Less Than Perfectly Drafted Endorsement Bars Flood Coverage
January 21, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe court decided that the policy's flood exclusion, despite being poorly located within the policy, barred coverage for loss caused by flood. Great Lakes Int'l Trading Inc. v. Travelers Prop. Cas. Co., 2014 U.S. Dist. LEXIS 165378 (D. Conn. Nov. 26, 2014).
Hurricane Sandy caused flood waters from the Hackensack River in New Jersey to inundate a warehouse where the insured had imported food products stored for sale in the United States. High winds also sheared open parts of the warehouse's roof, allowing extensive rainwater to enter the building.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
More Reminders that the Specific Contract Terms Matter
January 24, 2022 —
Christopher G. Hill - Construction Law MusingsIf there is a theme I have pounded upon here at Construction Law Musings in the over 13 years of posting, it is that the specific terms of your construction contracts will make a huge difference. While there have been reminders galore, a case from the Eastern District of Virginia presented another wrinkle on this theme. The wrinkle? A factoring company.
In CJM Financial, Inc. v. Leebcor Services, LLC et. al., the Court examined this scenario (though it went into more detail than I will here): Leebcorp hired a subcontractor, Maston Creek Services to provide certain construction services under two separate contracts. Maston then hired CJM, a factoring company, and assigned CJM its receivables and the right to collect those receivables. We wouldn’t be discussing this case if all had worked out as planned, so you likely anticipate at least some of what came next. The short story is that Matson failed to pay some of its suppliers and Leebcorp exercised its termination rights under those contracts when Matson refused to cure. In the interim, CJM had paid part of certain payment applications to Matson in compliance with the factoring agreement. When Leebcorp failed to pay CJM for Matson’s work, CJM exercised its assigned rights to collect the receivables and sued Leebcorp for breach of contract. In response, Leebcorp counterclaimed for, among other counts including civil conspiracy, breach of contract based on Matson’s failure to perform. CJM moved to dismiss the counterclaims.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Challenging and Defending a California Public Works Stop Payment Notice: Affidavit vs. Counter-Affidavit Process
October 21, 2019 —
William L. Porter - Porter Law GroupOne of the most effective collection procedures available to subcontractors and suppliers to California Construction projects is the “stop payment notice” procedure found under California Civil Code sections 9350 – 9364. Under this procedure, the unpaid subcontractor or supplier may serve the stop payment notice on the public entity and the direct or “prime” contractor and cause the public entity to withhold from the direct contractor 125% of the funds identified in the stop payment notice. Thereafter, funds will not generally be released unless the parties reach a settlement agreement or the issue is decided through litigation, arbitration or mediation. There is however an alternative procedure available to direct contractors to expedite the determination of whether a stop payment notice is valid and to possibly obtain an early release of the funds withheld by the public entity. This “summary proceeding” process could result in release of funds to the direct contractor in less than 30 days. The summary proceeding can also be challenged by the unpaid subcontractor or supplier. All public works contractors, subcontractors and suppliers should be aware of the process. The process for direct contractors to release a stop payment notice and for subcontractors and suppliers to challenge the process works as follows:
After a California stop payment notice has been served and the public entity has withheld funds accordingly, the direct contractor may challenge the stop payment notice by serving an “affidavit” (basically a sworn statement showing why the stop notice is not valid) on the public entity, demanding that the public entity release all funds withheld. Upon receipt of such an affidavit, the public entity will serve the subcontractor or supplier who served the stop payment notice with a copy of the affidavit, along with a “demand for release of funds”. If the stop payment notice claimant does not respond with a “counter-affidavit” by the date stated on the notice sent by the public entity (“not less than 10 days nor more than 20 days after service on the claimant of a copy of the affidavit”), then the public entity will be within its rights to release the withheld funds to the direct contractor, and the stop payment notice claimant will relinquish its stop payment notice rights.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
The Creation of San Fransokyo
June 17, 2015 —
Garret Murai – California Construction Law BlogSome of the most awe inspiring buildings and urban environments started off on paper and, these days, on computer screens. Think Babylon or even Pierre Charles L’Enfant’s Washington, D.C..
Most of those structures and cityscapes were designed for human habitation, but not all. Some were designed purely for our imaginations, like Minecraft, which those of you with young ones might be familiar with.
Another more recent example though is Big Hero 6, about a science-whiz named Hiro (pronounced “hero,” get it) who journeys from boyhood to manhood and saves the world along the way with his robot pal Baymax. The movie is set in foreign-yet-familiar “San Fransokyo.”
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
District Court's Ruling Affirmed in TCD v American Family Mutual Insurance Co.
May 10, 2012 —
CDJ STAFFIn the case, TCD, Inc. v American Family Mutual Insurance Company, the district court’s summary judgment was in favor of the defendant. In response, the Plaintiff, TCD, appealed “on the ground that the insurance company had no duty to defend TCD under a commercial general liability (CGL) insurance policy.” The appeals court affirmed the decision.
The appeals ruling provides a brief history of the case: “This case arises out of a construction project in Frisco, Colorado. The developer, Frisco Gateway Center, LLC (Gateway), entered into a contract with TCD, the general contractor, to construct a building. TCD entered into a subcontract with Petra Roofing and Remodeling Company (Petra) to install the roof on the building. The subcontract required Petra to "indemnify, hold harmless, and defend" TCD against claims arising out of or resulting from the performance of Petra’s work on the project. The subcontract also required Petra to name TCD as an additional insured on its CGL policy in connection with Petra’s work under the subcontract.”
Furthermore, “TCD initiated this case against Petra and the insurance company, asserting claims for declaratory judgment, breach of insurance contract, breach of contract, and negligence. The district court entered a default judgment against Petra, and both the remaining parties moved for summary judgment. The court granted summary judgment on the entirety of the action, in favor of the insurance company, concluding that the counterclaims asserted by Gateway against TCD did not give rise to an obligation to defend or indemnify under the CGL policy.”
The appeals court rejected each contention made by TCD in turn. First, “TCD contend[ed] that Gateway’s counterclaims constitute[d] an allegation of ‘property damage,’ which is covered under the CGL policy.” The appeals court disagreed. Next, “TCD argue[d] that [the court] should broaden or extend the complaint rule, also called the ‘four corners’ rule, and allow it to offer evidence outside of the counterclaims to determine the insurance company’s duty to defend in this case.” The appeals court was not persuaded by TCD’s argument.
The judgment was affirmed. Judge Roman and Judge Miller concur.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Taking Service Network Planning to the Next Level
July 22, 2019 —
Aarni Heiskanen - AEC BusinessCities and municipalities are basically systems for delivering services for the benefit of their citizens. An experimental project demonstrated how improving the flow of data between these services could save a lot of time and taxpayer money.
Emilia Rönkkö is an architect who worked for the Finnish city of Kuopio. Besides that, she is a Docent of Urban Planning at the University of Oulu.
“In Kuopio, my job included doing architectural programming for public investments and service network reviews. More specifically, surveys about Growth and Learning Services that were focused on daycares and schools,” Rönkkö explains. “Typically, a service network review with manual data collection procedures takes place every three to five years. I and other functionaries involved in the process wondered if there might be a better, more efficient way to do the reviews.”
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
California’s High Speed Rail Project. Are We Done With the Drama?
October 22, 2014 —
Garret Murai – California Construction Law BlogProponents of California’s high-speed rail project cleared a major hurdle this past week when the California Supreme Court declined to review a California Court of Appeals ruling which held that the state’s funding plan did not violate Proposition 1A, the voter-approved initiative passed in 2008, which provided initial funding for the project.
For those like me who have been following the fits and starts of California’s high-speed rail project, it may be hard to remember how it all got started, and how we got to where we are.
California's High-Speed Rail Project
California’s high-speed rail project involves the construction of a high-speed passenger rail system running from Northern California to Southern California. The $68 billion system, expected to begin operation in 2029, will initially run from San Francisco to the Los Angeles basin in under 3 hours with train speeds capable of over 200 miles per hour. The system will eventually extend from Sacramento to San Diego covering a distance of approximately 800 miles with up to 24 stations.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Kronick Moskovitz Tiedemann & GirardMr. Murai may be contacted at
gmurai@kmtg.com
Should I Stay or Should I Go? The Supreme Court Says “Stay”
June 10, 2024 —
Brendan J. Witry - The Dispute ResolverIn the construction industry, arbitration is a frequently agreed-upon and utilized dispute resolution method. The Federal Arbitration Act (the “FAA”), 9 U.S.C. 1, et seq., provides the underpinning and framework for how courts should handle litigation in connection with arbitration agreements. Where a party asserts that a claim brought in court should be subject to arbitration, Section 3 of the FAA provides that the action should be stayed. However, some courts have entertained a party’s request to dismiss a suit where the claim is subject to an arbitration agreement, creating a circuit split in the federal appeals courts. In
Smith v. Spizzirri, 2024 WL 2193872, issued on May 16, 2024, the Supreme Court held that, absent some other defect (such as the lack of personal or subject matter jurisdiction), Section 3 of the FAA requires a court which finds a claim is subject to an arbitration must stay the lawsuit during the arbitration proceedings rather than dismissing the action.[1] In so doing, the Court addressed a question that for years it left unanswered.
While most Circuits held, prior to Smith, that Section 3 requires a court to stay the litigation pending an arbitral award; the First, Fifth, Eighth, and Ninth Circuits each held that a court could dismiss an action in lieu of staying.
In Smith, both parties acknowledged the underlying claims were arbitrable, but when the district court compelled arbitration, the court dismissed the action rather than staying the court proceedings. The Ninth Circuit (relying on its prior precedent) affirmed, with two judges noting that the Ninth Circuit’s approach was incorrect. The Supreme Court granted certiorari and reversed.
Read the court decisionRead the full story...Reprinted courtesy of
Brendan J. Witry, Laurie & Brennan LLPMr. Witry may be contacted at
bwitry@lauriebrennan.com