General Indemnity Agreement Can Come Back to Bite You
October 21, 2019 —
Christopher G. Hill - Construction Law MusingsI talk about payment bonds often here at Construction Law Musings. I talk a bit less about performance bonds and even less about the General Indemnity Agreements (GIA) that are signed by companies and their principals as part of the agreement between a construction company and its bonding company for the provision of these bonds. However, this does not mean that these GIA’s are not important. In fact, these are the agreements that allow a bonding provider to recoup any money paid out pursuant to either a payment or performance bond.
A 2018 case illustrates their importance. In Allegheny Cas. Co. v. River City Roofing, LLC, the Court considered a claim by Allegheny seeking both specific performance of the collateral agreement and reimbursement of certain expenses and investigative costs expended by Allegheny pursuant to its performance bond. Allegheny sought to be reimbursed for certain payments for siding work, investigative costs, and costs spent enforcing the GIA. Allegheny further sought to force the defendants to post sufficient collateral. To do so, Allegheny sued in the Eastern District of Virginia and then moved for summary judgment stating that the GAI uneuivocally required such a result due to the good faith payment for the siding work and the plain language of the GIA.
In response, the Defendants, River City Roofing and its principals that had personally guaranteed the indemnity, argued that the GIA did not apply to the siding work because only the roofing contract was subject to the performance bond and that any bond claims for which collateral was demanded were inchoate and therefore not proper for specific performance.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Avoiding 'E-trouble' in Construction Litigation
September 10, 2018 —
Judah Lifschitz - Construction ExecutiveDuring the 2016 presidential election, the FBI subpoenaed Hillary Clinton's emails after she used a private email server during her time as Secretary of State. Separately, the more recent investigation into Donald Trump’s campaign policy adviser, George Papadopoulos, resulted in scrutiny over both his email and social media.
As shown the above examples, there are damaging effects of electronically stored information in politics, but how does it impact the construction industry?
If not used carefully and properly, emails will serve as “truth serum” in court. Attorneys can simply read an email to know employees’ thoughts or actions, meaning an impulsive email or social media post will most likely come back to haunt the company. Requests for ESI are inevitable in litigation today and the production of inappropriate emails and other ESI open the door for an opposing attorney to argue that a company fosters a culture of uncouth, unprofessional and unfocused project management.
Reprinted courtesy of
Judah Lifschitz, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Lifschitz may be contacted at
lifschitz@slslaw.com
Can an Architect, Hired by an Owner, Be Sued by the General Contractor?
September 10, 2014 —
Craig Martin – Construction Contractor AdvisorAs is often the answer in this blog, maybe. And, it will likely depend on which state’s law is applied. Over the last few weeks, courts around the country have reached differing conclusions on whether a general contractor may sue an architect that it did not hire.
Here’s the situation: The owner hires an architect to draft plans for a project. The project is then put out for bid and the owner hires a general contractor for the work. The general contractor and architect do not enter into a contract with each other.
If, during construction, the general contractor finds fault with the plans, it may seek Request for Information and Change Orders, to shore up the perceived problems with the plans. Ultimately, the general contractor may sue the architect to recover damages it suffered in completing the project.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Colorado Springs may be Next Colorado City to Add Construction Defects Ordinance
October 28, 2015 —
Beverley BevenFlorez-CDJ STAFFThe Gazette reported that Colorado Springs city councilwoman Jill Gaebler stated that “she would bring a proposal to the council next month that would address the construction defects issue.”
Gaebler told The Gazette: “We have gone back and forth with how best to address this issue. It is a statewide concern, so how do we bring forward something that is meaningful to our community without stepping on the toes of our legislators?”
The state of Colorado has tried and failed to pass construction defects legislation three years in a row, according to The Gazette. If Colorado Springs adopts an ordinance, it will become the ninth city to pass construction defects laws.
Read the court decisionRead the full story...Reprinted courtesy of
Gordon & Rees Ranks #5 in Top 50 Construction Law Firms in the Nation
June 29, 2020 —
Gordon Rees Scully MansukhaniGordon Rees Scully Mansukhani has been ranked the #5 construction law firm in the nation by Construction Executive in the magazine’s 2020 ranking of The Top 50 Construction Law Firms. Gordon & Rees is the only California-based law firm to rank in the Top 25.
The firm was ranked in the Top 10 in more specific areas as well.
- #1 in the Top 10 Law Firms Ranked by Most Locations
- #2 in the Top 10 Law Firms Ranked by Number of Construction Attorneys
- #6 in the Top 10 Law Firms Ranked by Number of States Admitted to Practice
“With offices throughout the nation and outstanding construction attorneys in many of those offices, we are able to offer our construction clients a diverse range of legal services wherever they do business,” said
Ernie Isola partner and co-chair of the firm’s construction practice group.
Read the court decisionRead the full story...Reprinted courtesy of
Gordon Rees Scully Mansukhani
California Subcontractor Gets a Kick in the Rear (or Perhaps the Front) for Prematurely Recorded Mechanics Lien
October 21, 2019 —
Garret Murai - California Construction Law BlogCalifornia provides three statutorily recognized construction payment remedies: (1) mechanics liens; (2) stop payment notices; and (3) payment bond claims. Each is intended to provide payment protections for those who furnish labor, materials and services on a construction project. However, each is also different in important ways.
One of those differences has to do with timing. Specifically, when the statutory payment remedy may be used by a claimant. Stop payment notices can be served at any time during a project even before a claimant has completed its work. However, mechanics liens may only be recorded and payment bond claims may only be made after a claimant has completed or ceased performing its work.
In Precision Framing Systems, Inc. v. Luzuriaga, Case No. E069158 (August 29, 2019), the 4th District Court of Appeal examined whether a subcontractor had prematurely recorded a mechanics lien and, thereby, was prevented from filing a lawsuit to foreclose on its mechanics lien.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Separation of Insureds Provision in CGL Policies
August 31, 2020 —
David Adelstein - Florida Construction Legal UpdatesCGL policies contain a “Separation of Insureds” provision. This provision oftentimes states:
Except with respect to the Limits of Insurance, and any rights or duties specifically assigned this Coverage Part to the first Named Insured, this insurance applies:
- As if each named insured were the only Named Insured; and
- Separately to each insured against whom claim is made or “suit” is brought.
This provision is designed to “create separate insurable interests in each individual insured under a policy, such that the conduct of one insured will not necessarily exclude coverage for all other insured.” Evanson Ins. Co. v. Design Build Interamerican, Inc., 569 Fed.Appx. 739 (11th Cir. 2014). This provision also allows one insured under the policy (e.g., additional insured) to sue another (e.g., named insured) without violating potential coverage because there are separate insurable interests. This is a valuable provision in CGL policies.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Recording a Lis Pendens Is Crucial
January 04, 2023 —
David Adelstein - Florida Construction Legal UpdatesIf you are in a construction dispute where you are pursuing a construction lien foreclosure action, recording a lis pendens is crucial. Did I say crucial? “[O]ne purpose of a notice of lis pendens is to alert all others that title to the property is involved in litigation and that ‘future purchasers or encumbrancers of that property’ are at risk of being bound by an adverse judgment.” Henry v. AIM Industries, LLC, 47 Fla.L.Weekly D653b (Fla. 2d DCA 2022). There really is never a reason not to record a
lis pendens when pursing a construction lien foreclosure. Please remember that – don’t forget to record the lis pendens!
There are times a lis pendens is recorded when the lis pendens is NOT based on a duly recorded instrument (e.g., construction lien or mortgage). A
lis pendens, however, is recorded because the dispute is tied to the property in which the lis pendens is being recorded. The lis pendens is recorded to best safeguard the plaintiff’s interest in the real property without fear that the real property will be sold impacting the purpose (and, of course, security) of the lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at