Notice and Claims Provisions In Contracts Matter…A Lot
February 27, 2023 —
David Adelstein - Florida Construction Legal UpdatesTechnical contractual provisions in contracts can carry the day. Whether you like it or not, and whether you appreciate the significance of the provisions, they matter. Notice provisions in a contract mean something. Following the claims procedure in a contract means something. The moment you think they don’t mean anything is the moment they will be thrown in your face and used as a basis to deny your position for additional money or time. You may think these provisions are being used as a “gotcha” tactic. They very well might be. But these are provisions included in the contract you agreed to so you know this risk before any basis for additional money or time even arises.
The recent bench trial opinion in Metalizing Technical Services, LLC v. Berkshire Hathaway Specialty Ins. Co., 2023 WL 385413 (S.D.Fla. 2023) illustrates the reality of not properly complying with such provisions. The keys when dealing with any notice or claims provision, or really any technical provision in your contract, is to (a) negotiate the risk before you sign the contract, (b) chart the provisions so your team know how to ensure compliance, and (c) make sure you comply with them. Period!
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Brenda Radmacher to Speak at Construction Super Conference 2024
November 05, 2024 —
Brenda Radmacher - The Construction SeytBrenda Radmacher, partner in Seyfarth’s Construction group, will present and moderate panels at the 38thAnnual Construction Super Conference 2024 on December 9-11. The conference is recognized as the preeminent construction conference developed for mid to senior-level professionals working in legal and commercial construction markets.
Panel – Looking Around Corners: Emerging Trends and Proactive Solutions
Brenda will co-present a panel on innovative ways to engage experts in construction disputes, focusing on early expert involvement to aid in risk management, issue analysis, mitigation, and documentation for potential litigation.
Panel – Top 10 Issues to Address in Your ADR Process for a Better Solution in Construction Disputes
Read the court decisionRead the full story...Reprinted courtesy of
Brenda Radmacher, SeyfarthMs. Radmacher may be contacted at
bradmacher@seyfarth.com
Indiana Appellate Court Allows Third-Party Spoliation Claim to Proceed
August 01, 2023 —
Ryan Bennett - The Subrogation StrategistIn Safeco Insurance Company of Indiana as Subrogee of Ramona Smith v. Blue Sky Innovation Group, Inc., et al, No. 22A-CT-1924, 2023 Ind. App. LEXIS 157, the Court of Appeals of Indiana (Appellate Court) reversed a trial court ruling that granted the motion to dismiss filed by Michaelis Corporation (Michaelis), a restoration company. The Appellate Court ruled that the trial court erred in dismissing the plaintiff’s spoliation and negligence claims against Michaelis, who discarded evidence relating to the cause of the fire at issue.
The plaintiff’s insured owned a home in Indianapolis, Indiana. On Halloween night in 2019, a fire occurred at the property. The plaintiff’s representatives preliminarily determined that the fire may have been caused by a digital dehydrator within the kitchen. Michaelis had a representative present at the site inspection and was allegedly told to preserve the kitchen area. That area was taped off with “caution” tape. Michaelis also placed a tarp over the kitchen to prevent weather damage. Despite the instructions and precautions, Michaelis demolished the kitchen and discarded the dehydrator along with other fire debris.
Read the court decisionRead the full story...Reprinted courtesy of
Ryan Bennett, White and Williams LLPMr. Bennett may be contacted at
bennettr@whiteandwilliams.com
Quick Note: Lis Pendens Bond When Lis Pendens Not Founded On Recorded Instrument Or Statute
May 20, 2019 —
David Adelstein - Florida Construction Legal UpdatesIf a lis pendens is recorded and the lis pendens is NOT founded on a duly recorded instrument (e.g., mortgage) or a statute (e.g., construction lien), a lis pendens bond should be recorded. The lis pendens bond should cover prospective damages associated with the wrongful / unjustified recording of a lis pendens that were suffered by the property owner. The reason being is that the lis pendens has an effect on the title to the property as long as the lis pendens is recorded. Damages could stem from a decline in the market value of the property, continued upkeep and maintenance of the property, and there may also be (and, really, should be) consideration for loss of investment return associated with the equity in that property.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
No Coverage for Faulty Workmanship Based Upon Exclusion for Contractual Assumption of Liability
August 06, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe Supreme Court for West Virginia determined the policy's contractual assumption exclusion barred coverage for the general contractor based upon claims of faulty workmanship. J.A. St & Assocs. v. Bitco Gen. Ins. Corp., 2019 W. Va. LEXIS 205 (May 1, 2019).
J.A. Street & Associates, Inc. entered a contract with the developer, Thundering Herd Development, L.L.C., to build a commercial shopping center on seventy-eight acres of land. Street agreed to oversee the site preparation for the development and the construction of many of the buildings. Thundering Herd retained an engineering firm, S&ME, Inc. to do geotechnical exploration and to provide advice regarding land preparation for the shopping center. Thundering Heard also entered an agreement with the Target Corporation to construct a store on a pad to be prepared at the shopping center.
Street hired subcontractors to prepare the site by grading the land and installing fill material. A slope was constructed at the rear of the proposed Target site, but it failed, causing a landslide, damage to the pad, and damage to adjacent property owned by a third party. Thundering Heard incurred $721,875 in additional costs to repair this slope, reconstruct the Target site, and compensate the neighbor for the damage to the adjacent property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Emotional Distress Damages Not Distinct from “Annoyance and Discomfort” Damages in Case Arising from 2007 California Wildfires
February 16, 2017 —
Kirsten Lee Price & Lawrence S. Zucker II - Haight Brown & Bonesteel LLPIn Hensley v. San Diego Gas & Elec. Co., (No. D070259, filed 1/31/17), the California Court of Appeal for the Fourth Appellate District held that emotional distress damages are available on claims for trespass and nuisance as part of “annoyance and discomfort” damages.
In Hensley, plaintiffs sustained fire damage to their home and property during the 2007 California wildfires. The Hensleys were forced to evacuate as the fires advanced. Although their home was not completely destroyed, it sustained significant damage and they were not able to return home permanently for nearly two months. Thereafter, the Hensleys filed suit against San Diego Gas and Electric Company (“SDG&E”) asserting causes of action for trespass and nuisance, among others. Mr. Hensley, who had suffered from Crohn’s disease since 1991, further claimed that as a result of the stress from the fire, he experienced a substantial increase in his symptoms and his treating physician opined that “beyond a measure of reasonable medical certainty... the stress created by the 2007 San Diego fires caused an increase of [Mr. Hensley’s] disease activity, necessitating frequent visits, numerous therapies, and at least two surgeries since the incident.” SDGE moved, in limine, to exclude evidence of Mr. Hensley’s asserted emotional distress damages arguing he was not legally entitled to recover them under theories of trespass and nuisance. The trial court agreed and excluded all evidence of such damages.
Reprinted courtesy of
Kirsten Lee Price, Haight Brown & Bonesteel LLP and
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP
Ms. Price may be contacted at kprice@hbblaw.com
Mr. Zucker may be contacted at lzucker@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations Devin Brunson on His Promotion to Partner!
April 26, 2021 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is very proud to announce Devin Brunson has been promoted to the position of partner with the firm!
Mr. Brunson came to BWB&O from another civil litigation firm and helped start the Denver, Colorado office along with partners Lucian Greco, John Toohey and Peter Brown. He has taken on a significant leadership role within the firm over the past several years and has been integral in growing the office to its current footprint.
He is licensed to practice law in Colorado, District of Colorado, and in the U.S. District Court. His practice is focused in the areas of civil and business litigation, construction litigation, and employment law. Mr. Brunson has a diverse practice background that includes complex civil litigation and intellectual property disputes and has had the privilege of representing business owners, contractors, corporate executives, and professional athletes during the course of his career.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Court Provides Guidance on ‘Pay-When-Paid’ Provisions in Construction Subcontracts
July 13, 2020 —
Ted R. Gropman & Cindy J. Lee - ConsensusDocsOn April 17, the California Court of Appeal decided Crosno Construction, Inc. v. Travelers Casualty & Surety Company of America,1 effectively narrowing the scope of enforceable “pay-when-paid” provisions in construction subcontracts to the extent the subcontractor seeks recovery against a general contractor’s payment bond surety. Although the Crosno case involved a public works project, the rationale and holding should apply with equal force to private works projects. Basing the bulk of its decision on the Wm. R. Clarke Corp. v. Safeco Insurance Co.2 case, the court found that an open-ended “pay-when-paid” provision in a subcontract is not enforceable against a subcontractor that seeks to recover on a public works payment bond claim. This article discusses the Crosno decision and the implications for contractors on both sides of the contract moving forward.
Brief Case Summary
In Crosno, general contractor Clark Bros., Inc. contracted with the North Edwards Water District (the District) to build an arsenic removal water treatment plant. Clark hired steel storage tank subcontractor Crosno Construction, Inc. to build and coat two steel reservoir tanks. Clark and Crosno’s subcontract included a “pay-when-paid” provision, which stated that Clark would pay Crosno within a “reasonable time” of receiving payments from the owner, but “in no event less than the time Contractor and Subcontractor require to pursue to conclusion their legal remedies against Owner or other responsible party to obtain payment.” After Crosno completed its work, a dispute arose between Clark and the District, and the District withheld payment from Clark (including the monies earmarked for Clark’s subcontractors). Clark sued the District for payment, and Crosno filed its own action against Travelers Casualty and Surety Company of America, the surety on Clark’s statutory public works payment bond, for recovery of the unpaid subcontract balance. Travelers rejected Crosno’s bond claim as premature, invoking the “pay-when-paid” subcontract language and pointing to Clark’s pending payment action against the District. The issue on appeal was whether the “pay-when-paid” provision in the subcontract blocked Crosno from recovering under the payment bond from Travelers while Clark’s lawsuit against the District was still pending.
Reprinted courtesy of
Ted R. Gropman, Pepper Hamilton LLP and
Cindy J. Lee, Pepper Hamilton LLP
Mr. Gropman may be contacted at ted.gropman@troutman.com
Ms. Lee may be contacted at cindy.lee@troutman.com
Read the court decisionRead the full story...Reprinted courtesy of