Government Claims Act Does Not Apply to Actions Solely Seeking Declaratory Relief and Not Monetary Relief
March 25, 2024 —
Garret Murai - California Construction Law BlogPerhaps it should come as no surprise, but public entities get special treatment under the law, and when filing a claim against a public entity, in most cases, a claimant is required to file a claim with the public entity before filing suit under the Government Claims Act (Gov. Code §810 et seq.).
But, as the next case demonstrates, that’s not always the case. In Stronghold Engineering Incorporated v. City of Monterey, 96 Cal.App.5th 1203 (2023), the 6th District Court of Appeals examined whether a public works contractor that alleged an extended overhead claim was required to file a Government Claims Act claim before filing suit when its initial complaint was limited to a claim for declaratory relief.
The Stronghold Case
In December 2015, general contractor Stronghold Engineering Incorporated entered into a construction contract with the City of Monterey for the renovation of the City’s conference center and an adjacent city-owned plaza. The construction contract provided that any modification to the construction contract had to be approved by the City through a written change order. No surprise there.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Nationwide Immigrant Strike May Trigger Excusable Delay and Other Contract Provisions
February 23, 2017 —
Adam P. Handfinger & Meredith N. Reynolds – Peckar & Abramson, P.C.Yesterday, February 16, 2017, media outlets reported a nationwide strike by immigrants and
businesses referred to as “A Day Without Immigrants”. The protest, organized largely through
social media, was a response by some to the Trump Administration’s immigration and foreign
trade policies. Participating businesses shut down and immigrants refused to work or spend
money in an eff ort to demonstrate the role of foreign-born workers in the U.S. economy.
While the number of businesses and individuals that participated is not yet known, several
contractors reported labor shortages and construction project delays or temporary shut
downs as a result of the protest.
Reprinted courtesy of
Adam P. Handfinger, Peckar & Abramson, P.C. and
Meredith N. Reynolds, Peckar & Abramson, P.C.
Mr. Handfinger may be contacted at ahandfinger@pecklaw.com
Ms. Reynolds may be contacted at mreynolds@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Not Remotely Law as Usual: Don’t Settle for Delays – Settle at Remote Mediation
May 25, 2020 —
Victor J. Zarrilli, Robert G. Devine & Michael W. Horner - White and Williams LLPThe emergence and rapid spread of COVID-19 has created extraordinary circumstances that have significantly impacted how we go about living, working and interacting with one another. The practice of law is no exception.
While most cases have been postponed and some extended indefinitely, the issues and disputes that first triggered the litigation remain. In fact, the burdens created by social distancing and other responses to the COVID-19 outbreak have served to only increase these disputes and create an urgent need in some for quick resolution.
In our previous article, we summarized some of the best practices that should be applied when taking and defending depositions in a remote, virtual setting. That technology can also offer the same benefits for alternative dispute resolutions. If planned properly, the use of technology allows remote mediations to be conducted as seamlessly as in-person mediations and, in some circumstances, affords additional benefits that can achieve the best possible resolution for all sides.
This article summarizes the opportunities technology has created by which parties can attempt to resolve their disputes through alternative dispute resolution methods, even in a time of social distancing.
Reprinted courtesy of White and Williams LLP attorneys
Victor J. Zarrilli,
Robert G. Devine and
Michael W. Horner
Mr. Zarrilli may be contacted at zarrilliv@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Horner may be contacted at hornerm@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Maybe California Actually Does Have Enough Water
September 06, 2021 —
Francis Wilkinson - BloombergIt’s hard to know how much to panic over California’s dwindling water supplies. The state has never really had enough water, after all, yet lawns in Beverly Hills somehow remain perpetually green. Earlier this month, however, came a sign that life might soon be getting more uncomfortable for more Californians.
On Aug. 3, the State Water Resources Control Board voted 5 to 0 to issue an “emergency curtailment” order for the Sacramento-San Joaquin Delta watershed. Last week the order was submitted to the state’s Office of Administrative Law, which is likely to approve it.
The watershed covers about 40% of the state, stretching roughly from Fresno to Oregon, and is California’s largest source of surface water. About 5,700 holders of water rights, largely in agriculture and business, will be affected by the reduction in water access. Although many farms have already drawn most of the water they need for the season, the board’s move was a sign that ancestral water rights won’t be a guarantee of actual water if drought persists.
Read the court decisionRead the full story...Reprinted courtesy of
Francis Wilkinson, Bloomberg
Payment Bond Surety Entitled to Award of Attorneys’ Fees Although Defended by Principal
February 01, 2023 —
Garret Murai - California Construction Law BlogFor contractors involved in California public works projects the scenario is not uncommon: The general contractor awarded the public works project is required to obtain a payment bond for the benefit of subcontractors and suppliers and the payment bond surety issuing the payment bond requires the general contractor to defend and indemnify the surety from and against any claims against the payment bond.
In
Cell-Crete Corporation v. Federal Insurance Company, 82 Cal.App.5th 1090 (2022), the 4th District Court of Appeal examined whether a payment bond surety, who prevails in a claim against the payment bond, is entitled to statutory attorneys’ fees when the party actually incurring the attorneys’ fees was the general contractor, pursuant to its defense and indemnity obligations, as opposed to the surety itself.
The Cell-Crete Case
General contractor Granite Construction Company was awarded a public works contract issued by the City of Thermal known as the Airport Boulevard at Grapefruit Boulevard and Union Pacific Railroad Grade Separation Project. We’ll just call it the “Project.” Subcontractor Cell-Crete Corporation entered into a subcontract with Granite for lightweight concrete and related work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
New Jersey Rules that Forensic Lab Analysts Can’t be Forced to Testify
August 06, 2014 —
Beverley BevenFlorez-CDJ STAFFThe New Jersey Law Journal reported that the New Jersey Supreme Court has rejected a rule that would have required “laboratory analysts who prepare forensic reports in criminal cases be available for cross-examination at trial.”
The court stated that “requiring every analyst who was involved in the testing to be available for questioning by the defense was not required by the U.S. Constitution's Sixth Amendment Confrontation Clause and that doing so would create ‘practical drawbacks that range from moderate to severe.’”
Read the court decisionRead the full story...Reprinted courtesy of
Massachusetts Federal Court Rejects Adria Towers, Finds Construction Defects Not an “Occurrence”
July 03, 2022 —
Eric B. Hermanson & Austin D. Moody - White and WilliamsIn an important ruling for insurers, U.S. District Court Judge Patti Saris found that Massachusetts does not follow the position taken in Cypress Point Condo Association v. Adria Towers, LLC, 226 N.J. 403, 418 (2016), i.e., it does not hold that "faulty workmanship claims [should be recognized] as ... an 'occurrence,' thus triggering coverage, 'so long as the allegedly defective work [was] performed by a subcontractor rather than the policyholder itself."
[1]
Instead, Judge Saris reaffirmed earlier Massachusetts authority holding faulty work is not an "occurrence" for coverage purposes,
[2] and found this authority applied whether or not the work in question was subcontracted.
In the alternative, Judge Saris found, even if a contractor's faulty work could be deemed an an "occurrence," such work did not constitute covered "property damage," because none of the alleged damage was "outside the scope of the work that Tocci was contractually required to fulfill as general contractor."
[3]
Reprinted courtesy of
Eric B. Hermanson, White and Williams and
Austin D. Moody, White and Williams
Mr. Hermanson may be contacted at hermansone@whiteandwilliams.com
Mr. Moody may be contacted at moodya@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Mobile Home Owners Not a Class in Drainage Lawsuit
March 01, 2012 —
CDJ STAFFComparing it to a “complex construction defect action,” the California Court of Appeals for Orange County has rejected the claims of a group of mobile home owners that they should be certified as a class in their lawsuit against Huntington Shorecliffs Mobilehome Park. The Appeals court sustained the judgment of the lower court. The court issued a decision in the case of Criswell v. MMR Family LLC on January 17, 2012.
The claims made by the group were that the owners and operators of the mobile home park had known of an “on-going and potentially worsening shallow groundwater condition on the property” and had “exacerbated the problem by changing ‘the configuration and drainage related to the hillside that abuts’ the park.” The homeowners claimed that the class should consist of “any past or current homeowner during the same time frame” who had experienced “the accumulation of mold, fungus, and/or other toxins,” “property damage to his/her mobilehome and/or other property resulting from drainage problems, water seepage, water accumulation, moisture build-up, mold, fungus, and/or other toxins,” emotional distress related to drainage problems or mold, and finally health problems “resulting from exposure to drainage problems, water seepage, water accumulation, moisture build-up, mold, fungus, and/or other toxins, in or around one’s home, lot, or common areas of the park.”
The lower court concluded that while the limits of the class were identifiable, they failed to constitute a class in other ways. First, the people affected were small enough in number that they could be brought together. They “are not so numerous that it would be impracticable to bring them all before the Court.”
The court noted that while many of the homeowners would have issues in common, they did not find “a well-defined community of interest among the class members.” The Appeals Court wrote that “the individual issues affecting each mobile home and homeowner will predominate over the common issue of the presence of standing or pooling water in and around the park.” The court noted that each home would be affected differently by water and “the ‘accumulation of mold, fungus, and/or other toxins.’”
While the court conceded that there would be common issues, such as the “defendants’ alleged concealment of excess moisture conditions and their allegedly negligent roadwork and landscaping,” they noted that “these common issues would be swamped by the swarm of individual determinations of property damage, emotional distress, and personal injury.” The Appeals Court cited an earlier case that ruled against certification “if a class action ‘will splinter into individual trials.’” The court affirmed the judgment of the lower court that they could not proceed as a class.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of