Washington School District Sues Construction Company Over Water Pipe Damage
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Yakima Herald reported that “[t]he Toppenish School District is suing a local construction company over a breach of contract that allegedly led to defective water pipes at one of its elementary schools, according to a complaint filed with the Yakima County Superior Court earlier this week.”
According to the complaint (as reported by the Yakima Herald), Toppenish officials alleged that the Huylar Construction Co. failed to install calcium silicate seals during the pipe installation. Furthermore, the complaint stated that last November, the school district discovered “’[e]xtensive corrosion and deterioration’ of the pipes.” Toppenish argued that failure to install the seals is a breach of contract.
Toppenish is suing for about $120,000. The Yakima Herald stated that a Huylar representative “could not be reached for comment.”
Read the court decisionRead the full story...Reprinted courtesy of
Common Flood Insurance Myths and how Agents can Debunk Them
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFProperty Casualty 360 listed four common misconceptions that many homeowners have about flood insurance. First myth on the list was, “I don’t have to worry about flooding because I don’t live near a body of water.” The author pointed out recent floods in desert areas such as Arizona and Nevada.
“I don't qualify for government flood insurance because my property isn’t located in a flood plain,” made number two on the list. According to Property Casualty 360, “NFIP can provide coverage available to any homeowner, regardless of their location.”
Read the court decisionRead the full story...Reprinted courtesy of
No Coverage for Faulty Workmanship Causing Property Damage to Insured's Product Only
October 07, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe Nebraska court found there was no coverage for rebar that did not meet specifications and did not cause property damage to other portions of the construction project. Drake-Williams Steel, Inc. v. Cont'l Cas. Co., 2016 Neb. LEXIS 116 (Neb. Aug. 5, 2016).
The general contractor was hired by the city to build an arena. Drake-Williams Steel, Inc. (DWS) was hired to supply rebar for the arena. The rebar was improperly bent when it was fabricated by DWS and did not conform to the terms of the contract. The rebar was incorporated into three components of the arena: the columns, the grade beams, and the pile caps. The pile caps were made of concrete with reinforcing rebar and were installed below ground level on top of the concrete piles that extended to the bedrock. The grade beams were also made of concrete and rebar. The beams formed an oval around the arena and connected different pile caps together and were also installed below ground level. No corrections were made to the grade beams.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Unintended Consequences of New Building Products and Services
April 19, 2022 —
David S. Jaffe – National Association of Home BuildersAs home builders throughout the United States are grappling with building material price surges, and shortages or delays for certain orders, many are exploring alternatives products to complete or start projects. For example, according to a recent article, some builders are constructing homes from natural materials such as rammed earth, adobe brick, and volcanic rock. In addition to being readily available on site there may be heating and cooling benefits due to the natural insulation provided by these materials. The article cautions, however, that using these alternative materials may come with added challenges such as higher costs due to a need for skilled labor, delays by home inspectors who may be unfamiliar with the techniques and methods of construction, and energy consultants who might have difficulty calculating the value of homes with these materials. See Home Builders Are Turning to Natural Materials to Get Around Supply Chain Problems; There are advantages to buying homes made with natural materials, but expect to pay a premium, Alanna Schubach, Mansion Global (March 25, 2022).
Another caution, not addressed in the article, however, but one that should be heeded by builders considering alternative materials, is the unintended consequences that might result from using alternative products, whether they are natural products or any others. The long-term effects of material use should not be ignored.
For instance, it has been reported that earthen materials are known to contain numerous organic substances and can also harbor mold. It was not too long ago that mold was a high liability issue for builders and property owners. Similarly, the use of rapidly renewable materials - products that can be produced naturally and quickly from nature - is a key component of green building. They are also cellulose or carbohydrate-based products and as such are typically optimal food sources for mold in the presence of moisture.
To avoid mold, it is important to understand the relationship between construction materials and their susceptibility to mold in the presence of moisture. “Buildings will never be designed, built, maintained, or utilized perfectly; and weather and natural disasters cannot be predicted. The one thing we can have complete control over, the materials within the building, should be selected wisely.” See Mold Susceptibility of Rapidly Renewable Building Materials Used in Wall Construction, AM Cooper, Master's thesis, Texas A&M University (2007) (Samples of wool, cork, straw, and cotton-- rapidly renewable materials used as exterior wall insulation products--were exposed to different moisture amounts in an encapsulated environment, representing the environment within a wall cavity when exposed to water from pipes, leaks, condensation and absorption, or from initial construction. The samples were monitored over time for mold growth).
Mold-related issues are just one example of the potential for unintended consequences from the use of alternative materials. Carefully reviewing building material choices in advance may help eliminate non-conforming building materials, returns and possibly disputes. NAHB has developed a guide,
Assessing Building Materials, for builders who may not have their own review process for gathering information from manufacturers and distributors when considering the selection of new building materials.
The guide is intended to arm members with the most important factor when evaluating new materials or products: information. Use the guide to step through the information collection process to make an informed decision on deploying new products or materials. The guide is not intended to be exhaustive or all-inclusive, but it will help builders ask the right questions and seek the most relevant information.
Copyright © 2022 by the National Association of Home Builders of the United States. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
David S. Jaffe, NAHBMr. Jaffe may be contacted at
DJaffe@nahb.org
Nonparty Discovery in California Arbitration: How to Get What You Want
January 08, 2019 —
Leilani L. Jones - Payne & FearsOpting for arbitration requires attorneys to balance efficiency and procedural protections. The implications of arbitration are something clients certainly have to carefully consider both when drafting arbitration provisions, and after initiating a demand. While arbitration can in many respects streamline the civil discovery process, one of the largest roadblocks for cases in California arbitrations is “streamlining” discovery from nonparties. This article explores the challenges presented by third party discovery in arbitration, and proposes strategies for obtaining such discovery efficiently and expeditiously.
Read the court decisionRead the full story...Reprinted courtesy of
Leilani L. Jones, Payne & FearsMs. Jones may be contacted at
llj@paynefears.com
New York Preserves Subrogation Rights
September 06, 2023 —
Lian Skaf - The Subrogation StrategistThe insurer’s right of subrogation is equitable in nature, even if not based in contract. However, since the insurer steps into the shoes of its insured and is limited to the rights of its insured, an integral part of the investigation process is determining what rights the insured has. Whether or not the insured can settle with the tortfeasor and that whether the settlement would also apply to the subrogated carrier is a question the Supreme Court of New York, a trial court, recently addressed.
In Utica First Ins. Co. v. Homeport I LLC, et al., No. 150448/2022, 2023 N.Y. Misc. LEXIS 3087 (N.Y. Sup. Ct.), the plaintiff insurance carrier’s insured, SI Waterfront Management Inc. (SI Waterfront), owned and operated a restaurant called Wynwood at 24 Navy Pier Court in Staten Island, New York. The owner of the property was Homeport I LLC (Homeport). Significant construction work pertaining to plumbing and draining lines at the property was done by Ironstate Holdings, LLC (Ironstate), the plumbing portion of which was conducted by subcontractor Claire Construction Corp. (Claire). As a result of the construction work, on June 8, 2021, SI Waterfront allegedly sustained property damage from flooding.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White and Williams LLPMr. Skaf may be contacted at
skafl@whiteandwilliams.com
Private Statutory Cause of Action Under Florida’s Underground Facility Damage Prevention and Safety Act
July 11, 2021 —
David Adelstein - Florida Construction Legal UpdatesFlorida’s Underground Facility Damage Prevention and Safety Act is set forth in Florida Statutes Chapter 556. Any owner or operator of underground infrastructure as well as contractors that perform underground excavation and demolition operations are familiar (or, need to be familiar) with this Act and the requirements it imposes on them.
In a nutshell, this Act requires excavators to notify operators of underground facilities (e.g., pipelines, cables, sewers) through a notification system before excavating or demolishing an underground location. Then notification system gives the operator of the underground facility two days’ advance notice that an excavation will be taking place. After receiving this notice, the operator of the underground facility must mark the area where its infrastructure is located which could be affected by the underground excavation or demolition operations. The Act further imposes duties on excavators to use increased caution, supervise mechanized equipment, perform excavation and demolition operations in a careful an prudent manner, and to re-notify the notification system if the operator’s marking is no longer visible so the location of the operator’s underground facility can be re-marked.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Homebuilders Call for Housing Tax Incentives
May 10, 2013 —
CDJ STAFFThe National Association of Home Builders has asked Congress to support tax incentives for home buyers and renters, including the Low Income Housing Tax Credit and the mortgage interest deduction. Robert Dietz, an economist at the NAHB, noted that in 2009, 35 million home owners were able to claim the mortgage deduction. Dietz responded to arguments that the deduction simply lead to people buying bigger homes by saying that “the need for a larger home created the higher loan deduction, not the other way around.”
The NAHB notes that one hundred new single-family homes creates more than 300 jobs and generates substantial tax revenues. “Housing provides the momentum behind an economic recovery because home building and associated businesses employ such a wide range of workers” said Dietz.
Read the court decisionRead the full story...Reprinted courtesy of