Where Breach of Contract and Tortious Interference Collide
January 11, 2022 —
Christopher G. Hill - Construction Law MusingsClaims for breach of contract are numerous in the construction law world. Without these claims we construction attorneys would have a hard time keeping the doors open. A 2021 case examined a different sort of claim that could arise (though, “spoiler alert” did not in this case) during the course of a construction project. That type of claim is one for tortious interference with business expectancy.
In Clark Nexsen, Inc. et. al v. Rebkee, the U. S. District Court for the Eastern District of Virginia gave a great explanation of the law of this type of claim in analyzing the following basic facts:
In 2018, Clark Nexsen, Inc. (“Clark”) and MEB General Contractors, Inc. (“MEB”) responded to Henrico County’s (“Henrico”) Request for Proposals (“RFP”) for the design and construction of a sport and convocation center (the “Project”). Henrico initially shortlisted Clark and MEB as a “design-build” team for the Project, but later restarted the search, issuing a second RFP. Clark and MEB submitted a second “design-build” proposal, but Henrico selected Rebkee Co. (“Rebkee”) for certain development aspects of the Project. MEB also submitted proposals to Rebkee, and Rebkee selected MEB as the design-builder for the Project. MEB, at Rebkee’s request, solicited proposals from three design firms and ultimately selected Clark as its design partner. From December 2019 to May 2020, Clark and MEB served as the design-build team to assist Rebkee in developing the Project. In connection therewith, Clark developed proprietary designs, technical drawings, and, with MEB, several cost estimates. In February 2020, MEB submitted a $294,334.50 Pay Application to Rebkee for engineering, design, and Project development work. Rebkee never paid MEB. Henrico paid MEB $50,000.00 as partial payment for MEB’s and Clark’s work. MEB then learned that Rebkee was using Clark’s drawings to solicit design and construction proposals from other companies. On July 23, 2020, Rebkee told MEB that Henrico directed it to cancel the design-build arrangement with MEB and Clark and pursue a different planning method. MEB and Clark sued and Rebkee for, among other claims, tortious interference with a business expectancy. Rebkee moved to dismiss the tortious interference claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Colorado Springs may be Next Colorado City to Add Construction Defects Ordinance
October 28, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Gazette reported that Colorado Springs city councilwoman Jill Gaebler stated that “she would bring a proposal to the council next month that would address the construction defects issue.”
Gaebler told The Gazette: “We have gone back and forth with how best to address this issue. It is a statewide concern, so how do we bring forward something that is meaningful to our community without stepping on the toes of our legislators?”
The state of Colorado has tried and failed to pass construction defects legislation three years in a row, according to The Gazette. If Colorado Springs adopts an ordinance, it will become the ninth city to pass construction defects laws.
Read the court decisionRead the full story...Reprinted courtesy of
Insurance Tips for Contractors
December 08, 2016 —
Patrick McNamara - Porter Law GroupMany contractors contentedly accept the insurance policies presented to them by their insurance carriers. However, it is a much better practice to be an active participant in choosing the most appropriate coverage for your business and the specific jobs that you are performing. Use the following tips to be sure your company has the best and most comprehensive coverage.
- Never purchase a Commercial General Liability (“CGL”) policy with a “sunset” provision limiting coverage under Products & Completed Operations liability (P&CO) to a 2, 3 or 4-year term. Why? Because the California statute of limitations for construction defect claims is generally 10 years.
- Never consider a “Claims-made” or “Modified Occurrence” coverage form which also have a built-in limitation as to the length or term of P&CO coverage. Example: If you purchase a claims-made policy and decide to “switch” your insurance to the preferred “occurrence” coverage form, unless a special provision is made prior to the new purchase, the claims-made coverage would become worthless after the sixty (60) day claims-reporting period.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McNamara, Porter Law GroupMr. McNamara may be contacted at
pmcnamara@porterlaw.com
New Homes in Palo Alto to Be Electric-Car Ready
October 01, 2013 —
CDJ STAFFElectric cars are still fairly rare, but if you buy a new home in Palo Alto, you’ll have a place to charge it. The Palo Alto City Council has been enthusiastic about a measure that would require new homes to come wired for car chargers. The hope of the council is that the measure will make owning an electric car “convenient, easy and economical.”
If added to the construction process, the wiring adds about $200 to the cost of the home, far less than the cost of adding it to an existing home. In addition to considering changes in the building code, the city also considered measures that would allow for the operation of public charging stations.
Read the court decisionRead the full story...Reprinted courtesy of
Colorado’s New Construction Defect Law Takes Effect in September: What You Need to Know
September 07, 2017 —
Jesse Witt - The Witt Law FirmColorado’s new construction defect law officially takes effect this month. Although HB 17-1279 was passed in May, the statutory text provides that it only applies “with respect to events and circumstances occurring on or after September 1, 2017.” With that date now upon us, practitioners should be mindful of the law’s new requirements.
The law applies to any lawsuit wherein a homeowner association files a construction defect action on behalf of two or more of its members. “Construction defect action” is defined broadly to include any claims against construction professionals relating to deficiencies in design or construction of real property. Before an association may commence such an action, its board must follow several steps.
First, the board must deliver notice of the potential construction defect action to all homeowners and the affected construction professionals at their last known addresses. This requirement does not apply to construction professionals identified after the notice has been mailed, or to construction professionals joined in a previously-approved lawsuit. The notice must include a description of the alleged construction defects with reasonable specificity, the relief sought, a good-faith estimate of the benefits and risks involved, and a list of mandatory disclosures concerning assessments, attorney fees, and the marketability of units affected by construction defects. The notice must also call a meeting of all homeowners. The notice should be sent to the construction professionals at least five days before the homeowners.
Reprinted courtesy of
Jesse Howard Witt, Acerbic Witt
Mr. Witt may be contacted at www.witt.law
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Is A Miller Act Payment Bond Surety Bound by A Default or Default Judgment Against Its Principal?
February 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesMaguire-O’Hara Construction, Inc. v. Cool Roofing Systems, Inc., 2020 WL 6532852 (W.D. Oklahoma 2020) is an interesting case dealing with suretyship law and the subject of whether a Miller Act payment bond surety is bound by a default or default judgment against its prime contractor (bond principal).
In this case, a subcontractor sued a prime contractor for breach of contract and the contractor’s Miller Act payment bond surety for a breach of the payment bond. The prime contractor did not respond to the lawsuit and the subcontractor obtained a default against the contractor. The Miller Act payment bond surety did engage counsel to defend itself in the dispute. Prior to trial, the subcontractor moved in limine to preclude the surety from raising defenses at trial under the subcontract because a default was entered against the prime contractor. The subcontractor argued that the surety should be bound by the default and, therefore, precluded from raising liability defenses under the subcontract. Such a ruling would leave the surety no defenses disputing liability at trial.
[A] suretys’ liability under the Miller Act coincides with that of the general contractor, its principal. Accordingly, a surety [can] plead any defenses available to its principal but [can]not make a defense that could not be made by its principal.
Maguire-O’Hara Construction, supra, at *2 (internal citations and quotations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction in the Time of Coronavirus
March 30, 2020 —
Christopher G. Hill - Construction Law MusingsOne cannot look look at one’s phone, computer or even the road outside the window without seeing signs of the impact that coronavirus (COVD-19) is having on the world at large. Schools are shut down, traffic is lighter and there is the daily count of new confirmed cases, in Virginia and elsewhere. “Social distancing” is the buzzword of the day. I am writing this post from a home office because of CDC and other guidance regarding the best way to “flatten the curve.” We have all been told to avoid large groups and stay close to home.
All of this is well and good, but construction must go on. In travelling around Richmond, I see construction vehicles on the road quite a bit. This is a good thing. It seems that most of the Richmond, Virginia area contractors are trying to stay as close to “business as usual” as possible while still remaining vigilant and careful to follow CDC and OSHA guidelines on workplace activity and COVD-19. However, the situation is ever changing and government and other outside forces could lead to project slowdowns, project shutdowns or other virus related impacts to everything from permitting to staffing of a project.
As I have discussed, likely ad nauseam, any commercial or residential construction project is controlled by a series of contracts (hopefully well drafted) that control the relationships on the job. Subcontractors in particular have the provisions of their subcontract and those of the prime contract to worry about. One of the major provisions that could trip up any construction professionals on these jobs is the notice provision of the subcontract (thanks for the reminder go to a friend and fellow construction lawyer Mark Cobb at his blog).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Resolving Subcontractor Disputes with Pass-Through Claims and Liquidation Agreements
May 13, 2024 —
Stephanie Cooksey - Peckar & Abramson, P.C.Imagine a project where you are unable to reach final completion due to an unresolved subcontractor claim. If the project owner is responsible for the claim, and both the owner and subcontractor are entrenched in their positions, how would you resolve this dispute?
The default option is a three-party lawsuit where the subcontractor sues you in your capacity as general contractor. By denying the claim, you bring the owner into the lawsuit as a liable party to the subcontractor’s claim. This option is efficient from the judicial system’s perspective, as it means one lawsuit instead of two. The subcontractor cannot sue the owner since the two have no contract between them. Thus, the subcontractor’s recourse is limited to suing the contractor. In the three-party lawsuit, you argue that if the subcontractor prevails in its claim against you, the owner is liable. If the owner successfully defends against the claim, the subcontractor takes nothing.
Putting judicial economy aside, it may not make economic sense for contractors to have a lawyer involved in litigating a case where they have no skin in the game. Fortunately, there is a better option than the three-party lawsuit on multi-party construction projects.
Read the court decisionRead the full story...Reprinted courtesy of
Stephanie Cooksey, Peckar & Abramson, P.C.Ms. Cooksey may be contacted at