Mitsubishi Estate to Rebuild Apartments After Defects Found
March 19, 2014 —
Kathleen Chu and Takahiko Hyuga – BloombergMitsubishi Estate Co. (8802), Japan’s biggest developer by market value, will rebuild a Tokyo residential complex where it stopped selling apartments that went for as much as 350 million yen ($3.4 million) after finding defects.
The reconstruction will take about three to four years to complete, and builder Kajima Corp. will be in charge of the project and cover the cost, said Masayuki Watanabe, a spokesman at Tokyo-based Mitsubishi Estate. The building was constructed by Kajima along with Kandenko (1942) Co., according to the developer.
Mitsubishi Estate stopped selling apartments in the building in central Tokyo’s upscale Aoyama neighborhood after finding it needed repairs, including to some of the pipes, the developer said in an e-mail on Feb. 3. Eighty-three out of 86 units were under contract and were expected to be handed over to the owners on March 20, the company said last month.
Ms. Chu may be contacted at kchu2@bloomberg.net; Mr. Hyuga may be contacted at thyuga@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Kathleen Chu and Takahiko Hyuga, Bloomberg
Final Furnishing Date is a Question of Fact
November 10, 2016 —
David Adelstein – Florida Construction Legal UpdatesConstruction liens need to be recorded within 90 days from the lienor’s final furnishing date on the project. This date is exclusive of punchlist or warranty work. The final furnishing date needs to be proven at trial to establish that the construction lien was timely recorded. If there is an evidentiary dispute as the final furnishing date (the contractor claims the date was “x” to establish the lien was timely and the owner claims the date was “y” to establish the lien was untimely), then the date is a question of fact to be determined by the jury.
For instance, in Best Drywall Services, Inc. v. Blasczyk, 2016 WL 6246701 (Fla. 2d DCA 2016), a contractor and owner entered into an oral agreement for a residential renovation project. The contractor recorded a construction lien after its final two invoices went unpaid. During trial, the contractor offered conflicting evidence as to when its final furnishing date on the project was. Numerous dates were offered in the record including dates that were more than 90 days prior to the date the contractor recorded its lien, meaning the lien was arguably untimely. As a result, the trial judge entered a directed verdict in favor of the owner and against the contractor on the contractor’s lien claim finding the lien was untimely recorded.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Katz, Barron, Squitero, Faust, Friedberg, English & Allen, P.A.Mr. Adelstein may be contacted at
dma@katzbarron.com
Real Estate & Construction News Roundup (08/15/23) – Manufacturing Soars with CHIPS Act, New Threats to U.S. Infrastructure and AI Innovation for One Company
September 25, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogIn our latest roundup, wildfires wreak havoc in Maui, JLL unveils an AI specifically for commercial real estate, the lasting effects of the CHIPS ACT, and more!
- So far, 11,000 JLL employees have used the company’s new proprietary large language model that has generative AI capabilities specifically for the commercial real estate industry. (Lindsey Wilkinson, Construction Dive)
- Since the enactment of the CHIPS Act, manufacturing activity has boomed with a nearly 80% increase from June 2022. (Sebastian Obando and Julia Himmel, Construction Dive)
- Construction-tech-focused investors among others have poured $35 million into an Israeli startup that develops leakage detection technology using artificial intelligence to prevent water damage. (Sharon Wrobel, Times of Israel)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Used French Fry Oil Fuels London Offices as Buildings Go Green
December 10, 2015 —
Siobhan Wagner – BloombergPricewaterhouseCoopers LLP’s office above Charing Cross railway station in London is cooled, heated and fueled by an unlikely source: used cooking oil.
The system, which helped the property become the greenest building in the U.K. capital, uses oil refined less than two miles away at London Bridge. It also helps prevent an invisible problem: “fatbergs” formed when oils dumped in drains and pipes congeal with baby wipes and diapers and block the city’s sewers.
“We’re using London’s waste to fuel a London office building,” said Jon Barnes, head of building at PwC. The system contributed toward a one-third reduction in electricity costs after a two-year refurbishment of the One Embankment Place office building that finished last year.
Read the court decisionRead the full story...Reprinted courtesy of
Siobhan Wagner, Bloomberg
I-35W Bridge Collapse may be Due to “Inadequate Load Capacity”
January 22, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Crookston Times reports that the I-35W Bridge collapse that occurred five years ago in Minneapolis, Minnesota, killing 13 people and injuring another 145, may have been caused by “inadequate load capacity.” The National Transportation Safety Board (NTSB) report stated that it is “a simple design flaw in metal plates that help connect one steel beam to another.” Due to the findings, “the NTSB set new safety recommendations for bridge design plans, bridge inspection and training of bridge inspectors.”
Read the court decisionRead the full story...Reprinted courtesy of
A Reminder to Get Your Contractor’s License in Virginia
April 25, 2023 —
Christopher G. Hill - Construction Law MusingsHow are ducks and contractors alike? A question I get often, particularly from construction contractors outside of Virginia is whether they need to get a Virginia contractor’s license. The answer is almost invariably “yes.” The next question is why? The answer is almost always “Because state law says so.” With some minor exceptions for material suppliers and the like, Virginia law requires that all of those that perform construction for others carry the proper license and specialization for the work performed. There is no exception for the proverbial “paper contractor” that takes money from an owner and subcontracts all of the actual physical work. It does not matter if you use a different term for what you do for the owner. If it walks like a duck and quacks like a duck. . .its a duck. If you take money to perform construction, you’re a contractor.
Some of the consequences of contracting without a license (aside from possible criminal charges) include among other things, the inability to perfect a mechanic’s lien under Va. Code 43-3(D) and, with minor exceptions, the ability to enforce a contract (meaning it really hurts your ability to get paid).
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
What If Your CCP 998 Offer is Silent on Costs?
March 18, 2019 —
Tony Carucci - Snell & Wilmer Real Estate Litigation BlogIn California, the “prevailing party” in litigation is generally entitled to recover its costs as a matter of law. See Cal. Code Civ. Proc. § 1032. But under California Code of Civil Procedure section 998, a party may make a so-called “offer to compromise,” which can reverse the parties’ entitlement to costs after the date of the offer, depending on the outcome of the litigation. Cal. Code Civ. Proc. § 998. The potential payoff of a 998 offer is that “If an offer made by a defendant is not accepted and the plaintiff fails to obtain a more favorable judgment or award, the plaintiff shall not recover his or her postoffer costs and shall pay the defendant’s costs from the time of the offer.” Cal. Code Civ. Proc. § 998(c)(1) (emphasis added).
But how do you determine whether a plaintiff obtained a more favorable judgment when the 998 offer is silent with respect to whether it includes costs?
In Martinez v. Eatlite One, Inc. (2018) 27 Cal.App.5th 1181, 1182–83, the defendant made a 998 offer of $12,001 that was silent regarding the treatment of attorneys’ fees and costs. Plaintiff did not respond to the offer, and the jury ultimately awarded plaintiff damages of $11,490. Id. In resolving the parties’ competing memoranda of costs and plaintiff’s motion for attorneys’ fees, the trial court awarded plaintiff her costs and attorneys’ fees. Id. at 1182. The trial court reasoned that plaintiff had obtained a more favorable judgment than the 998 offer because she was entitled to pre-offer costs and attorneys’ fees under the statute, which meant plaintiff’s ultimate recovery exceeded the 998 offer when added to the judgment. Id. at 1183. In other words, the court added plaintiff’s pre-offer costs and attorneys’ fees to the $11,490 verdict for the purposes of determining whether the “judgment” was greater than the 998 offer of $12,001. Id.
Read the court decisionRead the full story...Reprinted courtesy of
Tony Carucci, Snell & WilmerMr. Carucci may be contacted at
acarucci@swlaw.com
General Contractor Gets Fired [Upon] for Subcontractor’s Failure to Hire Apprentices
September 23, 2024 —
Garret Murai - California Construction Law BlogAs most public works contractors know, Labor Code section 1777.5 requires the hiring of apprentices on public works projects and, under Labor Code section 1777.7, violations are subject to civil penalties of up $100/day and up to $300/day days for repeated violations within a three-year period.
In
Lusardi Construction Co. v. Dept. of Industrial Relations, 102 Cal.App.5th (2024), a prime contractor learned the hard way that not only could it be penalized for its failure to hire apprentices but that it could also be liable for its subcontractor’s failure to hire apprentices. Forewarned is to be forearmed.
The Lusardi Construction Case
In 2014, general contractor Lusardi Construction Company hired subcontractor Pro Works Contracting to perform iron reinforcing work on a public works project owned by the San Marcos Unified School District.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com