out of the pandemic have been further disrupted by major storms such as recent tornados in Arkansas and Mississippi. Such events can have a ripple effect across many distinct supply lines as exemplified when the 2021 Texas freeze caused railroad closures and knocked out both petrochemical and semiconductor plants, causing shortages that affected construction and many other industries.
The wide-ranging reverberations from these events demonstrate how stakeholders across all stages of capital projects increasingly share common vulnerabilities. Crucially, the way in which disruption from extreme weather events has caused project delays and cost overruns shows how time, cost and scope are increasingly interlinked and equally vulnerable to systemic risks.
Traditional project-management methods where risks are not collectively managed and mitigated by all stakeholders are becoming increasingly inadequate, as risks to cost, time and scope are often considered in isolation. The domino effect of supply-chain disruption across capital projects similarly shows the inadequacy of project-management models where suppliers are not afforded a key stake in the project (or sometimes even a seat at the planning table). This traditional model cannot adapt to sudden, systemic risks that disrupt multiple suppliers and ripple out across all stakeholders, deliverables and project-management metrics.
Reprinted courtesy of Brad Barth, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decision
Read the full story...
Reprinted courtesy of
President Trump’s Infrastructure Plan Requires a Viable Statutory Framework (PPP Statutes)[i]
April 13, 2017 — John P. Ahlers - Ahlers & Cressman PLLC
Although we live in a politically-divided nation, there is one issue on which there seems widespread agreement: our country requires a massive upgrade to its infrastructure. Rundown airports, crumbling highways, obsolete ports, and dangerous bridges are now endemic across the United States. By contrast, Asian airports and elegant European bridges and rails show that our country needs an upgrade, the cost of which will be enormous.
President Trump promised to revitalize America’s aging roads, bridges, railways, and airports. He chose Wilbur Ross for Commerce Secretary and professor of Conservative Economics and Public Policy, Peter Navarro, to formulate an infrastructure plan. Navarro and Ross recommended that the government allocate $137 billion in tax credits for private investors who underwrite infrastructure projects. They estimate that over the next ten years, the credits could spur $1 trillion in investments. That is how much President Trump promised to spend on infrastructure, a key part of his job-creation plan.
His plan involves building the infrastructure with private-money financing. Public Private Partnerships (“PPP”) are not a new concept and have been successful in Canada, Europe, and various U.S. states who have pioneered this method of procurement. Federal tax credits have been used to spur private investment in housing, resulting in tens of thousands of low-income housing developments over the years. The credits are sold to private entities such as banks and equity firms that invest anywhere from $.70 to $1.10 in housing developments for every dollar they receive in credits, a ratio that fluctuates with economic conditions. Read the court decision
Read the full story...
Reprinted courtesy of John P. Ahlers, Ahlers & Cressman PLLC
Mr. Ahlers may be contacted at jahlers@ac-lawyers.com
Colorado Abandons the “Completed and Accepted Rule” in Favor of the “Foreseeability Rule” in Determining a Contractor’s Duty to a Third Party After Work Has Been Completed
January 17, 2013 — Brady Iandiorio, Higgins, Hopkins, McLain & Roswell, LLC
In a recent case, the Colorado Court of Appeals found that a contractor had a duty to a third party to warn it of a dangerous condition, even after the contractor had completed its work and the owner had accepted the contractor’s work. Collard v. Vista Paving Corp., -- P.3d --, 2012 WL 5871446 (Colo. App. 2012). While not an earth shattering or entirely new concept, the decision rendered in Collard directly accepted the foreseeability rule at the expense of the completed and accepted rule. Id.
In Collard, the City of Grand Junction (“the City”) hired Vista Paving Corp. (“Vista”) to construct two road medians according to the City’s plans and designs. On July 9, 2007, Vista began work on the medians. According to its contract with the City, Vista was responsible for traffic control during construction of the medians. On July 19, 2007, Vista completed its construction of both medians. On that date, the City’s project inspector conducted his final inspection of Vista’s work. The City’s inspector then told Vista that its work had been completed and that Vista was authorized to leave the site. Vista requested permission to remove the traffic control devices to which the City’s inspector agreed. Vista removed all of its traffic control devices.
Read the court decision
Read the full story...
Reprinted courtesy of Brady Iandiorio
Mr. Iandiorio can be contacted at iandiorio@hhmrlaw.com
New York’s Highest Court Reverses Lower Court Ruling That Imposed Erroneous Timeliness Requirement For Disclaimers of Coverage
June 18, 2014 — Robert F. Walsh and Paul A. Briganti – White and Williams LLP
On June 10, 2014, the New York Court of Appeals (the state’s highest court) issued a unanimous decision in KeySpan Gas East Corp. v. Munich Reinsurance America, Inc. (No. 110, June 10, 2014), reversing a lower court decision which had erroneously imposed on insurers a duty to disclaim coverage for property damage claims as soon as possible or risk waiving their coverage defenses. White and Williams represented one of the insurance company defendants in the action.
The case involved an action against three excess insurers for insurance coverage for underlying environmental claims arising from Manufactured Gas Plant sites. Upon receiving notice of the underlying claims, the three insurers reserved their rights to deny coverage on various grounds, including late notice of an occurrence, pending an investigation. The insurers ultimately denied coverage on the basis of late notice several years later based on information developed in discovery in the litigation. The policyholder/plaintiff KeySpan argued that the insurers had unreasonably delayed in issuing their disclaimers and that there was a triable issue of fact on whether such a delay amounted to a waiver of the late notice defense.
Reprinted courtesy of Robert F. Walsh, White and Williams LLP and Paul A. Briganti, White and Williams LLP
Mr. Walsh may be contacted at walshr@whiteandwilliams.com; Mr. Briganti may be contacted at brigantip@whiteandwilliams.com Read the court decision
Read the full story...
Reprinted courtesy of