San Francisco OKs Revamped Settling Millennium Tower Fix
August 29, 2022 —
Nadine M. Post - Engineering News-RecordAfter more than six months of scrutiny, San Francisco’s Department of Building Inspection has issued a revised building permit for the revamped perimeter pile upgrade of the settling 645-ft-tall Millennium Tower, thanks to a determination from the planning department that the revised scheme would not have any negative environmental impacts. The upgrade now consists of 18 piles to bedrock, already installed, rather than 52.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Did You Get a Notice of Mechanic’s Lien after Project Completion? Don’t Panic!
October 20, 2016 —
Christopher G. Hill – Construction Law MusingsSo, you own a piece of property. You decided to have some work done and after what you thought was proper due diligence, you hire a general contractor to build a great office building on the property. Your architect designs the space, you sign the construction contract for a price you find fair and that the bank approves. Construction starts and with a few minor hiccups, a couple of written changes and one minor but slightly annoying change required by the local building inspector, completes relatively on schedule. You write the final check to the general contractor for its final draw and start the process of leasing the space out. All is right with the world as best you can tell.
A month later, you walk to your mailbox and lo and behold, you have a certified mailing containing a notice that the plumbing subcontractor has recorded a mechanic’s lien on your property. After counting to 10 to let the various emotions pass, you call the general contractor to see what is going on. You’re told that there is a dispute regarding a change order about which you knew nothing and that the general contractor feels it is in the right and should not have to pay the money represented in the memorandum of lien so it won’t be paying the subcontractor unless and until it is told to do so by a court or an arbitrator.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, The Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Condos Down in Denver Due to Construction Defect Litigation
November 06, 2013 —
CDJ STAFFA new report suggests that fears of construction defect litigation may be the cause of the slump in condo building in the Denver area. The Denver Business Journal reports that the Denver Regional Council of Governments commissioned the study by Economic & Planning Systems. The conclusion of the report was that the only type of condominium likely to be built is high-cost units with high profit margins. This is not good news for the DRCOG, which is seeking to create more affordable housing.
The report found that builders assess the likeliness of being sued “is nearly 100 percent,” that costs of addressing construction defects are 12% higher than at apartment complexes, and that preparing for litigation adds about $15,000 to the cost of a condo unit.
One possible remedy is to reform Colorado’s construction defect laws. Bob Muphy, the mayor of Lakewook and an advocate of construction defect litigation reform, said that he sees “this as a verification of what I’ve been talking about.”
Read the court decisionRead the full story...Reprinted courtesy of
Houston Home Sales Fall for the First Time in Six Months
March 19, 2015 —
John Gittelsohn and Prashant Gopal - Bloomberg(Bloomberg) -- Houston home sales fell in February for the first time in six months, a sign lower oil prices are spooking buyers.
Sales of single-family houses dropped 5.8 percent from a year earlier to 4,521 homes, the Houston Association of Realtors reported Wednesday. Purchases fell among residences costing less than $150,000 because of tight supply, and among properties selling for more than $500,000 as wealthier buyers paused amid economic uncertainty, said James Gaines, research economist at Texas A&M University’s real estate center.
“They don’t know what the real impact of falling oil prices is,” Gaines said in a telephone interview from College Station, Texas. “We’re living in the twilight of uncertainty.”
Reprinted courtesy of
John Gittelsohn, Bloomberg and
Prashant Gopal, Bloomberg
Mr. Gittelsohn may be contacted at johngitt@bloomberg.net
Mr. Gopal may be contacted at pgopal2@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
When is a “Willful” Violation Willful (or Not) Under California’s Contractor Enforcement Statutes?
April 17, 2019 —
Garret Murai - California Construction Law BlogThe enforcement statutes applicable to the California Contractors’ State License Board aren’t exactly models in clarity. A few examples:
1. Business and Professions Code Section 7107: Abandonment without legal excuse of any construction project or operation engaged in or undertaken by the license as a contractor constitutes a cause for disciplinary action.
2. Business and Professions Code Section 7109: A willful departure in any material respect from accepted trade standards for good and workmanlike construction constitutes a cause for disciplinary action, unless the departure was in accordance with plans and specifications prepared by or under the direct supervision of an architect.
3. Business and Professions Code Section 7110: Willful or deliberate disregard and violation of the building laws of the state, or any political subdivision thereof, . . . or of the safety or labor laws or compensation insurance laws or Unemployment Insurance Code of the State, or of the Subletting and Subcontracting Fair Practice Act, or violation by any licensee of any provision of the Health and Safety Code or Water Code, relating to the digging, boring, or drilling of water wells, constitutes a cause for disciplinary action.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel RosenMr. Murai may be contacted at
gmurai@wendel.com
Pennsylvania: When Should Pennsylvania’s New Strict Products Liability Law Apply?
February 05, 2015 —
Robert Caplan and Timothy Carroll – White and Williams LLPPennsylvania has maintained its own peculiar brand of strict products liability law ever since the Supreme Court decided Azzarello v. Black Bros. Co., Inc.[1] in 1978. Maligned by many as “absurd and unworkable,”[2] if “excessively” orientated towards plaintiffs,[3] Azzarello’s unique approach to the Restatement (Second) of Torts § 402A (1965)[4] has recently been judicially consigned to the dustbin of history.
In Tincher v. Omega Flex, Inc.,[5] decided on November 19, 2014, the Pennsylvania Supreme Court expressly overruled Azzarello leaving in its place a new alternative standards approach to proving a Section 402A claim. An injured worker or subrogated insurer[6] must still prove that the seller, whether a manufacturer or a distributor, placed the product on the market in a “defective condition unreasonably dangerous to the consumer.”[7] But now, under Tincher, a plaintiff must use either a “consumer expectation test” or a “risk-utility test” to establish that criterion.[8]
Reprinted courtesy of
Robert Caplan, White and Williams LLP and
Timothy Carroll, White and Williams LLP
Mr. Caplan may be contacted at caplanr@whiteandwilliams.com; Mr. Carroll may be contacted at carrollt@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Snooze You Lose? Enforcement of Notice and Timing Provisions
November 11, 2024 —
Cornelius F. "Lee" Banta, Jr. - ConsensusDocsDeadlines are an inescapable part of the construction industry. Bid deadlines. Submittal deadlines. Material delivery deadlines. Substantial completion. Final completion. And so, inevitably, fighting about deadlines becomes a necessary byproduct. Was the deadline really a deadline? Was the schedule slippage on the critical path? Should there be an equitable extension to the date of substantial completion? Given the amount of attention and concern conferred on deadlines, those drafting construction contracts naturally seek to clarify which deadlines really matter with the inclusion of notice and timing provisions.
A contract’s change order and claims procedures are often a key friction point for those drafting and administering the contract. Should there be a requirement for prior written notice of a claim for cost/time relief? How much advance notice? Who should the request be sent to? Is a specific form of notice required? What are the consequences of failing to provide timely notice? A practitioner should pay careful attention to negotiating these terms on the front end, because rest assured, these contract provisions will garner scrutiny when a change order dispute boils over.
Read the court decisionRead the full story...Reprinted courtesy of
Cornelius F. "Lee" Banta, Jr., Peckar & Abramson, P.C.Mr. Banta may be contacted at
lbanta@pecklaw.com
Florida Courts Say that Developers Are Responsible for Flooding
July 31, 2013 —
CDJ STAFFThe Florida Supreme Court recently handed down a decision that developers can be held responsible if problems with infrastructure lead to damage to homes. Aaron Kase, writing on Lawyers.com, reviews the case, noting that the court said that “habitability of a home is impacted by stagnant standing water and the erosion of soil upon which the home is constructed. One need not wait until floodwaters inundate the home or the erosion swallows the residential structure to find protection.”
Kase notes that a trial court “sided with the developers’ argument that because the water infrastructure didn’t immediately support the houses, implied warranties of fitness and habitability shouldn’t apply and they shouldn’t be liable.” This was overturned at the district court, with the Supreme Court upholding the district court decision. Lisa Wilcox of Wilcox Law notes that “the Supreme Court determined that the warranty of habitability should be applied to protect home buyers from defects in the construction of these essential services even though they are not part of a home’s completed structure.”
Read the court decisionRead the full story...Reprinted courtesy of