Be a Good Neighbor: Techniques to Mitigate the Risk of Claims from Adjacent Landowners
December 07, 2020 —
Joshua Levy, Josh Neudorfer & Madeleine Bailey - Construction ExecutiveIn May 2020, a real estate developer performing excavation work in New York was sued by a neighboring property owner for property damage. A court overturned an injunction preventing the developer from continuing excavation work after reviewing a preconstruction assessment that showed the damage to the neighboring property was preexisting—not caused by the excavation (see Feldman v. 3588 Nostrand Ave. LLC as an example)
A preconstruction assessment is one of the most important tools in the arsenal of a developer protecting itself from neighbors bringing claims for property damage. Part two of this series will review the benefits of risk mitigation tools recommended for developers such as postconstruction assessments and monitoring during construction.
Preconstruction Assessment Overview
A preconstruction assessment is a review of a property adjacent to a site where demolition and/or construction activities are to take place. The goal of the assessment is to establish baseline conditions by conducting an inspection of buildings and infrastructure, including identification of existing damage to improvements, so that causation of any alleged damages can be more easily determined.
Reprinted courtesy of
Joshua Levy, Josh Neudorfer & Madeleine Bailey, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Levy may be contacted at joshua.levy@huschblackwell.com
Mr. Neudorfer may be contacted at jneudorfer@thesigmagroup.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Contract Provisions that Should Pique Your Interest
September 30, 2019 —
Christopher G. Hill - Construction Law MusingsConstruction contracts are a big part of my legal practice and the drumbeat here at Construction Law Musings. Why? Because not only does your construction contract set the expectations and “rules of the game” for a construction project, it will be read strictly and literally by the Virginia courts should there be a dispute. For these reasons, construction professionals need to be alert for the language in certain key clauses in a construction contract to assure that these clauses are as balanced as possible and also well understood. Here are my “Top Five”:
- “Pay if Paid”- These clauses are almost always in the subcontracts between a general contractor and a subcontractor and are enforceable in Virginia if drafted correctly and under the proper circumstances.
- Change Orders- Whether work is subject to a change order and the required payment for any changed work are often a key source of contention (read legal fees). A properly drafted and followed change order provision can help avoid much of this contention.
- Indemnity- Much has been made in recent years about indemnity provisions and their enforceability. All parties in the construction payment chain can and should be aware of how to best draft their indemnity provisions to make them enforceable. Failure to do so can be catastrophic.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Hunton Insurance Partner Syed Ahmad Serves as Chair of the ABA Minority Trial Lawyer Committee’s Programming Subcommittee
January 13, 2020 —
Michelle M. Spatz - Hunton Insurance Recovery BlogSyed Ahmad, a partner in Hunton Andrews Kurth’s Insurance Coverage practice, has volunteered to serve as Chair of the
ABA Minority Trial Lawyer Committee’s Programming Subcommittee. The Minority Trial Lawyer Committee (MTL) serves as a resource for minority litigators, in-house counsel and law students, aiming to foster professional development, legal scholarship, advocacy and community involvement. As Chair of the Programming Subcommittee, Syed, who was named to Benchmark Litigation’s 40 & Under Hot List earlier this year, will help advance MTL’s mission of facilitating discussions about diversity and the law and providing career network opportunities for minority trial lawyers.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle M. Spatz, Hunton Andrews KurthMs. Spatz may be contacted at
mspatz@HuntonAK.com
Someone Who Hires an Independent Contractor May Still Be Liable, But Not in This Case
April 18, 2023 —
Katherine Dempsey - The Subrogation StrategistIn Allstate Veh. & Prop. Ins. Co. v. Glitz Constr. Corp., 2023 N.Y. App. Div. LEXIS 1180, 2023 NY Slip Op 01171, the Supreme Court of New York, Appellate Division, Second Department (Appellate Court), considered whether a contractor could be found liable for its subcontractor’s alleged negligence in causing injury to a homeowner’s property. The homeowner’s insurer, as subrogee of the homeowner, sought to recover damages from the contractor despite an allegation that the subcontractor – an independent contractor – caused the injury to the homeowner’s property. Finding that there was no evidence that any of the exceptions to the non-liability rule related to hiring independent contractors applied, the Appellate Court affirmed the lower court’s decision granting judgment in favor of the contractor.
In this case, the homeowner hired the contractor (defendant) to convert her garage area into a bedroom and an office. The defendant later hired a subcontractor to perform the electrical rough-in work. At trial, the homeowner’s insurer (plaintiff) presented evidence that the subcontractor, who damaged an existing wire with a drill bit, caused an electrical failure that resulted in a fire. The defendant argued that it could not be held liable for the subcontractor’s alleged negligence because the subcontractor was an independent contractor and, on appeal, the Appellate Court agreed.
Read the court decisionRead the full story...Reprinted courtesy of
Katherine Dempsey, White and Williams LLPMs. Dempsey may be contacted at
dempseyk@whiteandwilliams.com
Hotel Owner Makes Construction Defect Claim
January 28, 2013 —
CDJ STAFFA lawsuit has been filed over the construction of the GrandStay Hotel & Conference Center in Apple Valley Minnesota. Apple Valley GSRS, LLC, who invested in the hotel, has sued Cole Group Architects and Cornerstone Construction, alleging that the architects design was not to industry standards and that the builder used inferior materials and techniques. The lawsuit makes claim of "significant damage."
The hotel hired an engineer who subsequently recommended that all the stucco and the roof should be be replaced. The stucco has shown signs of cracking and crumbling. The hotel states that the roof has problems with leaking.
Cornerstone has denied the hotel's claims. They have also counter-sued their subcontractors.
Read the court decisionRead the full story...Reprinted courtesy of
Court Strikes Down Reasonable Construction Defect Settlement
December 20, 2012 —
CDJ STAFFThe Court of Appeals of Washington has struck down a construction defect settlement between a building owner and the companies she hired to repair the siding, among other repairs to bring the building up to code. Yuan Zhang hired Hawk Construction LLC to do repair work. Hawk, in turn, hired Ready Construction LLC for some aspects of the project. Hawk and Ready were both insured by Capital Specialty Insurance Corporation.
There were several problems with Ready’s work. After removing old siding, they did not protect the building, nor did they remove all of the damaged layers. Ready covered, but did not fix, a mildew problem under the old siding. When new siding was reattached, the nails used were too short to adequately attach it.
After paying for an inspection of the work, Zhang had Hawk and Ready begin the repairs again, but the work was abandoned without being completed. Zhang sued Hawk for breach of contract. Hawk then sued Ready, claiming that “Ready was liable to Hawk to the extent that Hawk was liable to Zhang.” Capitol retained defense for both contractors.
Zhang settled with Hawk, in an agreement that gave her “the right to collect and/or pursue all costs and attorney fees paid by Hawk or its insurance company defending against the Zhang’s claims and pursuing claims against Ready.” Subsequently, she also settled with Ready. Both companies ceased operations.
Zhang had the settlements reviewed by a court, which concluded that the settlements were reasonable. Capital was allowed to appeal, claiming that the settlement included costs that were Zhang’s responsibility. The appeals court did not examine the question of the reasonableness of the settlement, concluding that Capitol’s interests were relevant only to “questions of bad faith, collusion, and fraud.”
In the case of Zhang, the court concluded that the relationship between Zhang and her former contractors was collusive. The court noted that “bad faith or collusion may exist when the evidence indicates a joint effort to create, in a non-adversarial atmosphere, a resolution beneficial to both parties, yet highly prejudicial to the insurer as intervener.” The court noted that both companies had minimal assets which were, in any case, exempted from the agreement. Further, the court found that the agreements failed to determine “what amount of the repairs related to preexisting water damage.” Zhang’s calculation of costs also included her expenses for architectural and engineering services, which the court points out, “where always Zhang’s costs to bear.”
The court concluded that “the overall structure of the settlements is highly probative of collusion, fraud, or bad faith.” Zhang’s agreements with Hawk and Ready allowed her to collect compensation from Hawk and then collect Ready’s compensation to Hawk for their portion of the settlement, allowing Zhang to collect the monies twice. Further, she was allowed to pursue Capitol for Hawk’s attorney expenses, even though Hawk had none. “The right to recover Hawk’s fees merely set up a windfall recovery for Zhang.” The court described the agreements among Zhang, Hawk, and Ready as “precisely the type of manipulation [the law] is intended to preclude.”
Read the court decisionRead the full story...Reprinted courtesy of
A Relatively Small Exception to Fraud and Contract Don’t Mix
April 01, 2015 —
Christopher G. Hill – Construction Law MusingsRemember all of my posts about how fraud and contract claims don’t usually play well in litigation? Well, as always with the law, there are exceptions. For instance, a well plead Virginia Consumer Protection Act claim will survive a dismissal challenge.
A recent opinion out of the Alexandria division of the U. S. District Court for the Eastern District of Virginia sets out another exception, namely so called fraudulent inducement. In XL Specialty Ins. Co. v. Truland et al, the Court considered the question of whether both a tort and contract claim can coexist in the same lawsuit when the tort claim is based upon the information provided to the plaintiff when that information proves false.
As the courts of Virginia have held for years, only certain information and statements made pre-contract can be the basis for a fraud claim in the face of a contractual duty to perform. One type of statement that is not properly the subject of a fraud in the inducement type claim is sales talk or opinion. Such sales talk (for example claiming that your company is the best for the job) is not the subject of a fraud claim because it is not meant to be relied upon and that such talk is an opinion about future performance, not a false statement of present fact or intent.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Show Must Go On: Shuttered Venues Operators Grant Provides Lifeline for Live Music and Theater Venues
March 29, 2021 —
David Rao - Snell & Wilmer Real Estate Litigation BlogAlthough it’s been a tough twelve months for many live music venues, movie theaters, and performing arts organizations, help may finally be around the corner. On December 27, 2020, the Economic Aid to Hard-Hit Small Businesses, Nonprofits, and Venues Act was signed into law, creating a $15 billion fund for grants to shuttered venues to be administered by the Small Business Administration’s (“SBA”) Office of Disaster Assistance. The law states that Shuttered Venues Operator Grants (“SVOGs”) will be made available to the following entities and individuals:
- Live venue operators or promoters;
- Theatrical producers;
- Live performing arts organization operators;
- Relevant museum operators, zoos, and aquariums which meet specific criteria;
- Movie theater operators;
- Talent representatives; and
- Each business entity owned by an eligible entity that also meets the eligibility requirements.
Read the court decisionRead the full story...Reprinted courtesy of
David Rao, Snell & WilmerMr. Rao may be contacted at
drao@swlaw.com