Renovation Contractors: Be Careful How You Disclose Your Projects
December 09, 2011 —
Derek J. Lindenschmidt, Colorado Construction LitigationIn Palu and Beyer v. Toney, 2011 WL 2560249 (Bankr. D. Colo.), the United States Bankruptcy Court for the District of Colorado determined that a Colorado District Court order granting summary judgment in favor of plaintiff home buyers was binding on the Bankruptcy Court in the defendant contractor’s bankruptcy proceeding based on issue preclusion.
Pertinent to this column is the subject matter of the summary judgment motion: Colorado’s Seller’s Property Disclosure (Form LC-18-5-04). In the underlying state court action, the plaintiff home buyers filed a motion for summary judgment contending that the defendant contractor represented to them, through the Seller’s Property Disclosure, that there were no present or past conditions involving moisture or water problems, roof problems or leaks, skylight problems, or gutter downspout problems.
In granting plaintiffs’ motion, the state court determined that the defendant contractor made these representations on her Seller’s Property Disclosure despite witnessing water leaking from the skylight onto the floor and being aware of repairs to the roof, skylight, and interior drywall prior to the sale of the property.
Read the full story…
Reprinted courtesy of Derek J. Lindenschmidt of Higgins, Hopkins, McClain & Roswell, LLP. Mr. Lindenschmidt can be contacted at lindenschmidt@hhmrlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Prefabrication Contract Considerations
March 08, 2021 —
David Adelstein - Florida Construction Legal UpdatesPrefabrication (also referred to as modular construction in instances), is a form of offsite construction where certain construction activities occur at an offsite manufacturing facility or location. Construction components or units are preassembled (prefabricated) at this offsite location prior to being delivered to the project site and then integrated into the project.
When preparing a prefabrication contract (including a prefabrication subcontract), there are a number of complex considerations that need to be weighed, and these considerations are bullet-pointed below. The purpose of these bullet-points is to give you considerations to discuss and vet when preparing, negotiating, and agreeing to a prefabrication contract or subcontract.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
“Genuine” Issue of “Material” Fact and Summary Judgments
December 18, 2022 —
David Adelstein - Florida Construction Legal UpdatesThis is short article on summary judgments. A motion for summary judgment, as you may already know, is a procedural vehicle to try to dispose of issues or claims in a lawsuit, either partially or fully. The objective is that the moving party claims that there is no genuine issue of material fact and that they are entitled to a judgment (partially or finally) as a matter of law. See Florida Rule of Civil Procedure 1.510. In May of 2021, Florida adopted the federal summary judgment standard which theoretically means trial courts should grant more summary judgments, not less, based on the more rigorous standard.
There have been many articles that discuss Florida’s new summary judgment standard including how the standard used to be versus how it is supposed to be now that it is modeled after the federal standard. That isn’t the point of this posting. (Here is an article published in the Florida Bar Journal that provides a primer on summary judgments in case you are interested.)
The point of this posting is to understand the words “genuine” and “material” as underlined above when moving for or defending against a summary judgment. These words have important meaning in the context of motions for summary judgment. In other words, what is a genuine issue of material fact? This is a question that should not be overlooked because these are the facts you want to focus on and frame your arguments on when moving for or defending against a summary judgment. Notably, these are also the facts you want to introduce and emphasize at trial.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Contractor Convicted of Additional Fraud
November 18, 2011 —
CDJ STAFFA Pennsylvania contractor in prison for fraud has been convicted with insurance fraud. The York Daily Record reports that Steven D. Gebhart was already in jail for fraud for about $350,000 for work he either failed to finish or even start or by using substandard materials and practices when he was convicted of insurance fraud. Gebbert’s offices were destroyed in a fire that was later determined to be arson. He was not charged with this, but instead for overestimating his losses to the insurance company. Sentencing for the fraud charge will be on December 21.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
DoD Will Require New Cybersecurity Standards in 2020: Could Other Agencies Be Next?
September 09, 2019 —
Alexander Gorelik - Smith CurrieThe Department of Defense (DoD) has announced a new five-tier standard for cybersecurity certification, which it calls the Cybersecurity Maturity Model Certification, or “CMMC”. Taking an unusual approach to informing the industry, the DoD has provided only limited information about the new standard through its website and a “road tour” led by the newly-appointed head of the DoD’s Chief Information Security Office (CISO), Ms. Katie Arrington.
During her recent presentation at the National Institute of Standards and Technology’s (NIST’s) Information Security and Privacy Advisory Board (ISPAB) meeting, on August 8, 2019, Ms. Arrington revealed several new details about the requirements. Outlined below are the most significant facts from that presentation and the DoD’s website:
All companies doing business with DoD (and all tiers of subcontractors) will need to obtain CMMC certifications.
DoD will require the new certifications from all contractors (including suppliers and subcontractors) that are performing under a DoD contract. Even contractors that do not process or handle Controlled Unclassified Information (CUI) must obtain CMMCs.
Read the court decisionRead the full story...Reprinted courtesy of
Alexander Gorelik, Smith CurrieMr. Gorelik may be contacted at
agorelik@smithcurrie.com
Approaching Design-Build Projects to Avoid (or Win) Disputes
August 07, 2023 —
Stuart Eisler - Construction ExecutiveStakeholders engage in design-build projects believing the collaborative nature better aligns parties' interests and reduces overall risk exposure. Each of the lead parties bases this belief on different factors—the owner sees an opportunity to reduce change-order exposure and improve delivery times, the design-builder (or contractor) aims to control design volatility by ensuring project components match budgeted projections, and the designer intends to benefit by greater constructability review from the design-builder team and often additional time to detail designs. Rarely do design-build parties contemplate claims arising while initiating a project.
This being said, design-build projects carry unique, inherent risks due to the award of often fixed-price contracts utilizing incomplete, preliminary designs. As scopes creep and costs balloon, previously harmonious parties experience discord and lurking claims. While the majority of design-build projects are completed without major dispute, there are strategies available to further avoid disputes and prevail in those that are unavoidable.
Reprinted courtesy of
Stuart Eisler, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Where Breach of Contract and Tortious Interference Collide
January 11, 2022 —
Christopher G. Hill - Construction Law MusingsClaims for breach of contract are numerous in the construction law world. Without these claims we construction attorneys would have a hard time keeping the doors open. A 2021 case examined a different sort of claim that could arise (though, “spoiler alert” did not in this case) during the course of a construction project. That type of claim is one for tortious interference with business expectancy.
In Clark Nexsen, Inc. et. al v. Rebkee, the U. S. District Court for the Eastern District of Virginia gave a great explanation of the law of this type of claim in analyzing the following basic facts:
In 2018, Clark Nexsen, Inc. (“Clark”) and MEB General Contractors, Inc. (“MEB”) responded to Henrico County’s (“Henrico”) Request for Proposals (“RFP”) for the design and construction of a sport and convocation center (the “Project”). Henrico initially shortlisted Clark and MEB as a “design-build” team for the Project, but later restarted the search, issuing a second RFP. Clark and MEB submitted a second “design-build” proposal, but Henrico selected Rebkee Co. (“Rebkee”) for certain development aspects of the Project. MEB also submitted proposals to Rebkee, and Rebkee selected MEB as the design-builder for the Project. MEB, at Rebkee’s request, solicited proposals from three design firms and ultimately selected Clark as its design partner. From December 2019 to May 2020, Clark and MEB served as the design-build team to assist Rebkee in developing the Project. In connection therewith, Clark developed proprietary designs, technical drawings, and, with MEB, several cost estimates. In February 2020, MEB submitted a $294,334.50 Pay Application to Rebkee for engineering, design, and Project development work. Rebkee never paid MEB. Henrico paid MEB $50,000.00 as partial payment for MEB’s and Clark’s work. MEB then learned that Rebkee was using Clark’s drawings to solicit design and construction proposals from other companies. On July 23, 2020, Rebkee told MEB that Henrico directed it to cancel the design-build arrangement with MEB and Clark and pursue a different planning method. MEB and Clark sued and Rebkee for, among other claims, tortious interference with a business expectancy. Rebkee moved to dismiss the tortious interference claim.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The CA Supreme Court Grants Petition for Review of McMillin Albany LLC v. Super Ct. 2015 F069370 (Cal.App.5 Dist.) As to Whether the Right to Repair Act (SB800) is the Exclusive Remedy for All Defect Claims Arising Out of New Residential Construction
December 02, 2015 —
Richard H. Glucksman, Esq., Glenn T. Barger, Esq., Jon A. Turigliatto, Esq., & David A. Napper, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinAs anticipated in a prior CGDRB 2015 Bulletin that discussed the Fifth Appellate District Court’s noteworthy opinion in McMillin Albany LLC v. Super Ct. 2015 F069370 (Cal.App.5 Dist), the California Supreme Court has granted the petition for review of the McMillin Albany decision. The Supreme Court will attempt to resolve the conflict of authority presented by the Fourth Appellate District Court’s opinion in Liberty Mut. Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98 and the Fifth Appellate District Court’s rejection of the Liberty Mutual holding in McMillin Albany.
In Liberty Mutual, the Fourth District Court of Appeal held that compliance with SB800’s pre-litigation procedures prior to initiating litigation is only required for defect claims [violations of SB 800’s building standards] that have not yet resulted in actual property damage. Where damage has occurred, a homeowner may initiate litigation under common law causes of action without first complying with the pre-litigation procedures set forth in SB 800.
Two years later, the Fifth District Court of Appeal, in McMillin Albany, held that the California Legislature intended that all construction defect claims arising out new residential construction are subject to the standards and requirements of the Right to Repair Act [SB800], including specifically, the requirement that the claimant provide the builder with notice and an opportunity to repair prior to filing a lawsuit. According to the Court, SB 800 is the exclusive remedy for all defect claims arising out of new residential construction sold on or after January 1, 2003.
The holdings in Liberty Mutual and McMillin Albany present a conflict of authority that the California Supreme Court has appropriately deemed worthy of review. The parties will now be permitted to file briefs on the merits and amicus briefs will certainly be submitted by the defense and plaintiff bars.
Our firm will be closely monitoring this case, the outcome of which will significantly impact pre-litigation construction defect claims going forward. We will provide updates as to further activities and the Supreme Court’s decision.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Glenn T. Barger,
Jon A. Turigliatto and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Barger may be contacted at gbarger@cgdrblaw.com
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of