Additional Dismissals of COVID Business Interruption, Civil Authority Claims
December 29, 2020 —
Tred R. Eyerly - Insurance Law HawaiiAmong the recent decisions dismissing complaints for business interruption and civil authority coverage due to closures caused by COVID-19 are Pappy's Barber Shops, Inc. v. Farmers Group, Inc., 2020 U.S. Dist. LEXIS 166808 (S.D. Calif. Sept. 11, 2020) and Sandy Point Dental v. Cincinnati Insurance Co., 2020 U.S. Dist. LEXIS 171979 (E.D. Ill. Sept. 21, 2020). The difficulty in proving "direct physical loss" was the downfall of both cases.
In Pappy's, claims were made for business income losses insured as a result of local and state closure orders. The policy required "direct physical loss of or damage to property at the described premises." Plaintiffs argued that "direct physical loss of" did not require a tangible damage or alteration to property and that the loss of the ability to continue operating their businesses as a result of the government orders met this requirement.
The court relied upon a prior decision, 10E, LLC v. Travelers Indem. Co. of Connecticut, 2020 U.S. Dist. LEXIS 165252 (C.D. Calif. Sept. 2, 2020) [post here], where the court noted that under California law, losses from inability to use property did not amount to "direct physical loss" within the meaning of the policy.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Colorado Senate Bill 15-177: This Year’s Attempt at Reasonable Construction Defect Reform
February 18, 2015 —
Zach McLeroy – Colorado Construction LitigationOn February 10, 2015, Senators Scheffer and Ulibarri introduced Senate Bill 15-177, which is sponsored in the House by Representatives DelGrosso and Singer. SB 15-177 amends the prerequisites, found in the Colorado Common Interest Ownership Act (“CCIOA”), for an association to file a construction defect action. The bill has been assigned to the Senate Committee on Business, Labor, and Technology but not yet scheduled for hearing.
The major points of the bill include: 1) enforcement of a mediation or arbitration provision contained in the original governing documents of a common interest community, even if subsequently amended or removed; 2) the addition of a requirement that mediation take place before a construction defect action can be filed; 3) heightened requirements that an association board provide advanced notice to all unit owners, together with a disclosure of projected costs, duration, and financial impact of the construction defect claim; 4) the addition of a requirement that the board obtain the written consent of a majority of the owners of units, and; 5) a requirement that prior to the purchase and sale of a property in a common interest community, the purchaser receive notice that binding arbitration may be required for certain disputes.
Read the court decisionRead the full story...Reprinted courtesy of
Zach McLeroy, Higgins, Hopkins, McLain & Roswell, LLCMr. McLeroy may be contacted at
mcleroy@hhmrlaw.com
U.S. Home Prices Rose More Than Estimated in February
May 07, 2015 —
Kathleen M. Howley – BloombergU.S. house prices rose more than economists estimated in February as the strongest labor market in seven years gives Americans the confidence to bid on property.
Prices climbed 0.7 percent on a seasonally adjusted basis from January, the Federal Housing Finance Agency said in a report Wednesday. The average economist estimate was for a 0.5 percent increase, according to data compiled by Bloomberg.
Housing demand is climbing as consumer confidence hovers close to an eight-year high. Sales of existing homes rose in March by the most in four years, the National Association of Realtors reported today. The number of U.S. households jumped by almost 2 million in 2014, according to data compiled by Bloomberg.
Read the court decisionRead the full story...Reprinted courtesy of
Kathleen M. Howley, BloombergMs. Howley may be contacted at
kmhowley@bloomberg.net
Construction Defect Lawsuit Came too Late in Minnesota
June 28, 2013 —
CDJ STAFFThe Minnesota Court of Appeals has upheld a summary judgment in a construction defect case, Lee v. Gorham. Minnesota law requires that contractors warranty that the home will be free of major construction defects during the first ten years, but claims must “be brought within two years of the discovery of the breach.” The Lees received a home inspection report in 2009 that identified a variety of defects, including “several possible structural defects.” The court noted that the report stated, “Contact your builder in writing of the findings, and discuss your options with an attorney.”
The Lees contacted the contractor, Gorham Builders. After initial silence, Gorham told the Lees that problems would “have to be ‘turned over to [the] insurance company.’” Rodney noted in his testimony that he had two choices, to either sue Gorham or hire an outside contractor. Mr. Lee had concluded that the legal costs were likely to be equal to the cost of the contractor.
In June, 2011, the Lees changed their mind about bringing a suit. Gorham sought and received a summary judgment dismissing the case on the grounds that too much time had passed since the Lees learned of the construction defect. The Lees appealed.
The appeals court upheld the summary judgment. The Lees claimed that the 2009 home inspection did not alert them of a “major construction defect,” but the court concluded that the language of the report fit within the Minnesota statutory definition of a “major construction defect.”
Nor was the appeals court convinced that at any time did Gorham provide “assurances that it would cure the defects to the home.” Within the same month as the May 2009 inspection, Gorham had made it clear that any problems were an issue for the insurance company. Thus, the appeals court concluded that the Lee’s equitable-estoppel argument was without merit.
The Lees also brought to appeal the new argument that they did not realize they were dealing with “major construction defects” until they received a subsequent home inspection in 2011. The court noted that the second report does not detail “new defects or structural issues not identified in the 2009 inspection report.” In addition to being “without merit,” the court noted that this claim was not made in the district court and so the appeals court “need not consider this issue on appeal.”
Read the court decisionRead the full story...Reprinted courtesy of
Pass-Through Subcontractor Claims, Liquidating Agreements, and Avoiding a Two-Front War
April 26, 2021 —
Bradley Sands, Jones Walker LLP - ConsensusDocsSubcontractor claims happen. When those subcontractor claims are prompted by owner actions or responsibilities, the general contractor must always be vigilant to plan for and work to avoid a two-front war in which the general contractor is pushing the owner for recovery while at the same time disputing the subcontractor’s entitlement.
Cooperation between the general contractor and the subcontractor and avoiding that two-front war can be accomplished through pass-through claims and ideally liquidating agreements. A pass-through claim is a claim by the subcontractor who has suffered damages by the owner with whom it has no contract, presented by the general contractor. A liquidating agreement or subcontract “liquidating language” goes a step further than simply a pass-through claim by “liquidating” the general contractor’s liability for the subcontractor’s claim and limiting the general contractor’s liability to the value recovered against the owner. The distinction between pass-through claims generally and use of liquidating agreements or language is described in greater detail below.
Pass-through subcontractor claims are routine in construction and an important, common sense approach to deal with ever-present changes and the unexpected that can have cost and time implications. Despite the common sense basis for subcontractor pass-through claims, there are important legal considerations that must be addressed, and critical planning required, starting with the subcontract clauses.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley Sands, Jones Walker LLPMr. Sands may be contacted at
bsands@joneswalker.com
Building Resiliency: Withstanding Wildfires and Other Natural Disasters
September 25, 2023 —
Bill Creedon - Construction ExecutiveAccording to the National Fire Protection Association, between 2016 and 2020 an estimated average of 4,300 fires per year plagued structures under construction, adding up to about $376 million in annual property damage. More recently, the National Centers for Environmental Information reported that wildfires accounted for more than $3.2 billion in damages across the United States. These figures alone point to the heightened awareness that all companies—particularly construction companies—should maintain surrounding the unique challenges and risks that wildfires can present and how they could potentially impact the integrity of projects and the associated safety of their workers.
As North America grapples with the increasing frequency and severity of wildfires, hurricanes and additional severe weather events, numerous industries have had to adapt and implement proactive measures to minimize their risks and associated exposures. The impact of these natural disasters on the construction industry is indisputable, necessitating proactive measures that construction companies should seriously consider adopting to effectively mitigate those risks, efficiently navigate insurance complexities and seamlessly integrate data-driven solutions alongside modern tools like AI and predictive modeling.
Reprinted courtesy of
Bill Creedon, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Creedon may be contacted at
bill.creedon@wtwco.com
No Indemnity Coverage Where Insured Suffers No Loss
November 05, 2014 —
Tred R. Eyerly - Insurance Law HawaiiThe insured subcontractor sought coverage under its Builder's Risk policy for loss despite already being paid under contract the amount sought under the policy. MKB Constr. v. Am Zurich Ins. Co., 2014 U.S. Dist. LEXIS 136096 (W.D. Wash. Sept. 24, 2014).
MKB contracted with the Lower Yukon School District (LYSD) to place gravel fill for a new building pad upon which a school building would be placed in Emmonak, Alaska. The project site was built on tundra that melted in the summer, becoming marshy and pocketed by pools of standing water. LYSD provided the bidding contractors with information stating that settlements of 3 to 9 inches could be expected in areas with 30 inches of fill.
The contract was awarded to MKB, who subsequently realized it had under bid the amount of gravel fill that would be required. The estimated difference in the amount bid and the amount that would be needed was 6,583 cubic yards. LYSD refused to increase the contract price.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Best Practices for Installing Networks in New Buildings
August 14, 2023 —
Patrick Chown - Construction ExecutiveA previous article, "
How to Install Networks in an Old Building," discussed the various challenges of implementing networking infrastructure in older spaces. The building layout, age of the building and use cases were the major challenges involved. New buildings provide an opportunity to incorporate state-of-the-art networking infrastructure from the ground up. Careful planning and foresight are essential to ensure optimal network performance and avoid future issues.
In new buildings, including corporate offices, multifamily residential complexes, hospitals, educational institutions and retail spaces, the potential use cases and users can vary significantly. Each of these spaces comes with its unique networking requirements. Regardless of the specific network applications, there are fundamental frameworks and best practices that can be employed to build a solid network foundation. By following these guidelines and adapting them to the specific needs of your new building, you can ensure a robust and flexible network infrastructure that accommodates ever-evolving technological demands.
Reprinted courtesy of
Patrick Chown, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of