Western Specialty Contractors Branches in San Francisco and Cleveland Take Home Top Industry Honors
January 03, 2022 —
Western Specialty Contractors(St. Louis, MO, Dec. 21, 2021) Western Specialty Contractors Branches in San Francisco, CA and Cleveland, OH are ending the year's fourth quarter on a high note, with each receiving a top industry award.
In October, Western's San Francisco Branch was named a 2021 International Concrete Repair Institute (ICRI) Project of the Year Award Finalist (Historic Category) for renovation and repurposing of the SMUD Museum of Science and Curiosity in Sacramento, CA. Western's Cleveland Branch was honored in December with the Institute of Real Estate Management (IREM) Northern Ohio Chapter's Industry Partner of the Year Award.
About Western Specialty Contractors
Family-owned and operated for more than 100 years, Western Specialty Contractors is the nation's largest specialty contractor in masonry and concrete restoration, waterproofing and specialty roofing. Western offers a nationwide network of expertise that building owners, engineers, architects, and property managers can count on to develop cost-effective, corrective measures that can add years of useful life to a variety of structures including industrial, commercial, healthcare, historic, educational and government buildings, parking structures, and sports stadiums. Western is headquartered in St. Louis, MO with 30 branch offices nationwide and employs more than 1,200 salaried and hourly professionals who offer the best, time-tested techniques and innovative technology. For more information about Western Specialty Contractors, visit www.westernspecialtycontractors.com.
Read the court decisionRead the full story...Reprinted courtesy of
Submitting Claims on Government Projects Can Be Tricky
March 19, 2015 —
Craig Martin – Construction Contractor AdvisorThe Federal Circuit Court of Appeals opinion in K-Con Building Systems, Inc. v. United States illustrates the difficulties a contractor may face when pursuing a claim before a Contracting Officer. After nearly 10 years of litigation, the court found that the contractor’s claim to the Contracting Officer did not contain enough detail to allow the claim to proceed. That’s a lot of time and resources wasted on a claim that was dead from the start.
K-Con was awarded a $582,000 job to design and build a Coast Guard support building in Michigan. K-Con was unable to complete the project by the finish date and the Coast Guard assessed liquidated damages of $109,554. K-Con contested the assessment of liquidated damages by submitting a one paragraph letter asserting that it was not the sole cause of the alleged delays; that the government was at fault for the delay; and the liquidated damages were an impermissible penalty. The Contracting Officer ultimately denied K-Con’s claim and K-Con appealed to the Court of Claims.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Policyholders' Coverage Checklist in Times of Coronavirus
March 16, 2020 —
Richard W. Brown & Andres Avila - Saxe Doernberger & Vita, P.C.Every state but West Virginia have reported hundreds of Coronavirus (COVID-19) cases in the U.S. More than half are in California, Washington, New York, and Massachusetts. The unprecedented social and economic impact of the Coronavirus makes it necessary for policyholders to keep open all lines of communications with their insurance brokers, insurance carriers, financial advisors, safety & compliance experts, and insurance coverage counsel even if it is not certain whether they will need to file insurance claims.
As always, the specific terms of the insurance policies and the way losses are documented and presented to insurance carriers will be pivotal in securing coverage for Coronavirus-related exposures, such as jobsite closures, stop-work orders, remote work mandated measures, business interruption, event cancelation, employees’ claims, among others.
Policyholders should consider the following checklist of key insurance coverage tasks to be better positioned to face the risks posed by the Coronavirus:
- Pre-Loss Risk Management: A careful review of the policyholder’s insurance program may show coverage for the Coronavirus outbreak. Now is the time to assess, with the guidance of your brokers and insurance coverage counsel, the specific coverages in place. Policyholders may want to particularly review the terms and conditions of their Property, General Liability, Pollution, Directors & Officers, Professional Liability, Fiduciary Liability, as well as Event Cancelation Insurance coverages, among others depending on their specific business trade. For instance, Policyholders would want to assess, ahead of time, whether there are bacterial/virus/communicable diseases/pandemics exclusions in their policies. It is also relevant to review, with a keen eye, the insuring agreements and pose hypotheticals to stress test them and see how far coverage would go with respect to a Coronavirus exposure;
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. and
Andres Avila, Saxe Doernberger & Vita, P.C.
Mr. Brown may be contacted at rwb@sdvlaw.com
Mr. Avila may be contacted at ara@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
In UK, 16th Century Abbey Modernizes Heating System by Going Back to Roman Times
March 18, 2019 —
Peter Reina - Engineering News-RecordAncient Romans in western England bathed in naturally warm spring water of the spa town of Aquae Sulis, now named Bath. Nearly 2,000 years later, the city’s 16th century abbey is now preparing to draw warmth from the still functioning Great Roman Drain to replace the former monastery’s dilapidated Victorian-era heating system.
Read the court decisionRead the full story...Reprinted courtesy of
Peter Reina, ENRMr. Reina may be contacted at
reina@btinternet.com
With VA Mechanic’s Liens Sometimes “Substantial Compliance” is Enough (but don’t count on it)
August 10, 2017 —
Christopher G. Hill - Construction Law MusingsVirginia mechanic’s liens are a powerful and tricky beast that in most cases require absolute precision in their preparation. However, an interesting opinion recently came out of the Virginia Supreme Court that may provide a bit of a “safe harbor” from the total form over function nature of a mechanic’s lien.
In Desai, Executrix v. A.R. Design Group Inc., the Court considered a lien memorandum that had what could be described as technical flaws in the preparation of the mechanic’s lien by A. R. Design Group. The basic facts are that A. R. Design Group used the form of lien found in Va. Code Sec. 43-5 (also found as Form CC-1512 at the Virginia Judiciary website) when it recorded two lien memoranda for two pieces of property owned by a trust. Relating to one of the two properties, the memorandum failed to identify the “Owner” as the trustee of the trust. On the memoranda relating to both properties the affidavit verifying the amounts claimed did not identify the signatory as agent for A. R. Design Group, instead listing the agent as the claimant and further failed to state a date from which interest is claimed or a date on which the debt was due.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Insurers Must Defend Allegations of Faulty Workmanship
June 20, 2022 —
Tred R. Eyerly - Insurance Law HawaiiGranting the insured's motion for partial judgment on the pleadings, the court determined the insurers had a duty to defend. Suez Treatment Solutions, Inc. v. Ace Am. Ins. Co. & Liberty Mut. Fire Ins. Co., 2022 U.S. Dist. LEXIS 59044 (S. D. N. Y. March 30, 2022).
Suez Treatment Solutions, Inc. held policies from Chubb and Liberty Mutual Fire Insurance Company to cover its operations in connection with the development of a pollution treatment system in North Carolina. When the project ultimately failed, an underlying action sought damages from Suez, alleging breach of contract, negligence, and fraud. Suez filed this case seeking a declaratory judgment that Chubb and Liberty were each obligated to defend and indemnify Suez in the underlying case.
The City of High Point hired Suez to upgrade the facilities at its wastewater treatment plant staring in 2021. Because mercury levels were too high in emissions from sewage-sludge incinerators, Suez began working on the installation of a Mercury Removal System. After installation, a leak occurred in a component known as the heat exchanger. The leak caused the system to shut down and weeks-long repairs began.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Specification Challenge; Excusable Delay; Type I Differing Site Condition; Superior Knowledge
January 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesAn Armed Services Board of Contract Appeals dispute, Appeal of L.S. Black-Loeffel Civil Constructors JV, ASBCA No. 62402, 2023 WL 5827241 (ASBCA 2023), involved which party bore liability for delay—the federal government or the prime contractor–based on various legal theories. Without detailing the factual details, a number of interesting legal issues were raised in this dispute including (1) a defective specification challenge, (2) excusable delay, (3) Type I differing site condition, and (4) superior knowledge. These legal issues are discussed below.
1. Specification Challenge (Defective Specifications)
The contractor claimed that the government’s specifications were defective in regard to a thermal control plan. The government countered that the specifications were not design specifications but performance specifications. The specifications were performance based because they did not tell the contractor how to achieve the performance-based criteria.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Alaska Supreme Court Dismisses Claims of Uncooperative Pro Se Litigant in Defect Case
August 11, 2011 —
CDJ STAFFThe Alaska Supreme Court found that in the case of Khalsa v. Chose, Ms. Khalsa? failure to cooperate with the courts has obligated them to dismiss her claims against Mr. Chose. Ms. Khalsa bought a home kit from Mandala Custom Homes of Nelson, British Columbia, Canada. Mr. Chose, one of the owners of Mandala was paid by Ms. Khalsa to supervise assembly in Fairbanks. After construction, the roof developed leaks. Ms. Khalsa stated that when climbing a ladder to inspect a skylight leak, she fell and injured herself.
During the subsequent suit, Khalsa proved uncooperative. She skipped a pretrial conference. She attended a hearing that set discovery deadlines but then did not comply with discovery, including her failure to provide medical records documenting her injuries. She eventually said that she would only be able to travel from Arizona to Alaska if the defendants paid for her and her caretaker?s expenses.
When finally deposed, Khalsa terminated the deposition after five minutes, alleging the deposition was “intentionally designed to cause [her] to endure further emotional distress, due to the psychological trauma . . . that was caused or contributed to by the defendants.”
Eventually, the lower court sanctioned her twice. In July, 2008, the court concluded that her failure to provide medical records required dismissal of her injury lawsuit. In October of that year, the court dismissed all remaining claims due to her “pattern of excuses and long delays in providing information for discovery culminating in her refusal to participate in her deposition by the defendants.” Further, Khalsa has argued that the trial court displayed “prejudice and bias toward the pro se plaintiff.”
The Alaska Supreme Court rejected all of Ms. Khalsa?s claims, dismissing her case. They did, however, note that she has thirty days to file an appeal.
Read the court’s decision…