Quick Note: Subcontractor Payment Bond = Common Law Payment Bond
February 16, 2017 —
David Adelstein – Florida Construction Legal UpdatesWhat is a common law payment bond? A common law payment bond is a bond not required or governed by a statute. For example, if a prime contractor provides the owner a payment bond, that bond will be a statutory payment bond. On the other hand, if a subcontractor provides the general contractor with a payment bond, that bond will be a common law payment bond. Why? Because there is not a statute that specifically governs the requirements of a subcontractor’s payment bond given to a general contractor. The subcontractor’s payment bond is aimed at protecting the general contractor (and the general contractor’s payment bond) in the event the subcontractor fails to pay its own subcontractors and suppliers. The subcontractor’s payment bond will generally identify that claimants, as defined by the bond, are those subcontractors and suppliers the subcontractor has failed to pay. This common law payment bond is not recorded in the public records so sometimes it can be challenging for a claimant (anyone unpaid working under the subcontractor that furnished the bond) to obtain a copy of the bond. With that said, an unpaid claimant should consider pursuing a copy of this bond in certain situations, particularly if it may not have preserved a claim against the general contractor’s statutory payment bond.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
New Joint Venture to Develop a New Community in Orange County, California
April 08, 2014 —
Beverley BevenFlorez-CDJ STAFFTaylor Morrison Home Corporation and two of its largest shareholders have created a joint venture “to acquire and develop the 195.5 acres of San Clemente coast known as Marblehead,” according to GlobeSt.com. The Scottsdale, Arizona-based developer is expected to begin construction on the 300 luxury home site in 2015.
“Marblehead is a truly unique site and one of the last undeveloped tracts of coastal land in California,” said Sheryl Palmer, president and CEO of Taylor Morrison, as quoted by GlobeSt.com. “It presents a tremendous opportunity that will deepen our land inventory of exceptional sites and further our standard of building high-quality homes in premier locations across North America.”
Read the court decisionRead the full story...Reprinted courtesy of
TOP TAKE-AWAY SERIES: The 2023 Annual Meeting in Vancouver
May 22, 2023 —
Marissa L. Downs - The Dispute ResolverProgram coordinators Katie Kohm and Peter Marino put together an amazing annual meeting last week in Vancouver. While its impossible to retread all of the ground we covered in discussing the "future of construction law," here are my top 10 take-aways:
10. Public-private partnerships may finally be taking off in the United States. P3s were slow to be pursued within the United States. According to panelists Peter Hahn, John Heuer, Sean Morley, and Lee Weintraub, this was chiefly because of the reticence of public bodies to deviate from the standard vendor model. Looking at the recent trends, it seems as though the United States--the "sleeping giant of public-private partnerships"--may finally be waking up. In 2022, a total of 29 public-private partnership projects were signed or reached financial close within the United States, representing an increase of 16% from the prior year. Thirty-eight states also now have some form of P3 enabling legislation. While we still lag behind our Canadian cousins, the future of P3s in this country is looking a little brighter.
9. The value proposition for the architecture profession is broken. Architects Lakisha Ann Woods (the CEO of AIA) and Phillip Bernstein (Associate Dean & Professor Adjunct Yale University) shared their thoughts with moderator Kelly Bundy on the challenges facing the architecture profession. The biggest issue they noted was the need to recruit qualified (and diverse) candidates into the profession. Unfortunately, this is difficult to do given the long career track (on average, it becomes 13.1 years to become a licensed architect) and the low salaries paid compared to other professions. Phillip shared that the high average starting salary for architecture grads from Yale (one of the leading programs in the country) is just $76,000. If we want to recruit the best and most innovative candidates into the field, the value proposition needs to change.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Coverage Exists for Landlord as Additional Insured
September 03, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Indiana Court of Appeals determined the landlord was entitled to coverage as an additional insured under the tenant's policy. Selective Ins. Co. v. Erie Ins. Exch., 2014 Ind. App. LEXIS 365 (Ind. Ct. App. July 30, 2014).
Rangeline, LLC owned a warehouse. Rangeline negotiated a lease with Hammons Storage to store insulation manufactured by Knauf Insulation. Pursuant to requirements in the lease, Hammons secured liability coverage with Erie Insurance naming Rangeline as an additional insured.
After Hammons moved insulation into the warehouse for storage, the pipes of the sprinkler system burst, causing damage to the insulation. The cause of the loss was determined to be water from the system freezing, which led to the cast iron fittings cracking, causing the failure of the sprinkler heads.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Best Lawyers Honors 43 Lewis Brisbois Attorneys, Recognizes Three Partners as 'Lawyers of The Year'
September 14, 2020 —
Lewis BrisboisBest Lawyers has selected 43 Lewis Brisbois attorneys across 25 offices for inclusion in its list of 2021 Best Lawyers in America. It has also recognized three Lewis Brisbois partners as "Lawyers of the Year": Los Angeles Partner Jon P. Kardassakis (Mass Tort Litigation / Class Actions - Defendants); Roanoke Partner Paul C. Kuhnel (Medical Malpractice Law - Defendants); and Northwest Indiana Managing Partner Renee J. Mortimer (Personal Injury Litigation - Defendants).
Please join us in congratulating these three partners and the following attorneys on their Best Lawyers recognition.
Reprinted courtesy of
Lewis Brisbois
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
California Appeals Court Remands Fine in Late Completion Case
November 18, 2011 —
CDJ STAFFThe California Court of Appeals in Stanislaus County has reversed the decision of the lower court in Greg Opinski Construction Inc. v. City of Oakdale. The earlier court had awarded the city of judgment of $54,000 for late completion, $3,266 for repair of construction defects and interest, and $97,775 in attorneys’ fees. The late completion of the project was due to actions by the City of Oakdale, however, the court rejected Opinski’s argument that the California Supreme Court decision in Kiewit did not allow this, as his contract with the city established a procedure for claiming extensions.
The appeals court noted that the Kiewit decision has been “criticized as an unwarranted interference in the power of contracting parties to shift the risk of delays caused by one party onto the other party by forcing the second party to give the first notice of any intention to claim an extension of time based on delays caused by first.” They cited Sweet, a professor at Boalt Hall, UC Berkeley’s law school, that Kiewit “gutted” the “provision that conditions the contractor’s right to claim an extension of time for delays beyond his control.”
Further changes in California law in response to the Kiewit decision lead to the current situation which the court characterized as “if the contractor wished to claim it needed an extension of time because of delays caused by the city, the contractor was required to obtain a written change order by mutual consent or submit a claim in writing requesting a formal decision by the engineer.”
Opinski also argued that the lower court misinterpreted the contract. The Appeals court replied that “Opinski is mistaken.” He cited parts of the contract regarding the increase of time, but the court rejected these, noting that “an inability to agree is not the same as an express rejection.”
The court also rejects Opinski’s appeal that “the evidence the project was complete earlier than September 30, 2005, is weightier than the evidence to the contrary,” which they describe as “not a winning appellate argument.” The court points out that the role of an appeals court is not to reweigh the evidence, but to determine “whether the record contains substantial evidence in support of the judgment.”
The court did side with Opinski on one question of the escrow account. They rejected most of his arguments, repeating the line “Opinski is mistaken” several times. They decided that he was mistaken on the timing of the setoff decision and on whether the city was the prevailing party. However, the appeals court did find that Opinski was not liable for interest on the judgment.
The appeals court rejected the awarding of prejudgment interest to the city as the funds from which the judgment was drawn was held in an escrow account. The court noted that the city had access to the funds and could “access the funds when it determined that Opinski had breached the contract.” The appeals court noted that the judgment exhausted the escrow balance and remanded the case to the lower court to determine the amount own to Opinski.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Incorporation, Indemnity and Statutes of Limitations, Oh My!
January 19, 2017 —
Christopher G. Hill – Construction Law MusingsWe all know that the contract is king in Virginia. We also know that Virginia will allow for a so called “incorporation” clause that will allow for “flow down” of certain prime contract provisions in a way that will make those provisions applicable to subcontractors. We also know that a claim for breach of contract or other contractual claim does not last forever due to certain statutes of limitation found in the Code of Virginia. What happens when all of these elements crash together in one place leading to litigation? Well, a relatively recent case from the Virginia Supreme Court gives at least a partial answer.
In Hensel Phelps Construction Company v Thompson Masonry Contractor, Inc, the Virginia Supreme Court considered a claim that arose from construction at Virginia Tech by Hensel Phelps. The construction concluded in 1998 (remember that date). The Prime Contract included language concerning a one year “Guarantee of Work” as well as fairly typical Warranty of Workmanship” language. However the Prime Contract also stated that the one year guaranty term did nothing to affect any other limitations period for any other action pursuant to the Prime Contract (this is important as well because Virginia Tech was not subject to any statute of limitations due to its status as an agency of the Commonwealth of Virginia). Final payment was made to Hensel Phelps and subsequently to the subcontractors in 1999.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
How Long does a Florida Condo Association Have to File a Construction Defect Claim?
September 17, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to a post on Orlando Sentinel’s HOA & Condo Blog, sponsored by the firm Becker & Poliakoff, generally a Condominium Association has “4 years from turnover of control of the Condominium Association from the developer” to file a lawsuit for construction defects. However, the association may have additional time to file.
If defects from the original construction were discovered after the 4 years have lapsed, “[a] condominium association may still pursue a claim for latent defects,” which is one that “is hidden, and not discovered despite the exercise of due diligence, for the period of 4 years from turnover.” The Statute of Repose in Florida is “10 years from the date the building received its original Certificate of Occupancy.”
Read the court decisionRead the full story...Reprinted courtesy of