Sometimes It’s Okay to Destroy Evidence
August 17, 2011 —
CDJ STAFFThe Minnesota Supreme Court has ruled in the case of Miller v. Lankow that Mr. Miller was within his rights to remediate his home, even though doing so destroyed the evidence of water intrusion.
Linda Lankow built a home in 1992. In 2001 or 2002, Lankow discovered a stucco problem at the garage which she attributed to moisture intrusion. She asked the original contractor to fix the wall. In 2003, Lankow attempted to sell her home, but the home inspection revealed fungal growth in the basement. Lankow made further repairs, including alterations to the landscaping.
In 2004, Lankow put her house on the market once again and entered into an agreement with David Miller. Miller declined to have an independent inspection, as the home had been repaired by professional contractors.
In 2005, Miller put the house on the market. A prospective buyer requested a moisture inspection. The inspection firm, Private Eye, Inc. found “significant moisture intrusion problems.”
Miller hired an attorney who sent letters to the contractors and to Lankow and her husband. Lankow’s husband, Jim Betz, an attorney, represented his wife and sent a letter to Miller’s attorney that Miller had declined an opportunity to inspect the home.
In 2007, Miller’s new attorney sent letters to all parties that Miller had decided to begin remediation work on the house. All stucco was removed. Miller then filed a lawsuit against the prior owners, the builders, and the realtors.
Two of the contractors and the prior owners moved for summary judgment on the grounds that Miller had spoliated evidence by removing the stucco. They requested that Miller’s expert reports be excluded. The district court found for the defendants and imposed sanctions on Miller.
The Minnesota Supreme court found that “a custodial party’s duty to preserve evidence is not boundless,” stating that “it may be particularly import to allow remediation in cases such as the one before us.” Their reasoning was that “remediation of the moisture intrusion problem in the home may be necessary, even essential, to address immediate health concerns.”
Given that Miller needed to remediate the problem in order to continue living there, and that he had given the other parties a “full and fair opportunity to inspect,” the court found that he was within his rights. The court reversed the judgment of the lower court and remanded it to them for review.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
COVID-19 Response: Recent Executive Orders Present Opportunities for Businesses Seeking Regulatory and Enforcement Relief and Expedited Project Development
June 15, 2020 —
Karen C. Bennett, Jane C. Luxton & Amanda L. Tharpe - Lewis BrisboisWashington, D.C. (June 8, 2020) - Two recent Executive Orders (EO) aimed at promoting economic recovery from the COVID-19 crisis offer regulatory and enforcement relief and encourage agencies to expedite infrastructure project approvals. The May 19, 2020 EO 13924, “Regulatory Relief to Support Economic Recovery,” directs agencies to determine whether previous regulatory reforms would promote economic recovery if made permanent and encourages compliance assistance through exercising enforcement discretion, including declining enforcement. And the June 4, 2020 EO 13927, “Accelerating the Nation’s Economic Recovery from the COVID-19 Emergency by Expediting Infrastructure Investments and Other Activities,” aims to speed up the permitting process for infrastructure projects to strengthen the national economy. As businesses look to move forward and recover from the COVID-19 pandemic, they should closely review these EOs for opportunities to take advantage of streamlined treatment and faster project approvals.
EO 13294 supplements the Administration’s efforts to address the economic crisis brought on by the COVID-19 pandemic by encouraging federal agencies to rescind, modify, waive, or provide exemptions from federal regulations that may inhibit economic recovery and to provide guidance to businesses, particularly small businesses, on what is required of them under federal law for reopening. Specifically, the EO directs agency heads to identify regulatory standards that may inhibit economic recovery and consider rescinding or waiving those regulations, exempting regulated entities from compliance, exercising enforcement discretion, or extending regulatory compliance and enforcement deadlines. It also allows for compliance assistance through accelerated regulatory procedures to receive a pre-enforcement ruling and directs agencies to assess previous regulatory reforms to determine whether making them permanent would promote economic recovery. Since taking office, the Trump Administration has made regulatory reform a cornerstone of its agenda. This Executive Order is a continuation of the aggressive steps taken by the Administration to reduce the regulatory burden faced by American businesses that many argue increases operating costs, inhibits job creation, and stifles economic growth.
Reprinted courtesy of Lewis Brisbois attorneys
Karen C. Bennett,
Jane C. Luxton and
Amanda L. Tharpe
Ms. Bennett may be contacted at Karen.Bennett@lewisbrisbois.com
Ms. Luxton may be contacted at Jane.Luxton@lewisbrisbois.com
Ms. Tharpe may be contacted at Amanda.Tharpe@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Florida’s Fourth District Appeals Court Clarifies What Actions Satisfy Florida’s Construction Defect Statute of Repose
November 14, 2018 —
Rahul Gogineni - The Subrogation SpecialistIn Gindel v. Centex Homes, 2018 Fla.App. LEXIS 13019, Florida’s Fourth District Court of Appeal recently concluded that the date on which the plaintiffs provided a pre-suit notice in compliance with §558.004 of Florida’s construction defect Right-to-Cure statute, Fla. Stat. §§ 558.001 to 558.005, et. seq., is the date on which the plaintiff commenced a “civil action or proceeding,” i.e. an “action,” within the meaning of Florida’s construction defect statute of repose, Florida Statue § 95.11(3)(c). Thus, reversing the decision of the trial court, the Fourth District held that the plaintiffs timely-filed their construction defect action against the defendants.
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com
MetLife Takes Majority Stake in New San Francisco Office Tower
October 21, 2015 —
Hui-Yong Yu – BloombergMetLife Inc. is taking a majority stake in a 43-story office tower being built next to San Francisco’s Transbay Transit Center, expanding the biggest U.S. life insurer’s holdings in one of the country’s most expensive office markets.
MetLife formed a joint venture with Chicago-based John Buck Co. and Golub & Co. for the property, called Park Tower at Transbay, the companies said in a statement before the building’s groundbreaking Tuesday. The tower, which doesn’t yet have a tenant, is scheduled for completion in 2018.
Financial terms of the venture weren’t disclosed. Fred Pieretti, a spokesman for MetLife, said the company will own a majority interest in the building.
Read the court decisionRead the full story...Reprinted courtesy of
Hui-Yong Yu, Bloomberg
NYC Landlord Accused of Skirting Law With Rent-Free Months Offer
October 15, 2024 —
Natalie Wong - BloombergThe opening of Tower 28, one of the tallest residential towers in New York City outside Manhattan, brought rent-stabilized units to Long Island City roughly seven years ago, adding affordable listings to a neighborhood where soaring prices were increasingly squeezing out many renters.
Now, three tenants at the 58-story building have filed a class-action lawsuit alleging the landlord sought to evade New York City rent regulations in order to raise prices even higher over time.
The lawsuit against the limited liability company tied to 42-12 28th St. in Queens claims that the property owner recorded initial rents with the New York State Division of Housing and Community Renewal that were higher than what the first tenant was actually charged and paid. In doing so, any future rent increases were based off a higher figure, according to the lawsuit.
Read the court decisionRead the full story...Reprinted courtesy of
Natalie Wong, Bloomberg
Conspirators Bilked Homeowners in Nevada Construction Defect Claims
March 28, 2012 —
CDJ STAFFCourthouse News has a summary of the current lawsuit over a Nevada conspiracy to defraud homeowners by taking control of homeowner boards and then providing inadequate repairs. Homeowners in eight Las Vegas area communities are involved in the suit, which claims that the conspirators purchased units in the communities and then transferred fractional interests to others to allow them to run for HOA board elections. The suit claims that David Amesbury and his firm helped manipulate the elections.
Once homeowner boards were controlled by the conspirators, Nancy Quon, the construction defect attorney whose recent death appears to be by suicide, handled the litigation against homebuilders. She would settle out of court, engaging Silver Lining Construction to “do very minor and superficial repairs” to the homes. The remainder of the money was split by the conspirators. The suit also notes that the construction defect claims were “frivolous,” and?in addition to the negative publicity?caused the homes to lose at least 5% of their value.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Strategy for Enforcement of Dispute Resolution Rights
May 30, 2018 —
Whitney Judson - Smith CurrieArbitration and litigation each offer their own benefits and drawbacks to litigants looking to resolve a construction dispute. A careful analysis of these benefits and drawbacks may be helpful in determining whether to avoid or pursue either dispute resolution process. Arbitration is oftentimes regarded as the more economically feasible dispute resolution option and is therefore attractive to many construction dispute litigants. Although arbitration may prove to be less expensive than litigation in the long run, some litigants may prefer to file a case in court because the upfront filing fees in litigation are less expensive than the filing fees of arbitration.
Litigants may also prefer the decision makers of one process for dispute resolution over another. Arbitrators in a construction dispute oftentimes have a background in the construction industry, whereas a judge or jury may not. Strategy may dictate whether the preferable decision maker should have experience within the construction industry or be free of any construction industry knowledge and possible biases. The finality of decisions may also be a reason to strategically choose one dispute resolution process over another. Arbitration decisions are overturned only under very narrow and specific circumstances. The losing party in litigation however, has a right to appeal decisions to a higher court and has more options for recourse when the findings of the court are not supported by the evidence or the law.
Read the court decisionRead the full story...Reprinted courtesy of
Whitney Judson, Smith CurrieMs. Judson may be contacted at
wtjudson@smithcurrie.com
Construction Contract Provisions that Should Pique Your Interest
September 30, 2019 —
Christopher G. Hill - Construction Law MusingsConstruction contracts are a big part of my legal practice and the drumbeat here at Construction Law Musings. Why? Because not only does your construction contract set the expectations and “rules of the game” for a construction project, it will be read strictly and literally by the Virginia courts should there be a dispute. For these reasons, construction professionals need to be alert for the language in certain key clauses in a construction contract to assure that these clauses are as balanced as possible and also well understood. Here are my “Top Five”:
- “Pay if Paid”- These clauses are almost always in the subcontracts between a general contractor and a subcontractor and are enforceable in Virginia if drafted correctly and under the proper circumstances.
- Change Orders- Whether work is subject to a change order and the required payment for any changed work are often a key source of contention (read legal fees). A properly drafted and followed change order provision can help avoid much of this contention.
- Indemnity- Much has been made in recent years about indemnity provisions and their enforceability. All parties in the construction payment chain can and should be aware of how to best draft their indemnity provisions to make them enforceable. Failure to do so can be catastrophic.
Read the court decisionRead the full story...Reprinted courtesy of