Drug Company Provides Cure for Development Woes
November 18, 2011 —
CDJ STAFFVertex Pharmaceuticals is poised to become the holder of Boston’s biggest commercial lease, paying $72.5 million for 1.1 million square feet on Boston’s waterfront. Vertex’s new buildings are still under construction, but the plans have spurred other development in the Fan Pier area, according to the New York Times. The Times quotes Mary A. Burke, a senior economist at the Federal Reserve Bank of Boston that the Vertex project gives “a big push” to the “momentum for economic growth.”
The Fallon Company is building Vertex’s new laboratory and office space. They are separately planning to build a high-rise with 150 luxury condominium units. According to Joseph Fallon, the chief executive and president of the Fallon Company, there is already a waiting list of 50 buyers for the condominiums.
Across the street from the Vertex site, a group including Morgan Stanley and Boston Global Investors is planning a 23-block mixed use project that would include 1.2 million square feet of retail space. Additionally, the New England Development and the Hanover Group is building a 356-unit apartment building at the adjacent Pier 4.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
High-Rise Condominium Construction Design Defects, A Maryland Construction Lawyer’s Perspective
July 15, 2015 —
Nicholas D. Cowie – Maryland Condo Construction Defect Law BlogThe increased migration from suburbs to metropolitan areas has accompanied an increase in high-rise construction, including the development of high-rise condominium buildings. The resulting metamorphosis of urban skylines, such as seen from Maryland’s Baltimore harbor, has also brought with it many complex construction law and construction litigation issues. Our law firm’s Maryland condominium construction law practice is increasingly called upon to resolve disputes involving high-rise condominium construction design defects between condominium associations, developers, contractors, builders, and design professionals arising out of the construction of high-rise buildings.
A condominium building is typically considered to be a high-rise when it is approximately seven or more stories above grade according to the National Fire Protection Association Life Safety Code, which defines a high-rise as being 75 feet (23 meters) measured from the lowest level accessible to fire department vehicles up to the floor level of the highest occupiable story. High-rise buildings may be residential (e.g., condominiums or multifamily apartment buildings), commercial (e.g., commercial office or retail space), or mixed-use structures. A mixed-use high-rise development might contain retail space, office space, a parking garage, apartments, and condominiums, each owned or maintained by separate entities and each sharing common expenses for the building.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas D. Cowie, Cowie & Mott, P.A.Mr. Cowie may be contacted at
ndc@cowiemott.com
How Does Weather Impact a Foundation?
December 27, 2021 —
Brent Pearson - Construction ExecutiveWhen it comes to commercial properties, it pays to be prepared. However, there are few things as unpredictable as the weather. With there being several weeks left in hurricane season, the weather can have quite an impact on the foundations of different properties. Whether it’s a new home or a century-old commercial property, preserving the integrity and safety of the structure is paramount. For those in construction looking to learn more about how the weather can sway a foundation, below are several examples along with tips on prevention.
Rain, Rain Go Away!
Hurricanes are known for bringing strong winds and plenty of rain. This can spell disaster for buildings with weak foundations. Torrential downpours can cause wet and weak soil. Too much rain—whether generated by hurricanes or frequent storms—can negatively impact the foundations of commercial properties and homes as well. It can also cause the soil to weaken, which can lead to a foundation sinking into the ground. For those that may have crawl spaces underneath their properties, heavy rains may cause water to seep under and into it. Water will sit in the crawl space, and it could take days or even weeks to dry out, causing moisture and possible mold damage.
Reprinted courtesy of
Brent Pearson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Top Talked-About Tech at the 2023 ABC Joint Tech Summit
May 15, 2023 —
Grace Arnold - Construction ExecutiveAt the
2023 ABC Joint Tech Summit in Tysons Corner, Virginia, on April 27, there was talk, of course, of various construction technologies, including AI, VR, autonomous vehicles, impairment detection, digital twins, blockchains and Spot the Robot Dog. All this different tech, however, was discussed for the same two reasons: safety and efficiency.
While some companies are just discovering the vast uses for and benefits of smart technology in construction, other companies are already well into adoption and implementation. Here is a breakdown of some of the contech showcased at the Joint Tech Summit, which was presented by four ABC chapters: Chesapeake Shores, Greater Baltimore, Metro Washington and Virginia.
AUTONOMOUS MACHINES
The talk of the Tech Summit was Spot the Robot Dog from
Boston Dynamics. Spot can walk, run, crawl, climb stairs and tortuous terrain, right itself from a fall, return to its charging port when its battery runs low and is compatible with a variety of add-ons, like 360 cameras. Spot is controlled via tablet and can be programmed to run on its own, allowing for increased worker and jobsite safety and productivity.
Reprinted courtesy of
Grace Arnold, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Harmon Tower Demolition on Hold Due to Insurer
November 27, 2013 —
CDJ STAFFPermission for CityCenter to demolish Harmon Tower over claims of dangerous construction defects have been withdrawn by the judge in the case after the building’s insurer said it needed more time to investigate. After they were granted permission to demolish the building on August 23, CityCenter filed a claim of total loss with their insurer FM Global on August 27.
Now FM Global is saying that they need to further inspect the building. Meanwhile, a demolition contractor has already gained approval to start removing the exterior glass. And things stand, it looks as if that won’t be happening on the planned date of December 2.
CityCenter contends that FM Global has already done their inspections, describing FM Global’s prior actions as “the most extensive investigation of anyone,” according to Mark Ferrario, an attorney for CityCenter.
Also, the initial plan to implode the building has been rejected. Should demolition proceed, the building will be dismantled floor by floor.
Read the court decisionRead the full story...Reprinted courtesy of
Federal Miller Act Payment Bond Claim: Who Gets Paid and Who Does Not? What Are the Deadlines?
September 16, 2019 —
William L. Porter - Porter Law GroupWhen working on federal public works construction projects there are no Stop Payment Notice or Mechanics Lien remedies available to protect subcontractors’ and suppliers’ right to payment. Instead, unpaid subcontractors and suppliers must resort to making a claim for payment under a federal law known as the AMiller Act@ (40 USCS 3131 et seq.). Many claimants however, do not realize that the right to make a Miller Act claim is not available to all subcontractors and suppliers. Before committing to performing work on a federal project it is important for subcontractors and suppliers to understand whether or not a Miller Act claim will be available. For those who have no Miller Act rights, careful consideration must be given to whether it is worth the risk to take on the project. For those who have valid Miller Act claim rights, important deadlines must be considered.
Who Gets Paid Under a Miller Act and Who Does Not
For federal projects in excess of $100,000, contractors who have a contract directly with the Federal Government must obtain Miller Act Payment Bond intended for the protection of Subcontractors, laborers and material suppliers to the project.
As a general rule, every subcontractor, laborer, or material supplier who deals directly with the prime contractor and is unpaid may bring a lawsuit for payment against the Miller Act Payment Bond. Further, every unpaid subcontractor, laborer, or material supplier who has a direct contractual relationship with a first-tier subcontractor may bring such an action. The deadlines for these claims are described below.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Quarter Four a Good One for Luxury Homebuilder
December 20, 2012 —
CDJ STAFFToll Brothers has announced that their fourth-quarter net income is $2.35 per share, which they attribute in part to an income tax benefit. Their revenue, at $632.8 million, easily exceeded analysts’ projections of $565.1 million. Additionally, their number of signed contracts jumped seventy percent while their cancellation rate dropped nearly half to 4.9 percent.
Read the court decisionRead the full story...Reprinted courtesy of
When Employer’s Liability Coverage May Be Limited in New York
June 28, 2021 —
Robert S. Nobel & Craig Rokuson - Traub LiebermanNew York recognizes that coverage under Workers’ Compensation (“WC”) and Employer’s Liability (“EL”) policies is generally unlimited. See Tully Const. Co. v. Illinois Nat. Ins. Co., 131 A.D.3d 598 (2d Dept. 2015); Oneida Ltd. v. Utica Mut. Ins. Co., 263 A.D.2d 825, 694 N.Y.S.2d 221 (3d Dept. 1999). However, there is case holding that EL coverage may be limited in certain instances, such as when the primary EL carrier is listed as scheduled underlying insurance on an excess policy.
In Liberty Mut. Ins. Co. v. Ins. Co. of State of Pennsylvania, 43 A.D.3d 666, 841 N.Y.S.2d 288 (1st Dept. 2007), an employee of General Industrial Service Corporation (“General”), a subcontractor on a construction project, sought to recover under New York’s Labor Law against the project’s owner and construction manager. Those defendants, in turn, brought a third-party action for indemnification against General. The employee’s personal injury claim was ultimately settled for $2.5 million. After the settlement, the excess insurer, Liberty, filed suit against the primary employer’s liability insurers, The Insurance Company of the State of Pennsylvania and American International Group of Companies (collectively, “AIG”), which had refused to participate in the defense or settlement of the underlying personal injury litigation. Although the issue of whether the plaintiff in the underling action had sustained a “grave injury” (necessary to support the common law indemnity claim against General and trigger coverage under the Employer’s Lability policy) had not yet been determined, the court held that “[i]n the event the existence of a grave injury is proven, AIG’s liability will be limited to $1 million.”
Reprinted courtesy of
Robert S. Nobel, Traub Lieberman and
Craig Rokuson, Traub Lieberman
Mr. Nobel may be contacted at rnobel@tlsslaw.com