Indiana Court Enforces Contract Provisions rather than Construction Drawing Markings
January 14, 2015 —
Beverley BevenFlorez-CDJ STAFFTimothy J. Abeska, a vice-chair of Barnes & Thornburg LLP’s Construction Law Practice Group, analyzed Goodrich Quality Theaters, Inc. v. Fostcorp Heating and Cooling, Inc., 16 N.E.3d 426 (Ind. Ct. App. 2014), which “provides an example of a court enforcing contract provisions rather than markings on construction drawings that are inconsistent with contract requirements.”
The case evolved from a dispute on a construction of an IMAX theater, when the general contractor did not understand the architect’s markings for non-standard joist girders, and ordered standard joist girders, per the contract. The error created delays and other problems, which led to payment disputes and mechanic’s liens against the project.
Abeska stated that “[t]his case shows the importance of making sure all documents which comprise a construction contract are consistent with each other, as courts will enforce contracts negotiated by the parties. The case also demonstrates that litigation is not a quick process, as the Court of Appeals Opinion was issued more than seven years after the project was completed.”
Read the court decisionRead the full story...Reprinted courtesy of
Finding Plaintiff Intentionally Spoliated Evidence, the Northern District of Indiana Imposes Sanction
March 14, 2018 —
Shannon M. Warren – The Subrogation Strategist On January 23, 2018, the Northern District of Indiana issued a decision that clarifies what constitutes spoliation of evidence under Indiana law. In
Arcelormittal Ind. Harbor LLC v. Amex Nooter, LLC, 2018 U.S. Dist. LEXIS 10141 (N.D. Ind.), the defendant filed a motion for sanctions, alleging that the plaintiff intentionally spoliated critical evidence. The defendant sought dismissal of the action, asserting that the plaintiff intentionally discarded and lost important physical evidence within hours of a fire that occurred while the defendant’s employees were performing work at its facility. The decision underscores the importance of taking immediate action to properly identify and secure potentially material evidence in order to satisfy ones duty to preserve pre-suit evidence and avoid any spoliation defenses and associated sanctions.
In
Arcelormittal, the court initially considered whether to apply state or federal law when analyzing a litigant’s duty to preserve pre-suit evidence and determine if that party committed spoliation. Since the case was brought in federal court based on diversity jurisdiction, the court held that Indiana state law governed the spoliation analysis.
As noted by the court, under Indiana state law, “the intentional destruction, mutilation, altercation, or concealment of evidence” is considered to be spoliation. Thus, under Indiana law, a party who knew or should have known that litigation was imminent “may not lose, destroy or suppress material facts or evidence.” The plaintiff argued that Indiana law requires a showing of improper purpose or bad faith to establish that a litigant spoliated evidence. The
Arcelormittal court rejected the plaintiff’s argument.
Read the court decisionRead the full story...Reprinted courtesy of
Shannon M. Warren, White and Williams LLPMs. Warren may be contacted at
warrens@whiteandwilliams.com
Top 10 Take-Aways from the 2024 Annual Forum Meeting in New Orleans
May 20, 2024 —
Marissa L. Downs & Brendan Witry - Laurie & Brennan, LLPOver 600 construction lawyers, experts, and consultants met in New Orleans last week for the Forum’s 2024 Annual Meeting where Program Coordinators Brenda Radmacher and Joseph Imperiale together with John Cook and Buck Beltzer put together an insightful program focused on all things construction litigation. Here are our 10 top take-aways from this unique program.
10. Don't underestimate the soft skills that are necessary to effectively represent your clients. There are different ways to measure success when it comes to construction litigation, according to Stephen Dale (WSP USA), Melissa Beutler Withy (Big-D), and Matthew Whipple (Wohlsen Construction). What these (and likely other inside counsel) will look for when retaining outside counsel is the ability to accurately forecast litigation expense and timely communicate case developments. Being able to master these "soft" skills is as important (if not more so) as an attorney's aptitude for trial advocacy. The in-house counsel who hire litigation counsel will be held accountable to deliver results on the investment they are making in legal fees. Outside counsel who cannot manage budgets or avoid surprises in the course of a case will not be successful as litigators.
Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLP and
Brendan Witry, Laurie & Brennan, LLP
Ms. Downs may be contacted at mdowns@lauriebrennan.com
Mr. Witry may be contacted at bwitry@lauriebrennan.com
Read the court decisionRead the full story...Reprinted courtesy of
Delays and Suspension of the Work Under Fixed Price Government Contract
July 22, 2024 —
David Adelstein - Florida Construction Legal UpdatesHere is an interesting fact pattern and case decided by the Civilian Board of Contract Appeals dealing with (1) force majeure type events and epidemics (Covid-19); (2) suspension of the work; and (3) delays. These are three topics important to all contractors including federal contractors.
In Lusk Mechanical Contractors, Inc. v General Services Administration, 2024 WL 1953697, CBCA 7759 (CBCA 2024), a contractor entered into a fixed price contract with the government to repair, replace, and modernize site and building systems at a federal building. The contractor commenced work right before Covid-19. When Covid-19 hit, the government issued the contractor a two-week suspension of work notice on March 27, 2020. The suspension of work allowed off-site administrative work to continue but suspended on-site physical work. The government extended the suspension of work three more times. The contractor could resume work on the exterior on June 1, 2020, but was not permitted to resume work on the interior until July 20, 2020. On the same date that the contractor was able to commence interior work, it submitted a modification for delay caused by the suspension – 64 days for the time period the entire site shutdown, and 51 days for the interior work shutdown.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Homeowner Who Wins Case Against Swimming Pool Contractor Gets a Splash of Cold Water When it Comes to Attorneys’ Fees
February 05, 2024 —
Garret Murai - California Construction Law BlogLooking outside as of late it seems like the glorious, sun-drenched days of Summer are just a nostalgic memory of days long gone. So, to bring back some of those warm-weather memories, I have a swimming pool case for you. Although, like most of the things we write about here on the California Construction Law Blog it’s not all fun-in-the-sun.
The Lee Case
In Lee v. Cardiff, 94 Cal.App.5th 398 (2023), Homeowner Dianne Lee entered into a construction contact with contractor David Brian Cardiff doing business as Advantage Pools Bay Area for a swimming pool and landscaping project totaling $231,500. It must have been quite a pool.
As these things sometimes go, a dispute arose and Cardiff left the job before its was finished. Lee later sued alleging breach of contract, negligent construction and violation of the Contractor State License Law.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Hawaii Appellate Court Finds Duty to Defend Group Builders Case
May 10, 2013 —
Tred EyerlyOn May 19, 2010, the Hawaii Intermediate Court of Appeals determined construction defect claims did not constitute an occurrence under a CGL policy.Group Builders, Inc. v. Admiral Ins. Co., 123 Haw. 142, 231 P.3d 67 (Haw. Ct. App. 2010) ("Group Builders I"). The appeal in Group Builders I, however, only addressed the duty to indemnify. The ICA has now issued a second decision (unpublished), holding that there is was duty to defend Group Builders on the construction defect claims under Hawaii law, based upon the policy language and the allegations in the underlying complaint. Group Builders, Inc. v. Admiral Ins. Co., 2013 Haw.App. LEXIS 207 (Haw. Ct. App. April 15, 2013).
The underlying suit involved allegations by Hilton Hotels Corp. that Group Builders, a subcontractor working on an addition to the hotel, was responsible for mold found after completion of the project. Hilton alleged that the "design, construction, installation, and/or selection of the . . . building exterior wall finish . . . did not provide an adequate air and/or moisture barriers." The counts alleged against Group Builders included breach of contract and negligence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyMr. Eyerly can be contacted at
te@hawaiilawyer.com
Fifth Circuit Confirms: Insurer Must Defend Despite Your Work/Your Product Exclusion
February 14, 2022 —
Nathan A. Cazier & Scott S. Thomas - Payne & FearsThe United States Court of Appeals for the Fifth Circuit recently confirmed that liability insurers have a duty to defend their insureds in construction defect cases when the underlying complaint alleges damage to property beyond the product and work of the insured – even if the complaint merely implies that the insured seeks such damage, without explicitly alleging so. Siplast, Incorporated v. Employers Mutual Casualty Company, No. 20-11076, 2022 WL 99303 (5th Cir. Jan. 11, 2022).
The Archdiocese of New York replaced the roof over Cardinal Spellman High School in the Bronx, using a roofing membrane manufactured by Siplast, Inc. (“Siplast”). After a rainstorm a few years later, school officials reported water damage to the ceiling tiles throughout the school, and repair attempts only made the leaking worse. Siplast disputed that the leaks were its fault and refused to replace the roof, so the Archdiocese sued.
Reprinted courtesy of
Nathan A. Cazier, Payne & Fears and
Scott S. Thomas, Payne & Fears
Mr. Cazier may be contacted at nac@paynefears.com
Mr. Thomas may be contacted at sst@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Home Prices Climbed 0.1% in July as Gains Slowed
September 24, 2014 —
Prashant Gopal – BloombergU.S. home prices rose less than economists estimated in July as investors pull back from the property market.
Prices climbed 0.1 percent on a seasonally adjusted basis from June, the Federal Housing Finance Agency said today in a report from Washington. The average economist estimate was for a 0.5 percent increase, according to data compiled by Bloomberg.
Investors who helped drive up prices are retreating as fewer foreclosures and other discounted homes become available. All-cash purchases in August fell to about 23 percent of the market from the usual 33 percent, the National Association of Realtors reported yesterday. Investors accounted for 12 percent, the least since late 2009.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net