New York Court Rejects Owner’s Bid for Additional Insured Coverage
September 06, 2021 —
Eric D. Suben - Traub LiebermanTenders for additional insured coverage in construction accidents are frequently litigated in New York courts. Although the past few years have seen changes in the law regarding the causal nexus between the named insured’s work and coverage for the purported additional insured, courts often find there is at least a duty to defend the additional insured where there are allegations of the employer/subcontractor’s presence at the site.
An exception is the recent decision in Gemini Insurance Company v. Certain Underwriters at Lloyd’s, London, Index No. 652669/20 in the Supreme Court of the State of New York, County of New York (Lebovits, J.). In that case, Gemini insured the owner and general contractor of a construction project, and Lloyd’s insured the injured claimant’s employer under a policy endorsed to provide additional insured coverage to entities who “have agreed in writing in a contract or agreement” with the named insured that they must be “added as additional insured.” Although the court found that the contracts here satisfied this requirement for additional insured coverage, the court’s analysis did not end there.
Noting that even where such contract exists, the Lloyd’s policy would not provide additional insured coverage “in all circumstances” (emphasis in original), the court next considered whether the underlying injury was “caused in whole or in part by: 1. [The named insured’s] acts or omissions, or 2. The acts or omissions of those acting on [the named insured’s] behalf,” as required under the endorsement’s wording.
Read the court decisionRead the full story...Reprinted courtesy of
Eric D. Suben, Traub LiebermanMr. Suben may be contacted at
esuben@tlsslaw.com
Ninth Circuit Issues Pro-Contractor Licensing Ruling
July 18, 2018 —
Amy L. Pierce – Gravel2Gavel Construction & Real Estate Law BlogOn July 10, the U.S. Court of Appeals for the Ninth Circuit issued its much anticipated and a pro-contractor ruling in MP Nexlevel of California, Inc. v. CVIN LLC. The appeal arose from a dispute over the scope of a California specialty contractor’s license and, more particular, involved whether the subcontractor’s performance of certain work was outside the scope of its license constituting a breach of contract and resulting in the contractor not being entitled to payment for its work (Cal. Bus. & Prof. Code § 7031(a)). In an unpublished opinion, the Ninth Circuit reversed and remanded the matter, finding that “Nexlevel’s work here was ‘incidental and supplemental’ to the installation of these fiberoptic systems,” as contemplated by Cal. Code Regs. Tit. 16, § 831.
Read the court decisionRead the full story...Reprinted courtesy of
Amy L. Pierce, Pillsbury Winthrop Shaw Pittman LLPMs. Pierce may be contacted at
amy.pierce@pillsburylaw.com
California Supreme Court Finds that When it Comes to Intentional Interference Claims, Public Works Projects are Just Different, Special Even
November 21, 2017 —
Garret Murai - California Construction Law BlogOriginally published by CDJ on April 20, 2017
Earlier, we reported on a California Court of Appeals decision – Roy Allan Slurry Seal, Inc. v. American Asphalt South, Inc. – which held for the first time that a second-place bidder on a public works contract could sue a winning bidder who failed to pay its workers prevailing wages, under the business tort of intentional interference with prospective economic advantage.
Fast forward nearly two years, several amicus briefs, and “one doghouse”* later and the California Supreme Court has . . . reversed.
The Roy Allan Slurry Seal Case
To catch you up, or rather, refresh your recollection . . .
Between 2009 and 2012, American Asphalt South, Inc. was awarded 23 public works contracts totaling more than $14.6 million throughout Los Angeles, Orange, San Bernardino and San Diego counties. Two of the losing bidders on those projects – Roy Allan Slurry Seal, Inc. and Doug Martin Contracting, Inc. – sued American in each of these counties for intentional interference with prospective economic advantage as well as under the Unfair Practices Act (“UPA”) (Bus. & Prof. Code §§ 17000 et seq.) and the Unfair Competition Law (“UCL”) (Bus. & Prof. Code §17200).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
U.S. Building Permits Soared to Their Highest Level in Nearly Eight Years
June 17, 2015 —
Michelle Jamrisko – BloombergThrough all its ups and downs, the U.S. homebuilding industry is making slow progress.
While housing starts declined 11.1 percent in May to a 1.04 million annualized rate, it followed a revised 1.17 million pace the prior month to cap the best back-to-back readings since late 2007, Commerce Department data showed Tuesday in Washington. Permits for future projects climbed to the highest level in almost eight years.
The stop-and-go nature of the rebound, which has been exacerbated by the inclement weather that brought construction to a near standstill at the start of the year, masks a steady recovery in the industry at the center of the past recession. While residential real estate has yet to fulfill its typical role as a pillar of this economic expansion, gains in hiring and bigger paychecks are brightening Americans’ moods and could lift home purchases in the second half of 2015.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko, Bloomberg
Good and Bad News on Construction Employment
February 10, 2012 —
CDJ STAFFThe construction industry hit a two-year high in January, with 21,000 jobs added that month. The mild winter is assumed to have helped. According to the General Contractors of America, the construction industry currently employs about 5.57 million people. This is a 21 percent gain over January 2010. Ken Simonson, the chief economist of GCA, noted that “the unemployment rate in construction is still double that of the overall economy.” He said it was not currently clear if “the recent job growth reflects a sustained pickup or merely acceleration of homebuilding and highway projects that normally halt when the ground freezes in December and January.”
Stephen Sandherr, the chief executive officer of the GCA, said that the federal government had to make infrastructure funding a top priority. “Without adequate long-term funding for infrastructure, competitive tax rates and fewer costly regulatory hurdles, the construction industry may lose some of the jobs it gained in the last year.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
The Burden of Betterment
February 23, 2017 —
Ryan M. Charlson, Esq. - Florida Construction Law NewsThe concept of betterment has long been used by defendants in cases involving defective design or construction to limit the damages awarded to a plaintiff.[1] The theory behind betterment is that: “if in [the] course of making repairs [an] owner adopts a more expensive design, recovery should be limited to what would have been the reasonable cost of repair according to original design.”[2] Betterment is often raised as an affirmative defense, requiring a defendant to prove that the plaintiff has received a good or service that is superior to that for which the plaintiff originally contracted. A recent South Florida case seems, at first blush, to suggest the burden of establishing the value of betterments may fall to the plaintiff, although a closer reading indicates the decision is likely to have limited applicability.
In Magnum Construction Management Corp. v. The City of Miami Beach, the Third District Court of Appeal was asked to review the damages award to the City for construction defects associated with the redesign and improvement of a park.[3] The completed project contained landscaping deficiencies, along with other “minor defects” in the playground’s construction.[4] After a unilateral audit, and without providing the contractor its contractually required opportunity to cure the defects, the City “removed, redesigned, and replaced the playground in its entirety.”[5] It did so despite no recommendation by the City’s own expert to perform such work.[6] During the bench trial, the “only measure of damages provided by the City was the costs associated with the planning, permitting, and construction of a park that is fundamentally different from the one it contracted with [the contractor] to build.”[7]
Read the court decisionRead the full story...Reprinted courtesy of
Ryan M. Charlson, Cole, Scott & Kissane, P.A.Mr. Charlson may be contacted at
ryan.charlson@csklegal.com
2018 Spending Plan Boosts Funding for Affordable Housing
April 11, 2018 —
Emily Bias – Gravel2Gavel Construction & Real Estate Law BlogOn March 23, President Trump signed into law the Consolidated Appropriations Act, 2018, a $1.3 trillion spending package that includes a 12.5% increase in low-income housing tax credit allocations over the next four years, along with funding increases for several affordable housing programs. This is welcome news to affordable housing developers who have been facing funding gaps as a result of reductions in the corporate tax rate under the Tax Cuts and Jobs Act enacted in late 2017, which led to reduced pricing from equity investors.
Read the court decisionRead the full story...Reprinted courtesy of
Emily Bias, Pillsbury Winthrop Shaw Pittman LLPMs. Bias may be contacted at
emily.bias@pillsburylaw.com
Construction Defect Leads to Death of Worker
January 28, 2013 —
CDJ STAFFThe family of a Florida man has received $2.4 million in damages as a result of his death. Victor Lizarraga was killed when a steel column fell due to the anchor bolts being improperly secured. The general contractor on the project, R. L. Haines, told subcontractors that the epoxy had sufficient time to cure. An OSHA investigation determined that the epoxy was not used properly. Mr. Lizarraga worked for a subcontractor on the project.
Mr. Lizarraga and his coworkers were hired to erect steel columns. The epoxy failed, sending a 1,750-pound column down onto Mr. Lizarraga. According to the lawsuit, "due to the sudden and unexpected nature of this incident Mr. Lizarraga had no ability, opportunity or time to get out of the way of the falling column."
Other parties in the lawsuit settled with the family. R. L. Haines was the only defendant to go to a jury trial.
Read the court decisionRead the full story...Reprinted courtesy of