New Executive Order: Revitalizing Our Nation’s Commitment to Environmental Justice for All
May 08, 2023 —
Anthony B. Cavender - Gravel2GavelThe White House has released the text of the President’s new Executive Order strengthening the Federal Government’s commitment to taking new actions to enhance and promote environmental justice. The Order was published in the Federal Register on April 26, 2023 at 88 FR 25251. President Clinton’s pioneering 1994 Executive Order remains effective, but the Federal Government must, as part of a whole-of-government approach to environmental justice, “build upon and strengthen its commitment to deliver environmental justice to all communities across America.”
Unlike that Order, this Order defines “environmental justice.” For purposes of this new Order, “environmental justice” takes into account all adverse human health and environmental effects and hazards, including those related to climate change, the cumulative impacts of environmental and other burdens, and the legacy of racism or other structural or systematic barriers, and ensures equitable access to a healthy, sustainable and resilient environment in which to live, play, work, learn, worship and engage in cultural and subsistence practices.
“Federal activity” is now broadly defined as “any agency rulemaking, guidance, policy, program, practice or action that affects or has the potential to affect human health and the environment, including any agency action related to climate change.” This Order references the seven previous Executive Orders devoted to climate change, clean energy and the Inflation Reduction Act.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
AI in Construction: What Does It Mean for Our Contractors?
December 17, 2024 —
Patrick Scarpati - Construction ExecutiveArtificial intelligence is revolutionizing the construction industry by enhancing efficiency, safety and decision-making throughout the project lifecycle. AI in construction involves the application of advanced technologies like machine learning, computer vision and data analytics to various construction processes. Through AI, machines can learn and imitate human cognitive functions.
The possibilities may sound endless, but as an industry traditionally looking from the outside in at technology, we must first step back to educate ourselves on the basics. This paper is meant to function as a starting point in your journey to understand AI and its potential impact on the construction industry. By reading through definitions, construction use cases and considerations, the reader should walk away with a base level of knowledge to ensure they can actively participate in future conversations on AI in construction.
Reprinted courtesy of
Patrick Scarpati, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Developer Pre-Conditions in CC&Rs Limiting Ability of HOA to Make Construction Defect Claims, Found Unenforceable
August 16, 2021 —
Garret Murai - California Construction Law BlogThe Davis-Stirling Common Interest Development Act (Civ. Code §4000, et seq.), also known simply as “Davis-Stirling,” is a statute that applies to condominium, cooperative and planned unit development communities in California. The statute, which governs the formation and management of homeowners associations or HOAs, also governs lawsuits filed by HOAs for construction defects.
In the next case,
Smart Corners Owner Association v. CJUF Smart Corner LLC, Case No. D076775 (May 20, 2021), the 4th District Court of Appeal addressed the pre-litigation voting requirements of Davis-Stirling and the impact of recent amendments to the Act.
The Smart Corners Case
In 2004, CJUF Smart Corner LLC contracted with Hensel Phelps Construction Company for the construction of the Smart Corner condominium project, a 19-story mixed-use development with 301 residential units and common areas, in San Diego, California. As part of the development an HOA was formed, the Smart Corner Owner Association.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Stay-At-Home Orders and Work Restrictions with 50 State Matrix
April 27, 2020 —
Smith CurrieAs each day of the coronavirus pandemic passes, more and more states, cities and counties across the country are implementing stay-at-home (or shelter-in-place) orders and restrictions on individuals and businesses. These restrictions are impacting numerous persons and businesses, including those working in the construction industry. Smith Currie is keeping abreast of these restrictions and has developed the matrix below identifying statewide and local restrictions in place. This matrix is by no means complete, and we will continue updating it as we become aware of additional orders. In the write ups included with the PDF below, you will find links to the applicable orders with more detailed information. Consult legal counsel for advice on the impact of a particular restriction or restrictions to your business.
Read the court decisionRead the full story...Reprinted courtesy of
Smith CurrieThe firm Smith Currie may be contacted at
info@smithcurrie.com
Accounting for Payments on Projects Became Even More Crucial This Year
September 21, 2020 —
Christopher G. Hill - Construction Law MusingsI discussed
several of the statutory changes affecting the construction industry here at Construction Law Musings in the run-up to July 1, 2020. One of those changes, an amendment to
Virginia Code Section 43-13, may add another arrow to the collection quiver of subcontractors and suppliers. As part of the previously-linked rundown, I highlighted one of the big additions in 2020, namely the amendment making those pesky clauses that let those up the payment chain from you hold money on “this or any other project” void as against public policy.
The other big addition to 43-13 is the change that adds a possible civil cause of action for downstream and unpaid subcontractors and suppliers in the event that funds paid to a general contractor or subcontractor are not first used to pay their downstream contractors and suppliers. Prior to July 1, 2020, this statute provided criminal penalties for such behavior but did not contain the possibility of a civil penalty. The operative language for the change is as follows:
The use by any such contractor or subcontractor or any officer, director, or employee of such contractor or subcontractor of any moneys paid under the contract before paying all amounts due or to become due for labor performed or material furnished for such building or structure for any other purpose than paying such amounts due on the project shall be prima facie evidence of intent to defraud. Any breach or violation of this section may give rise to a civil cause of action for a party in contract with the general contractor or subcontractor, as appropriate; however, this right does not affect a contractor’s or subcontractor’s right to withhold payment for failure to properly perform labor or furnish materials on the project.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Prevailing HOAs Not Entitled to Attorneys’ Fees in Enforcement Actions Brought Under Davis-Stirling
August 30, 2017 —
Lawrence S. Zucker II & Michael C. Parme – Haight Brown & Bonesteel LLPIn Retzloff v. Moulton Parkway Residents’ Ass’n, (2017) Cal. App. LEXIS 727, the Fourth District Court of Appeal considered the novel question of whether attorneys’ fees can be included as part of the cost award to a ‘prevailing association’ under Cal. Civ. Code §5235(c).
Plaintiffs were former board members of Moulton Parkway Residents’ Association, No. One (“the Association”) who sued the Association for alleged violations of the Davis-Stirling Common Interest Development Act (Civ. Code §4000 et. seq.) which regulates the governance of common interest developments such as condominium communities and homeowners associations. Plaintiffs’ suit alleged that the Association regularly conducted business outside of scheduled board meetings and failed to make certain records available for inspection.
Reprinted courtesy of
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP and
Michael C. Parme, Haight Brown & Bonesteel LLP
Mr. Zucker may be contacted at lzucker@hbblaw.com
Mr. Parme may be contacted at mparme@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Can I Record a Lis Pendens in Arizona if the Lawsuit is filed Another Jurisdiction?
September 26, 2022 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogRecent research I did on a case led me to the conclusion that Arizona law recognizes foreign litigation (i.e., a lawsuit filed outside of Arizona) as a justification for the recording of a lis pendens against real property located within Arizona. See
TWE Retirement Fund Trust v. Ream, 198 Ariz. 268 (Ct. App. 2000). Apparently, there’s some debate about whether foreign litigation can support a local lis pendens. See
Boca Petroco, Inc. v. Petroleum Realty II, 285 Ga. 487 (Ga. 2009). As noted in the TWE case, Arizona’s lis pendens statute
(A.R.S. 12-1191) does not discriminate between local or foreign “actions.” As such, if litigation is pending anywhere that affects Arizona real property, a lis pendens can (and probably should) be filed.
Reprinted courtesy of
Ben Reeves, Snell & Wilmer
Mr. Reeves may be contacted at breeves@swlaw.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of