Repair Cost Exceeding Actual Cash Value Does Not Establish “Total Loss” Under Fire Insurance Policy
June 05, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn California FAIR Plan Assn. v. Garnes (No. A143190, filed 5/26/17), a California appeals court ruled that “total loss” under Insurance Code section 2051 refers to physical damage or loss, not the economic fact that the cost of repair exceeds the actual cash value of a home. Thus, where the home is not physically destroyed, the insured is entitled to the actual cost of repair, minus depreciation, even if that amount exceeds the fair market value of the home.
In Garnes, the insured had a fire policy issued by the California FAIR Plan with limits of $425,000. It was agreed that the assessed value of the insured home was only $75,000. The insured suffered a kitchen fire with estimated repair costs of $320,000. The FAIR Plan declared the home a total loss because the cost of repair exceeded the home’s value, and offered to pay the actual cash value as provided by Insurance Code section 2051(b)(1).
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Subrogation 101 (and Why Should I Care?)
July 16, 2023 —
Clark Thiel & Alexis N. Wansac - Gravel2Gavel Construction & Real Estate Law BlogWhat is subrogation? Why am I being asked to waive it? Should I care? To answer that last question, let’s take a quick run at the first two.
What Is Subrogation?
“Subrogation” refers to the act of one person or party standing in the place of another person or party. It is a legal right held by most insurance carriers to pursue a third party that caused an insurance loss in order to recover the amount the insurance carrier paid the insured to cover the loss. This occurs when (i) the insurance carrier makes a payment on behalf of its insured as the result of a covered accident or injury, and then (ii) the insurer then seeks repayment from the at-fault party.
Reprinted courtesy of
Clark Thiel, Pillsbury and
Alexis N. Wansac, Pillsbury
Mr. Thiel may be contacted at clark.thiel@pillsburylaw.com
Ms. Wansac may be contacted at alexis.wansac@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Providing Your Insurer Prompt Notice
May 20, 2024 —
David Adelstein - Florida Construction Legal UpdatesSometimes, when it comes to insurance, you may hear the argument that you breached your insurance policy by failing to provide your insurer with prompt notice as the insurance policy requires. Well, this is not such an absolute issue. With that said, you should absolutely provide your insurer with prompt notice of a claim or loss. No legitimate reason not to. But, if you don’t, it is not an absolute get out of jail free card for your insurer, but it does give them a good argument, which you don’t really want to deal with.
In Gulfpoint Construction Co., Inc. v. Westfield Ins. Co., 2024 WL 1759228 (11th Cir. 2024), an insured appealed a trial court’s ruling that found it did not provide prompt notice to its property insurer as the policy required. In this case, notice was provided two years after a loss from a hurricane. The insurer denied coverage and, in doing so, relied on the insured’s failure to provide prompt notice. Although the trial court agreed, the appellate court found this was a genuine issue of material fact.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The Nightmare Scenario for Florida’s Coastal Homeowners
April 20, 2017 —
Christopher Flavelle - BloombergOn a predictably gorgeous South Florida afternoon, Coral Gables Mayor Jim Cason sat in his office overlooking the white-linen restaurants of this affluent seaside community and wondered when climate change would bring it all to an end. He figured it would involve a boat.
When Cason first started worrying about sea-level rise, he asked his staff to count not just how much coastline the city had (47 miles) or value of the property along that coast ($3.5 billion). He also told them to find out how many boats dock inland from the bridges that span the city’s canals (302). What matters, he guessed, will be the first time a mast fails to clear the bottom of one of those bridges because the water level had risen too far.
“These boats are going to be the canary in the mine,” said Cason, who became mayor in 2011 after retiring from the U.S. foreign service. “When the boats can’t go out, the property values go down.”
If property values start to fall, Cason said, banks could stop writing 30-year mortgages for coastal homes, shrinking the pool of able buyers and sending prices lower still. Those properties make up a quarter of the city’s tax base; if that revenue fell, the city would struggle to provide the services that make it such a desirable place to live, causing more sales and another drop in revenue.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Flavelle, Bloomberg
Pass-Through Subcontractor Claims, Liquidating Agreements, and Avoiding a Two-Front War
April 26, 2021 —
Bradley Sands, Jones Walker LLP - ConsensusDocsSubcontractor claims happen. When those subcontractor claims are prompted by owner actions or responsibilities, the general contractor must always be vigilant to plan for and work to avoid a two-front war in which the general contractor is pushing the owner for recovery while at the same time disputing the subcontractor’s entitlement.
Cooperation between the general contractor and the subcontractor and avoiding that two-front war can be accomplished through pass-through claims and ideally liquidating agreements. A pass-through claim is a claim by the subcontractor who has suffered damages by the owner with whom it has no contract, presented by the general contractor. A liquidating agreement or subcontract “liquidating language” goes a step further than simply a pass-through claim by “liquidating” the general contractor’s liability for the subcontractor’s claim and limiting the general contractor’s liability to the value recovered against the owner. The distinction between pass-through claims generally and use of liquidating agreements or language is described in greater detail below.
Pass-through subcontractor claims are routine in construction and an important, common sense approach to deal with ever-present changes and the unexpected that can have cost and time implications. Despite the common sense basis for subcontractor pass-through claims, there are important legal considerations that must be addressed, and critical planning required, starting with the subcontract clauses.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley Sands, Jones Walker LLPMr. Sands may be contacted at
bsands@joneswalker.com
Water Backup Payment Satisfies Insurer's Obligation to Cover for Rain Damage
February 16, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe insured's attempt to secure additional coverage beyond a $10,000 payment for water damage after a rain storm damaged the interior of its building failed. Bible World Christian Ctr. v. Colony Insurance Co, 2016 U.S. Dist. LEXIS 175766 (M.D La. Dec. 20, 2016).
The interior of Bible World's building was damaged by water that leaked in from the roof after a heavy rain storm. Bible World's officials met with Robert Chandler, an employee of Omni Insurance Group, the day after the rain event. Chandler had assisted Bible World in procuring its commercial property policy with Colony Insurance Company. Chandler told Bible World to fix the property and that its costs would be covered under the policy. Bible World spent $79,876.81 in repairs.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Ready, Fire, Aim: The Importance of Targeting Your Delay Notices
November 08, 2021 —
Bradley Sands, Jones Walker LLP - ConsensusDocsProviding written notice of delay to subcontractors when a project is behind schedule is a regular part of good project documentation practices. A properly targeted delay notice is an important, project correspondence that is an appropriate response to a subcontractor’s specific delay or ongoing delays. However, when a project falls behind schedule and the project management team is in the fog of war, it could seem like a good idea to start firing off project delay notices to any and every subcontractor. While these delay notices may provide a short term burst of productivity, you could find that those same notices are aimed back at you in a future litigation.
This article identifies two potential unintended consequences of sending delay notices that a contractor should keep in its sights and then provides recommendations for properly calibrating future delay notices in light of these potential consequences.
Acceleration: You Might Get What You Ask For
A delay notice to a subcontractor could be interpreted as—or expressly state—direction to the subcontractor to accelerate its work. When a subcontractor is directed to accelerate its work, it may incur additional costs for premium, extended, or overtime labor, additional crews, increased supervision costs, increased overhead costs, and losses due to productivity impacts from the acceleration (e.g., stacking of trades and fatigue). A subcontractor may be entitled to recover these increased costs that are caused by a direction to accelerate.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley Sands, Jones Walker LLPMr. Sands may be contacted at
bsands@joneswalker.com
Personal Thoughts on Construction Mediation
September 20, 2021 —
Christopher G. Hill - Construction Law MusingsConstruction Mediation WorksAs I left a mediation last week at 8:30 at night, I realized something that I knew all along. Mediation works.
Why does mediation work? For several reasons that I can think of.
The first, and likely most important is that lawyers are expensive. In most construction cases, we charge by the hour and those hours build up, especially close to a trial date. A mediated settlement can avoid this sharp uptick in attorney fees that always occurs in the last month before trial. Therefore the earlier the better.
The second is the flexibility to make a business decision. Commercial contractors and subcontractors are in a business, and they should be making business decisions. While one such decision can be to go to litigation; litigation is not always the best solution from a financial, or stress perspective. Construction professionals, with the assistance of construction attorneys, can come up with a creative way to deal with a problem and solve it.
Read the court decisionRead the full story...Reprinted courtesy of