Duty to Defend Negligent Misrepresentation Claim
April 15, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Kansas Court of Appeals determined that the insurer must defend claims of negligent misrepresentation against its insured. Central Power Sys. & Servs. v. Universal Underwriters Ins. Co., 2014 Kan. App. LEXIS 9 (Kan. Ct. App. Feb. 21, 2014).
Central Power contracted to furnish Eagle Well with 10 oil-rig engines and 10 oil-rig transmissions. Eagle Well alleged that Central Power informed them that the engines and transmissions would be operational without any additional components. As is turned out, the engines could not operate without a wiring harness. Eagle Well had to hire a third party to make wiring harnesses that would meet their needs and to install the wiring harnesses.
Eagle Wells sued Central Power, alleging damages in the form of lost profits for the time it took to make the engines independently operational. Further, damages were incurred due to money needed for the costs of purchasing the wiring harnesses from the third party and attaching the harnesses to the engines. Claims asserted against Central Power included breach of contract, negligence and negligent misrepresentation.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
A Tuesday With Lisa Colon
July 02, 2024 —
Lisa Colon - The Dispute ResolverAs a seasoned construction lawyer, I've always prided myself on being independent and tough. However, my toughness was tested when my life took an unexpected turn. In 2013, I was diagnosed with a genetic cardiomyopathy, a condition which made it harder for my heart to pump blood. That diagnosis in itself was devasting since I had to change many things about the way I lived, including having to abandon running, my favorite hobby. After living 10 years in this new normal, in May 2023, I was told my right ventricle was no longer working and there were no further therapies available. I needed a heart transplant. The journey was long, arduous, and filled with both physical and emotional challenges. This life-altering experience not only gave me a new lease on life but also profoundly changed my perspective on practicing law. In this post, I will share three key lessons I learned from my heart transplant journey that have significantly impacted how I approach my legal practice.
Lesson 1: The Importance of Patience and Persistence
The journey to receiving a heart transplant is often fraught with uncertainty and long waiting periods. My new heart came quickly. I waited 22 days on the transplant list, but for me, the wait seemed interminable, filled with numerous hospital visits, medical tests, and moments of despair. Then came the recovery. The early days were filled with weekly biopsies, unimaginable nerve pain, and days of wondering if things would ever get better. During this time, I learned the true meaning of patience. Each day was a test of my resolve, and giving up was never an option. I had to persist through the toughest days, believing that a positive outcome was possible.
Read the court decisionRead the full story...Reprinted courtesy of
Lisa Colon, Saul EwingMs. Colon may be contacted at
lisa.colon@saul.com
Showdown Over Landmark Housing Law Looms at U.S. Supreme Court
October 01, 2014 —
Greg Stohr – BloombergOver the past four decades, U.S. courts have ruled that plaintiffs making discrimination claims under the Fair Housing Act don’t have to prove intentional bias.
Civil rights advocates simply have to show that lenders, insurers, developers or government agencies acted in ways that had a “disparate,” or unequal, impact on minority groups.
Now, the Supreme Court is weighing whether to hear an appeal from Texas officials who argue that intent to discriminate must be proven and that the “disparate impact” standard is too loose an interpretation of the landmark 1968 law that prohibited discrimination in housing.
Read the court decisionRead the full story...Reprinted courtesy of
Greg Stohr, BloombergMr. Stohr may be contacted at
gstohr@bloomberg.net
Use Your Instincts when Negotiating a Construction Contract
August 07, 2018 —
Christopher G. Hill - Construction Law MusingsI have often discussed the more “mechanical” aspects of contract negotiation and drafting here at Construction Law Musings. However, there is another, less objective (possibly) and more “feel” oriented aspect to construction contracting that can have as big an impact on your construction project. What am I talking about? Your instinct as a construction professional when looking the other party in the eye and getting a feel for the company or individual with whom you are contracting.
Why is this so important? Firstly, and this is a truism, no matter how well drafted your construction contract is (and it should be well drafted and reviewed by an experienced construction attorney), if the other party wishes to “play games” and not honor the terms of that contract, you could still very well end up in litigation with the attendant frustration and expense. Having a great looking, well thought out and at least reasonably “fair” construction contract may make the litigation process somewhat less painful but it does not completely avoid the risk of litigation. If the other party or parties to the contract decide not to pay you or perform as they promised, you are left to enforce whatever contract you have in place.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Insurer Must Defend Additional Insured Though Its Insured is a Non-Party
November 18, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe plaintiff insurer's motion for partial summary judgment seeking an order that defendant insurer was obligated to defend a non-party as an additional insured was granted. Am Empire Surplus Lines Ins. Co. v. Burlington Ins. Co., 2019 N. Y. Misc. LEXIS 4145 (N. Y. Sup. Ct. July 25, 2019).
Quality Building Construction, LLC was the contractor hired to work on exterior facade of a building owned by Central Park West Corporation. The underlying complaint alleged that Quality caused plastic spacers and pedestals used for the penthouse terrace to fall down the roof drain riser. A clog and rainwater backup resulted in water damage to apartment 8A. The resulting damage was allegedly due to the clogged roof drain riser.
Quality subcontracted the work to Mega State, Inc. The subcontract required Mega to indemnify and hold Quality harmless against claims in connection with Mega's work, as well as name Quality as an additional insured on a primary, non-contributory bases under Mega's CGL policy. Burlington issued a policy to Mega naming Quality as an additional insured. American Empire issued a CGL policy to Quality.
Quality was sued in the underlying action, but Mega was not. American Empire tendered a demand for coverage to Mega and Burlington, relying on the agreement between Quality and Mega. Burlington responded that Mega was not liable for the alleged damages. American Empire sued Burlington. Subsequently, Burlington accepted the tender to defend Quality in the underlying action, and reserved rights as to whether Burlington's policy was primary and on the question of indemnification. American Empire agreed to withdraw its suit if Burlington would modify its reservation of rights. Burlington refused.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Terminating the Notice of Commencement (with a Notice of Termination)
July 19, 2017 —
David Adelstein - Florida Construction Legal UpdatesThe notice of commencement is important for purposes of construction lien priority. Stock Bldg. Supply of Florida, Inc. v. Soares Da Costa Const. Services, LLC, 76 So.3d 313, 317 (Fla. 3d DCA 2011) (“[A] notice of commencement serves to determine the priority of liens under the Construction Lien Law.”). A lien relates back in time to the date the notice of commencement was recorded assuming the notice of commencement is still in effect when the lien is recorded (or an amended noticed of commencement is recorded). Lien priority is very important and the reason why a contractor should always want to ensure there is an effective notice of commencement in place rather than an expired notice of commencement.
For the same reasons why a contractor wants to ensure there is an effective notice of commencement, there are times an owner wants to terminate a notice of commencement. An owner may want to terminate the potential priority of a construction lien. For instance, say the owner is refinancing or obtaining a construction loan in the midst of construction. A lender will want to ensure its mortgage maintains first priority and certainly priority over a potential construction lien. Otherwise, why would a lender finance the construction if it does not maintain first priority. It generally will not. Thus, an owner needs to terminate the notice of commencement so that the closing occurs on the loan and the mortgage recorded before a new notice of commencement is recorded and construction continues.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
Dadelstein@gmail.com
Ten Years After Colorado’s Adverse Possession Amendment: a brief look backwards and forwards
September 25, 2018 —
Luke Mecklenburg - Snell & Wilmer Real Estate Litigation BlogIn response to national outrage over an infamous adverse possession case in Boulder, Colorado, in which a lawyer and a judge intentionally took their neighbors’ undeveloped land through adverse possession, the Colorado legislature amended the state’s adverse possession statute (C.R.S. § 38-41-101) to make the claim significantly harder to prove. It did this because it believed “there were insufficient ‘obstacles’ to establishing a claim for adverse possession under the existing law.”[1] Effective July 1, 2008, the amendment created a heightened burden of proof, additional element requirements, and the possibility of a losing defendant recovering money from successful plaintiffs for the value of the land they took and the taxes the defendant had paid on that land.
The Boulder case eventually settled, but the resulting statutory amendments have drastically changed the landscape of Colorado’s adverse possession law. Ten years later, this blog post takes a brief look at the amended statute, the impact it has had, and questions that have yet to be resolved.
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & WilmerMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
Asbestos Confirmed After New York City Steam Pipe Blast
July 21, 2018 —
Eydie Cubarrubia - Engineering News-RecordAsbestos has been found at the site where an underground steam pipe exploded early Thursday morning near the Flatiron building in midtown Manhattan.
Read the court decisionRead the full story...Reprinted courtesy of
Eydie Cubarrubia, ENRMs. Cubarrubia may be contacted at