Does a Contractor (or Subcontractor) Have to Complete its Work to File a Mechanics Lien
January 10, 2018 —
Wally Zimolong - Zimolong LLCYes. There seems to be common misconception that a contractor, subcontractor, or supplier, has six months
from its last day of work on the project to file a mechanics lien. I frequently see mechanics liens whereby the claimant states “Claimants last day of work on the project was X.” However, Section 1502 (49 P.S. Section 1502) of the Pennsylvania Mechanics Lien is clear that a lien must be filed within six month of “the completion of his work.” Under the Lien Law, “completion of the work” is a defined term and means “means performance of the last of the labor or delivery of the last of the materials required by the terms of the claimant’s contract or agreement, whichever last occurs.”
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Agree First or it May Cost You Later
May 08, 2023 —
Bill Wilson - Construction Law ZoneBusiness relationships often begin before parties execute a written agreement containing the terms and conditions by which the relationship will be governed. With little more than a Letter of Intent (“LOI”) or Letter of Award (“LOA”) one party is typically pressured to begin investing time and money to start preliminary work on a project. If such LOI or LOA contains nothing more than an agreement to agree later, the performing party should minimize its investment until the later agreement is executed. A recent court decision in New York confirmed the danger to the performing party under “agreement to agree” provisions.
In Permasteelia North America Corp. v. JDS Const. Group, LLC, 2022 WL 2954131 (N.Y. Sup. CT. 7/22/22), the plaintiff subcontractor allegedly performed $1.9 million worth of preliminary work under nothing more than a LOA with an agreement to agree provision. Issues arose, and the parties never entered any later written agreement. The general contractor refused to pay the plaintiff anything for its preliminary work. In response, the plaintiff filed suit against the general contractor asserting four counts: foreclosure of its lien, breach of contract, unjust enrichment, and account stated. All four counts were based on an alleged oral “handshake deal” for subcontract work for the project. The general contractor’s LOA stated that neither party would be bound “unless and until the parties actually execute a subcontract.” During discovery, the plaintiff admitted that neither party intended to enter into any contract until its potential terms were negotiated, reduced to writing, and signed. Moreover, the plaintiff only offered one set of meeting minutes and a few project agendas to support its alleged “handshake deal.” Once these necessary undisputed facts were confirmed, the defendant moved for summary judgment on all four counts.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com
New York Shuts Down Majority of Construction
March 30, 2020 —
Laura Bourgeois LoBue & Matthew D. Stockwell - Gravel2Gavel Construction & Real Estate Law BlogDue to pressure from construction workers, officials, and some construction workers having tested positive for COVID-19, the Empire State Development Corp. (acting on behalf of Governor Cuomo) has frozen all construction in New York today, with the exception of work on hospitals and health care facilities, transit facilities, roads and bridges, affordable housing and homeless shelters.
As a result, commercial construction and condominium projects are on hold, with the exception of work that must be completed to prevent unsafe conditions. Until now, construction has been considered “essential” in New York.
Reprinted courtesy of
Laura Bourgeois LoBue, Pillsbury and
Matthew D. Stockwell, Pillsbury
Ms. LoBue may be contacted at laura.lobue@pillsburylaw.com
Mr. Stockwell may be contacted at matthew.stockwell@pillsburylaw.com
Read the court decisionRead the full story...Reprinted courtesy of
How Many Bridges Does the Chesapeake Bay Need?
August 03, 2022 —
Ethan McLeod - BloombergSteve Kline, a 7th-generation Marylander, knows well the vacation tradition of driving across the twin spans of the Chesapeake Bay Bridge for trips to the beach resort of Ocean City. His grandfather, an ironworker, helped build the bridge’s first span, which opened in 1952.
He’s also very familiar with another seasonal rite: wading through the infamous miles-long traffic backups that last from Memorial Day through the end of summer.
But Kline, president of the nonprofit Eastern Shore Land Conservancy, is not on board with the state’s proposed multibillion-dollar fix — a new 4.3-mile-long crossing, to be built alongside the two current spans of the Bay Bridge. In April, the Maryland Transportation Authority (MDTA) announced it had received federal approval to use this route for a potential new, wider bridge that would be likely to eventually replace its older siblings, addressing the notorious summer bottlenecks for decades to come. And on June 10, at a press conference held near the bridge’s eastbound ramp, Maryland Governor Larry Hogan announced that he would commit $28 million in bridge toll revenue to fund the second phase of an environmental impact study on the idea.
Read the court decisionRead the full story...Reprinted courtesy of
Ethan McLeod, Bloomberg
Traub Lieberman Chair Emeritus Awarded the 2022 Vince Donohue Award by the International Association of Claim Professionals
August 07, 2022 —
Richard K. Traub - Traub LiebermanTraub Lieberman is pleased to announce that firm Chair Emeritus Richard Traub has been awarded the 2022 Vince Donohue Award by the International Association of Claim Professionals (IACP).
The IACP provides a forum for senior Claim leaders from across the globe to build relationships with their peers, enhance their knowledge of strategic claim issues and trends, freely exchange views and ideas in order to improve the development, leadership and professionalism of its members and foster goodwill and better business among insurance organizations worldwide. Attorneys at Traub Lieberman have been longstanding members and Diamond Sponsors of the IACP.
Read the court decisionRead the full story...Reprinted courtesy of
Richard K. Traub, Traub LiebermanMr. Traub may be contacted at
rtraub@tlsslaw.com
Sales of Existing U.S. Homes Decrease on Fewer Investors
September 24, 2014 —
Jeanna Smialek – BloombergPurchases of previously owned U.S. homes unexpectedly declined in August for the first time in five months as investors retreated from the market.
Existing home sales dropped 1.8 percent to a 5.05 million annual pace, from a revised 5.14 million pace in July, the National Association of Realtors reported today in Washington. The median forecast of 72 economists in a Bloomberg survey called for 5.2 million. The share of properties sold to investors was the lowest in almost five years.
As wage gains are slow to materialize and credit conditions remain tight, it has been difficult for first-time homebuyers to enter the housing market to make up the decrease in investor activity. Employment growth and easier lending rules could help would-be buyers to feel more secure in taking the plunge into homeownership.
Read the court decisionRead the full story...Reprinted courtesy of
Jeanna Smialek, BloombergMs. Smialek may be contacted at
jsmialek1@bloomberg.net
Client Alert: Naming of Known and Unknown Defendants in Initial Complaints: A Cautionary Tale
September 24, 2014 —
R. Bryan Martin & Whitney L. Stefko – Haight Brown & Bonesteel LLPOn September 12, 2014, the Ninth Circuit Court of Appeals, in Butler v. National Community Renaissance of California, upheld a district court's dismissal of certain defendants named in amended complaints, affirming the necessity of naming those known and unknown defendants in Plaintiff's original complaint.
In April 2009, Plaintiff Zina Butler filed an action in federal district court, naming a single defendant, National Community Renaissance Corporation ("National"), for an alleged warrantless search of Plaintiff's apartment on April 18, 2007. The single page complaint asserted that the apartment manager provided a Section 8 investigator, a City employee and Sherriff deputies keys to Plaintiff's apartment and conducted a search in violation of her Fourth Amendment rights. Shortly after, Plaintiff filed a first amended complaint, with the only change being the addition of defendant, the Housing Authority of the County of Los Angeles ("HACoLA") in the caption. In May 2009, the court (on its own accord) dismissed the first amended complaint with leave to amend as "it [was] unclear whom Plaintiff intend[ed] to sue."
In June 2009, Plaintiff filed a second amended complaint, identifying National and HACoLA in the caption as defendants, but separately identifying several other individuals and entities allegedly involved in the incident occurring in April of 2007 in the complaint's statement of facts. The Court, once again, dismissed the second amended complaint with leave to amend for the same reasons it dismissed Plaintiff's first amended complaint.
Reprinted courtesy of
R. Bryan Martin, Haight Brown & Bonesteel LLP and
Whitney L. Stefco, Haight Brown & Bonesteel LLP
Mr. Martin may be contacted at bmartin@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
99-Year-Old Transmission Tower Seen as Possible Cause of Devastating Calif. Wildfire
December 11, 2018 —
Contra Costa Times - Engineering News-RecordDec. 08 --PULGA -- With winds gusting around 50 mph in the morning hours of Nov. 8 , portions of a PG&E steel lattice transmission tower -- exposed to the elements high on a ridgetop and originally built when Woodrow Wilson was president -- failed.
As high-voltage lines got loose and whipped around, striking the metal tower, molten aluminum and metal sprayed across tinder dry vegetation, igniting the brush. Arriving firefighters could only watch as the blaze underneath the power lines quickly spread to wild timber and brush.
Read the court decisionRead the full story...Reprinted courtesy of
Engineering News-RecordENR may be contacted at
ENR.com@bnpmedia.com