Washington Supreme Court Interprets Ensuing Loss Exception in All-Risk Property Insurance Policy
May 20, 2024 —
David G. Jordan & William E. Phillips IV - Saxe Doernberger & Vita, P.C.The "ensuing loss" clause is a provision that restores coverage for property insurance claims that are subject to certain policy exclusions, such as “faulty workmanship” and “faulty design.” It applies in cases where there is damage from a covered cause of loss that ensues, or results from, the excluded cause of loss. Courts across jurisdictions have grappled with interpreting the breadth of this clause, leading to varying conclusions regarding its scope and applicability. One of the primary challenges in interpreting “ensuing loss” lies in determining the ultimate cause of damage. Courts must ascertain whether the ensuing loss is sufficiently distinct from the excluded event to warrant coverage under the policy. This analysis often hinges on whether the cause of loss is thought to constitute a separate and independent occurrence or is merely a continuation or exacerbation of the excluded event.
Reprinted courtesy of
David G. Jordan, Saxe Doernberger & Vita, P.C. and
William E. Phillips IV, Saxe Doernberger & Vita, P.C.
Mr. Jordan may be contacted at DJordan@sdvlaw.com
Mr. Phillips may be contacted at WPhillips@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
LEED Certified Courthouse Square Negotiating With Insurers, Mulling Over Demolition
June 06, 2011 —
Douglas Reiser, Builders Council BlogApparently, Courthouse Square is still unresolved. The County hasnow hired an attorney to handle its insurance claim against Affiliated FM. Is there a lawsuit coming?
Right now, no lawsuit is expected. According to officials, the insurer has been acting in good faith. But, its been quite a while since Salem officials learned that the Courthouse Square building had significant concrete issues that would result in probable demolition of the LEED certified building.
If you have yet to hear about Courthouse Square, let me fill you in briefly. The Salem building was substantially completed in 2000 and LEED certified by the US Green Building Council in 2002. The project cost more than $30 Million to complete and the building was revered for its innovation as a crowning achievement for city leaders.
But, structural problems in the building’s core were discovered as early as 2002, writes Chris Cheatham of Green Building Law Update. Final tests earlier in the year, determined that the building had to be vacated. The building has been clear since July 2010.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
Brooklyn Atlantic Yards Yields Dueling Suits on Tower
September 03, 2014 —
Erik Larson – BloombergForest City Ratner Cos., the initial developer of Brooklyn’s $4.9 billion Atlantic Yards project surrounding Barclays Center arena, exchanged lawsuits with the Swedish construction firm Skanska AB (SKAB) over claims of design flaws and delays in building a stalled residential tower.
The lawsuits, filed today in Manhattan state court, focus on a contract for the 34-floor “modular” residential high-rise building under construction next to the arena for the National Basketball Association’s Brooklyn Nets that opened in 2012 as the centerpiece of the former rail yard and a symbol of the New York borough’s resurgence.
Skanska, a Stockholm-based firm that has grown to become New York’s second-largest building contractor, seeks at least $50 million in damages for changes to the building that were made without consultation, according to its complaint. Brooklyn-based Forest City Ratner blames Skanska for the project’s problems, citing “tens of millions of dollars” in cost overruns caused by a lack of skill and a failure to adhere to terms of the 2012 contract.
Read the court decisionRead the full story...Reprinted courtesy of
Erik Larson, BloombergMr. Larson may be contacted at
elarson4@bloomberg.net
ASCE's Architectural Engineering Institute Announces Winners of 2021 AEI Professional Project Award
April 19, 2021 —
American Society of Civil EngineersRESTON, Va. – The
American Society of Civil Engineers' (ASCE) Architectural Engineering Institute (AEI) is pleased to announce the 100 Mount Street project by Skidmore, Owings & Merrill and Billie Jean King Main Library, also by Skidmore, Owings & Merrill as Best Overall Projects winners for AEI's Professional Project Awards. The 100 Mount Street project won the award Best Overall Project Over $100 Million, while the Billie Jean King Main Library won the award for Best Overall Project Under $100 Million. Traditionally, AEI announces project winners during its in-person annual Awards Banquet; however, ASCE held the banquet virtually this year to follow CDC guidelines which suggest avoiding large gatherings.
The AEI Professional Project Award recognizes outstanding achievements in design and construction by honoring the art and science of an integrated approach to architectural engineering. The program focuses on high performance buildings including structural, mechanical, electrical and lighting systems as well as construction management and architectural engineering integration. Projects are evaluated on originality and innovative character, integration and collaboration, sustainability, energy efficiency and economics, effective use of technology and constructability and site logistics.
ABOUT THE AMERICAN SOCIETY OF CIVIL ENGINEERS
Founded in 1852, the American Society of Civil Engineers represents more than 150,000 civil engineers worldwide and is America's oldest national engineering society. ASCE works to raise awareness of the need to maintain and modernize the nation's infrastructure using sustainable and resilient practices, advocates for increasing and optimizing investment in infrastructure, and improve engineering knowledge and competency. For more information, visit www.asce.org and follow us on Twitter, @ASCETweets and @ASCEGovRel.
About ASCE's Architectural Engineering Institute
Established in 1998, AEI is the premier organization for architectural engineering, promoting an integrated, multi-disciplinary approach to planning, design, construction and operation of buildings, by encouraging innovation, collaboration and excellence in practice, education and research of architectural engineering. For more information, visit www.asce.org/aei.
Read the court decisionRead the full story...Reprinted courtesy of
American Society of Civil Engineers
Turkey Digs Out From a Catastrophe
April 18, 2023 —
Pam McFarland - Engineering News-RecordIn what’s left of Antakya, a once-thriving and cosmopolitan tourist destination in the southeastern edge of Turkey, the streets seem weirdly quiet. Buildings stand askew at odd angles or are completely toppled, and the rubble from the homes of people who lived inside of them is neatly collected into piles and mounds.
Reprinted courtesy of
Pam McFarland, Engineering News-Record
Ms. McFarland may be contacted at mcfarlandp@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
South Carolina Clarifies the Accrual Date for Its Statute of Repose
March 18, 2019 —
William L. Doerler - The Subrogation StrategistIn Lawrence v. General Panel Corp., 2019 S.C. LEXIS 1, No. 27856 (S.C. Jan. 1, 2019), the Supreme Court of South Carolina answered a certified question related to South Carolina’s statute of repose, S.C. Code § 15-3-640,[1] to wit, whether the date of “substantial completion of the improvement” is always measured from the date on which the certificate of occupancy is issued. The court held that a 2005 amendment to § 15-3-640 did not change South Carolina law with respect to the date of substantial completion. Thus, under the revised version of § 15-3-640, “the statute of repose begins to run at the latest on the date of the certificate of occupancy, even if there is ongoing work on any particular part of the project.” A brief review of prior case law may assist with understanding the court’s ruling in Lawrence.
In Ocean Winds Corp. of Johns Island v. Lane, 556 S.E.2d 377 (S.C. 2001), the Supreme Court of South Carolina addressed the question of whether § 15-3-640 ran from substantial completion of the installation of the windows at issue or on substantial completion of the building as a whole. Citing § 15-3-630(b),[2] the court found that the windows “were ‘a specified area or portion’ of the larger condominium project” and, upon their incorporation into the larger project they could be used for the purpose for which they were intended. Thus, the court held that “the statute of repose began running when installation of the windows was complete.”
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and WilliamsMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
Texas Supreme Court Authorizes Exception to the "Eight-Corners" Rule
February 28, 2022 —
Jared De Jong, Nathan A. Cazier & Scott S. Thomas - Payne & FearsFor decades, an insurer’s duty to defend under Texas law was determined exclusively by reviewing the insurance contract and the allegations of the complaint under the “eight-corners rule.” All of this changed last week when, in a long-awaited decision, the Texas Supreme Court ruled that courts may consider extrinsic evidence to determine the existence of coverage in certain limited situations. Monroe Guar. Ins. Co. v. BITCO Gen. Ins. Corp., No. 21-0232, 2022 WL 413940 (Tex. Feb. 11, 2022).
In Monroe, a drilling contractor was sued for damages arising out of the allegedly botched drilling of an irrigation well. The underlying lawsuit alleged that negligent drilling caused damage to surrounding farmland. However, the complaint did not allege when the damage occurred. The contractor’s insurers, BITCO General Insurance Corporation (“Bitco”) and Monroe Guarantee Insurance Company (“Monroe”) disputed whether Monroe owed a duty to defend. Although Bitco agreed to provide a defense, Monroe refused, arguing that the property damage happened before its policy period. Bitco sued Monroe for contribution. In the trial court, the insurers stipulated that a drill bit became stuck before Monroe’s policy incepted, a fact that would have supported Monroe’s “prior damage” defense. On summary judgment, though, the trial court ruled this stipulated fact could not be considered under Texas’ eight-corners rule. Monroe appealed, and the Fifth Circuit, which had previously endorsed an exception to the eight-corners rule under Northfield Insurance Co. v. Loving Home Care, Inc., 363 F.3d 523, 531 (5th Cir. 2004), certified the question to the Texas Supreme Court.
Reprinted courtesy of
Jared De Jong, Payne & Fears,
Nathan A. Cazier, Payne & Fears and
Scott S. Thomas, Payne & Fears
Mr. Jong may be contacted at jdj@paynefears.com
Mr. Cazier may be contacted at nac@paynefears.com
Mr. Thomas may be contacted at sst@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
Nationwide Immigrant Strike May Trigger Excusable Delay and Other Contract Provisions
February 23, 2017 —
Adam P. Handfinger & Meredith N. Reynolds – Peckar & Abramson, P.C.Yesterday, February 16, 2017, media outlets reported a nationwide strike by immigrants and
businesses referred to as “A Day Without Immigrants”. The protest, organized largely through
social media, was a response by some to the Trump Administration’s immigration and foreign
trade policies. Participating businesses shut down and immigrants refused to work or spend
money in an eff ort to demonstrate the role of foreign-born workers in the U.S. economy.
While the number of businesses and individuals that participated is not yet known, several
contractors reported labor shortages and construction project delays or temporary shut
downs as a result of the protest.
Reprinted courtesy of
Adam P. Handfinger, Peckar & Abramson, P.C. and
Meredith N. Reynolds, Peckar & Abramson, P.C.
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Ms. Reynolds may be contacted at mreynolds@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of