Sometimes a Reminder is in Order. . .
February 18, 2020 —
Christopher G. Hill - Construction Law MusingsRecently, I was talking with my friend Matt Hundley about a recent case he had in the Charlottesville, VA Circuit Court. It was a relatively straightforward (or so he and I would have thought) breach of contract matter involving a fixed price contract between his (and an associate of his Laura Hooe) client James River Stucco and the Montecello Overlook Owners’ Association. I believe that you will see the reason for the title of the post once you hear the facts and read the opinion.
In James River Stucco, Inc. v. Monticello Overlook Owners’ Ass’n, the Court considered Janes River Stucco’s Motion for Summary Judgment countering two arguments made by the Association. The first Association argument was that the word “employ” in the contract meant that James River Stucco was required to use its own forces (as opposed to subcontractors) to perform the work. The second argument was that James River overcharged for the work. This second argument was made without any allegation of fraud or that the work was not 100% performed.
Needless to say, the Court rejected both arguments. The Court rejected the first argument stating:
In its plain meaning, “employ” means to hire, use, utilize, or make arrangements for. A plain reading of the contractual provisions cited–“shall employ” and references to “employees”–and relied on by Defendant does not require that the persons performing the labor, arranged by Plaintiff, be actual employees of the company or on the company’s payroll. It did not matter how the plaintiff accomplished the work so long as it was done correctly. The purpose of those provisions was to allocate to Plaintiff responsibility for supplying a sufficient workforce to get the work done, not to impose HR duties or require the company to use only “in house” workers. So I find that use of contracted work does not constitute a breach of the contract or these contractual provisions.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
New WA Law Caps Retainage on Private Projects at 5%
May 29, 2023 —
Brett M. Hill & Ryanne S. Mathisen - Ahlers Cressman & Sleight PLLCThis month, Governor Jay Inslee signed into law a new statute that caps retainage on private construction projects to five percent (5%), provides a mechanism for subcontractors to get paid their retainage prior to project completion, and allows for contractors and subcontractors to post a retainage bond and get paid their retainage early. For those interested in reading the full text of this new law, the statute can be found
here.
The new statute goes into effect on July 23, 2023. Under the statute, when a contractor or subcontractor considers their work under a contract subject to retainage complete, they may notify the party they contracted to perform the work for. Within 15 days of receiving the notice of completion of work, the party receiving the notice must respond with either (1) notice of acceptance of work or (2) notice of uncompleted items to the contractor or subcontractor.
If the party receiving notice does not provide notice of uncompleted items within 15 days or fails to respond to the notice of completion entirely, the unpaid retainage will begin to accrue interest at a rate of one percent (1%) per month, 30 days after the initial 15-day period. However, this interest will not accrue against a contractor who has not been paid the retainage by an upper-tier contractor or owner until payment has been received, so long as that contractor has submitted its subcontractor’s notice of completion to the upper-tier contractor or owner within 30 days of receipt.
Reprinted courtesy of
Brett M. Hill, Ahlers Cressman & Sleight PLLC and
Ryanne S. Mathisen, Ahlers Cressman & Sleight PLLC
Mr. Hill may be contacted at brett.hill@acslawyers.com
Ms. Mathisen may be contacted at ryanne.mathisen@acslawyers.com
Read the court decisionRead the full story...Reprinted courtesy of
Building Permits Up in USA Is a Good Sign
November 27, 2013 —
CDJ STAFFThe number of building permits for houses issued throughout the country hasn’t been higher since June 2008, a sign that the home building industry continues to recover, even in the face of higher interest rates. “These reports are unequivocally in line with our view that the housing recovery remains will on track, as the lack of supply will continue to support both construction activity and house prices,” according to Harm Bandholz, the chief U.S. economist for UniCredit Research.
Building permits were up 13.9% over last year and beat projections of 930,000 permits on an annual rate. The current annual rate for building permits is 1.03 million. Permits for multifamily homes were up 20.1% in September and 15.3% in October. Single-family homes were up 0.8% in October, but had fallen 1.9% the month before.
Read the court decisionRead the full story...Reprinted courtesy of
Washington School District Sues Construction Company Over Water Pipe Damage
August 27, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Yakima Herald reported that “[t]he Toppenish School District is suing a local construction company over a breach of contract that allegedly led to defective water pipes at one of its elementary schools, according to a complaint filed with the Yakima County Superior Court earlier this week.”
According to the complaint (as reported by the Yakima Herald), Toppenish officials alleged that the Huylar Construction Co. failed to install calcium silicate seals during the pipe installation. Furthermore, the complaint stated that last November, the school district discovered “’[e]xtensive corrosion and deterioration’ of the pipes.” Toppenish argued that failure to install the seals is a breach of contract.
Toppenish is suing for about $120,000. The Yakima Herald stated that a Huylar representative “could not be reached for comment.”
Read the court decisionRead the full story...Reprinted courtesy of
Alabama Court Determines No Coverage For Insured's Faulty Workmanship
June 28, 2013 —
Tred EyerlyThe Alabama Supreme Court found there was no coverage for the insured cabinet maker for claims arising from alleged faulty workmanship. Shane Traylor Cabinetmaker, L.L.C. v. Am. Resources Ins. Co., Inc., 2013 Ala. LEXIS 42 (May 3, 2013).
The insured was sued by a homeowner for property damage caused by faulty workmanship. The insurer refused to defend, contending there was no "occurrence." The trial court granted summary judgment to the insurer.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyTred Eyerly can be contacted at
te@hawaiilawyer.com
Courts Take Another Swipe at the Implied Warranty of the Plans and Specifications
December 15, 2016 —
John P. Ahlers – Ahlers & Cressman PLLCImplied warranties are warranties created by law, legislation, or courts. In the construction industry, one of the most prominent implied warranties is that owners who provide plans and specifications to their contractors impliedly warrant the adequacy of their plans and specifications.[i] That implied warranty had its beginning in the 1918 US Supreme Court decision of U.S. v. Spearin[ii] and is, therefore, popularly known as the Spearin Doctrine. Under the Spearin Doctrine, if the contractor completes the work in accordance with the owner’s plans and specifications, but there is a deficiency or failure, the owner, not the contractor, is responsible. When the owner breaches its implied warranty, in most instances, the contractor is entitled to additional compensation for extra work performed, delays experienced, and other additional expense or loss occasioned by the warranty breach. A recent case demonstrates that this implied warranty is not “immunity.” The contractor must still act reasonably and diligently, particularly when the contract provisions so require.
In the recent Fifth Circuit case of Dallas/Ft. Worth International Airport v. INet Airport Systems,[iii] the court, despite the implied warranty that existed, did not grant the contractor summary judgment on claims involving admitted plan deficiencies, since factual issues existed regarding the contractor’s cooperation and participation in the solution to the defects.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman, PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Risk-Shifting Tactics for Construction Contracts
February 24, 2020 —
Nate Budde - Construction ExecutiveAnyone who has worked in the construction industry is familiar with the financial risks involved. With thin margins, cash flow issues and the litany of potential claims and damages that can arise, contractors need to be able to manage that risk properly.
There is the right way of going about it, and there's a wrong way. Unfortunately, the wrong way (which involves using leverage and shifting risk to other parties) is the more prevalent approach. There are different contractual tactics employed by owners and general contractors alike to shift financial risk to other parties.
Why is construction so financially risky?
There are a few different reasons there is so much risk involved. First and foremost, the construction payment chain itself is inherently risky. Owners and lenders release project funds and trust that the money will reach everyone on the job. But that can’t happen unless each link in the payment chain passes payment to the next. That's a lot of trust for an industry that's not particularly known for it.
Another reason is how construction projects begin. Upfront payment is rare in this industry. This leads to floating the initial costs, extending credit and potentially borrowing money to do so. And those who typically bear this burden, lower-tier subs and suppliers, are the least equipped for that level of risk.
Reprinted courtesy of
Nate Budde, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Budde may be contacted at
nate@levelset.com
When “Substantially Similar” Means “Fundamentally Identical”: Delaware Court Enforces Related Claim Provision to Deny D&O Coverage for Securities Class Action
August 10, 2021 —
Geoffrey B. Fehling, Lawrence J. Bracken II & Lorelie S. Masters - Hunton Andrews KurthA company faces two class action lawsuits—filed by different plaintiffs, complaining of different allegedly wrongful conduct, asserting different causes of action subject to different burdens of proof, and seeking different relief based on different time periods for the alleged harm. Those facts suggest the suits are not “fundamentally identical,” but that is what a Delaware Superior Court recently concluded in barring coverage for a policyholder seeking to recover for a suit the court deemed “related” to an earlier lawsuit first made outside the policy’s coverage period. First Solar Inc. v. National Union Fire Ins. Co. of Pittsburgh, Pa., No. N20C-10-156 MMJ CCLD (Del. Super. Ct. June 23, 2021). The decision, which is not on all fours with some of the authority upon which it relies, underscores the inherent unpredictability of “related” claim disputes and need for careful analysis of the policy language against the factual and legal bases of the underlying claims.
Underlying Shareholder Class Actions and D&O Claims
Shareholders of solar panel manufacturer First Solar sued the company and its directors and officers in a class action lawsuit (the “Smilovits Action”) for the class period April 2008 to February 2012. The Smilovits Action asserted federal securities violations arising from First Solar’s alleged misrepresentations about the company’s business strategies, product design, financial strength, and ability to offer solar electricity at comparable rates to conventional energy producers (i.e., achieving “grid parity”), artificially inflated stock price, insider trading, manipulation of solar power metrics, and violations of GAAP accounting standards. First Solar submitted a claim to its D&O insurer, National Union, which provided coverage for the Smilovits Action and exhausted the policy.
Reprinted courtesy of
Geoffrey B. Fehling, Hunton Andrews Kurth,
Lawrence J. Bracken II, Hunton Andrews Kurth and
Lorelie S. Masters, Hunton Andrews Kurth
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Ms. Masters may be contacted at lmasters@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of