Contractor Succeeds At the Supreme Court Against Public Owner – Obtaining Fee Award and Determination The City Acted In Bad Faith
September 20, 2021 —
Lindsay T. Watkins - Ahlers Cressman & Sleight PLLCA contractor won a rare but much-deserved victory at the Supreme Court on July 8, 2021 in Conway Construction Co. v. City of Puyallup, 197 Wn.2d 825, 490 P.2d 221 (2021). The case, which involved an aggressive stance by a public owner:
- confirmed that the public owner bears the burden of demonstrating a termination for default is justified,
- reaffirmed the requirement to provide an opportunity to cure, and
- rejected the public owner’s attempts to escape its own contract language that the contractor relied upon.
John Ahlers and Lindsay Watkins of Ahlers Cressman and Sleight and Jamie Becker of Osborne Construction submitted the Amicus Brief for the Associated General Contractors (AGC) of Washington in support of Conway to the Supreme Court.
Read the court decisionRead the full story...Reprinted courtesy of
Lindsay T. Watkins, Ahlers Cressman & Sleight PLLCMs. Watkins may be contacted at
Lindsay.Watkins@acslawyers.com
Insurer Not Required to Show Prejudice from an Insured’s Late Notice When the Parties Contract for a Specific Reporting Period
September 09, 2019 —
Christopher Raney - Gordon & Rees Insurance Coverage Law BlogThe Fifth Circuit Court of Appeals recently affirmed an order granting summary judgment in favor of the Firm’s insurer client on an issue of first impression in Texas. The issue before the trial court was whether, under Texas law, an insurer is required to demonstrate prejudice resulting from an insured’s failure to comply with an agreed term set in an endorsement to the parties’ insurance contract establishing a specific time limit for an insured to give the insurer notice of a claim.
The case involved alleged damage to an insured’s commercial property from a hailstorm. The insured did not report the alleged loss to its insurer until approximately 17 months after the date of loss. The insurer denied the claim based on a one-year notice requirement in a policy endorsement. The Texas Windstorm or Hail Loss Conditions Amendment Endorsement stated that:
In addition to your obligation to provide us with prompt notice of loss or damage, with respect to any claim where notice of the claim is reported to us more than one year after the reported date of loss or damage, this policy shall not provide coverage for such claims.
The insured sued the insurer in Houston federal court, alleging causes of action for breach of contract and violations of the Texas Insurance Code. The insured argued the insurer was required to show prejudice from the insured’s late notice; the insurer argued that a showing of prejudice was not required. The trial court recognized that this issue had not been decided by the Texas Supreme Court of the Fifth Circuit Court of Appeals.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Raney, Gordon & Rees Scully MansukhaniMr. Raney may be contacted at
craney@grsm.com
Contractor Walks Off Job. What are the Owner’s Damages?
September 25, 2018 —
David Adelstein - Florida Construction Legal UpdatesWhat are your damages as the result of a breach of the construction contract? This is an important question, right? It is probably the most important part of your case. If you didn’t have damages, you wouldn’t be in a dispute. So, I repeat, what are your damages as the result of a breach of the construction contract? The below case explains dealing with a contractor that elected to walk off the job mid-construction.
In Forbes v. Prime General Contractors, Inc., 43 Fla.L.Weekly D20194a (Fla. 2d DCA 2018), owners hired a contractor to perform a residential renovation job for $276,000. The owners were to pay the contractor in five draw payments (common for residential jobs) where the third draw payment was due upon the contractor’s completion of the dry-in (as defined in the contract). After the contractor received the first two draw payments totaling $138,000 plus an additional $6,000 for updated architectural plans, the contractor claimed the job doubled in price and demanded that the owners pay the contractor the third draw payment immediately (before it was due) plus an additional $31,450. The contractor refused to continue unless the owners agreed to its terms, and then walked off the job when the owners would not agree to these terms (nor should the owners agree to those terms). At the time the contractor walked off the job, the owners’ home was not habitable due to the construction.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
How the New Dropped Object Standard Is Changing Jobsite Safety
January 02, 2019 —
Derek Rose - Construction ExecutiveIn the United States, a dropped object injures a worker every 11 minutes—equating to nearly 50,000 cases every year. For those who seek medical treatment for these types of injuries, it can cost an average of $42,000. In fact, 5 percent of all fatalities on jobsites are due to falling objects, according to the Bureau of Labor Statistics.
These statistics highlight the overwhelming importance of dropped object prevention. OSHA already identifies dropped object incidents under the category of “Struck by Object” in its widely recognized “Fatal Four” list of the four leading causes of fatalities in the construction industry.
Reprinted courtesy of
Derek Rose, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Time Limits on Hidden Construction Defects
November 06, 2013 —
CDJ STAFFFrom the time a home is built, California starts a ten-year countdown, which Alan I. Schimmel, writing at California Lawyer, notes is not a statute of limitations, but a statute of repose. During that time, homeowners might be able file a claim over construction defects that don’t immediately become evident. After that ten-year limit, “any latent defects they discover would have to be corrected using money from their own pockets.”
The readily observable defects, the patent defects, have a four-year limit. Mr. Schimmel focusses on latent defects, “which generally lurk behind walls or underground.” He also notes that “they may cause catastrophic damage before they are even detected.” If a construction defect is found, the “law requires the owner of a single-family residence to notify the builder in writing of the claimed defects.”
Read the court decisionRead the full story...Reprinted courtesy of
Contract Disruptions: Navigating Supply Constraints and Labor Shortages
January 24, 2022 —
Greg Ross & Tim Lynch - Construction ExecutiveThe biggest worries in today’s economy—supply chain disruptions, labor shortages and the worst inflation in decades—are creating big headaches in the construction industry. What’s worse, large projects underway are often based on contracts hammered out pre-pandemic, before the uncertainties and disruptions that spread around the globe with COVID-19. Construction firms find themselves executing on contracts signed when the potential for delayed timelines and rising costs seemed more remote.
A recent report from the U.S. Chamber of Commerce finds almost all contractors (93%) say they are experiencing a shortage of an important product such as steel, lumber or copper. A rising number of companies on commercial projects (54%) also cite difficulty finding skilled workers. Grant Thornton clients, among them some of the country’s biggest construction companies, report that sourcing materials and hiring workers is a bigger challenge today—and more expensive—than at any other time in recent decades.
Reprinted courtesy of
Greg Ross and Tim Lynch, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Appellate Court Endorses Discretionary Test for Vicarious Disqualification of Law Firms Due To New Attorney’s Conflict
February 07, 2018 —
David W. Evans and Stephen M. Tye – Publications & Insights In
California Self-Insurer’s Security Fund et al. v. The Superior Court of Orange County (1/26/2018 – No. G054981), the Fourth Appellate District considered whether vicarious disqualification of a law firm is mandatory or discretionary where an attorney with a conflict joins a firm and the firm enacts an ethical screen to prevent transmission of confidential information between the new attorney and the rest of the firm.
This case arose from an effort by the California Self-Insurer’s Security Fund (the “Fund”) to be reimbursed for workers’ compensation benefits advanced on behalf of the Healthcare Industry Self-Insurance Program (the “Program”). The Fund hired Nixon Peabody LLP (“Nixon Peabody”) to represent it in connection with this matter. In November 2013, represented by members of Nixon Peabody’s San Francisco office, the Fund filed a lawsuit naming 304 members of the Program as defendants. Approximately 170 defendants have since settled.
Two of the non-settling defendants (“Moving Parties”), were represented by Michelman & Robinson, LLP (“M&R”). From approximately 2009 until February 1, 2017, attorney Andrew Selesnick served as Chair of M&R’s Health Care Department at the firm’s Los Angeles office, managing a team of attorneys who represented clients in the healthcare industry. Commencing in 2014, a team of four attorneys at M&R, including Selesnick, represented the Moving Parties and four other defendants, the latter of whom have since settled. Selesnick was actively involved, including participating in a confidential discussion pertaining to Moving Parties’ liability and damages and receiving many e-mails containing communications about the common defense of the remaining 170 defendants.
Reprinted courtesy of
David W. Evans, Haight Brown Bonesteel and
Stephen M. Tye, Haight Brown Bonesteel
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Tye may be contacted at stye@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Mortgage Applications in U.S. Jump 11.6% as Refinancing Surges
October 22, 2014 —
Danielle Trubow – BloombergMortgage applications in the U.S. soared last week as a plunge in borrowing costs led to biggest gain in home refinancing since January 2012.
The Mortgage Bankers Association’s index rose 11.6 percent in the period ended Oct. 17, the biggest gain since January, after a 5.6 percent advance the week before, figures from the Washington-based group showed today.
The refinancing gauge jumped 23.3 percent while the purchase applications measure dropped 4.6 percent.
Read the court decisionRead the full story...Reprinted courtesy of
Danielle Trubow, BloombergMs. Trubow may be contacted at