Insurer's Motion for Summary Judgment on Faulty Workmanship Denied
June 04, 2024 —
Tred R. Eyerly - Insurance Law HawaiiThe court found that the insurer failed to meet its burden on summary judgment seeking a judgment that faulty workmanship precluded coverge. Auto-Owners Ins., Co. v. AAA Discount Homes, LLC, 2024 U.S. Dist. LEXIS 48463 (S.D. Ga. March 19, 2024).
Heather Way sued AAA Discount Homes, LLC and Delta Transport & Management, Inc. for manufacturing defects found in a manufactured home which was delivered and assembled by Delta. Way had contracted with AAA for the construction, delivery, assembly, setting, tie down with brick underpinning steps and construction of front and back porches. AAA, assisted by Delta, delivered the home and assembled it, including raising the roof, over the course of a few days.
Subsequently, Way discovered extensive water damage and mold in the home. Way alleged that AAA and its subcontractors made careless, unsafe, and unsuccessful attempts at removing the old and repairing the water damage. The presence of chemicals in the home made it uninhabitable. Way alleged the home was improperly assembled by Delta and its negligence resulted in damages.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Forethought Is Key to Overcoming Construction Calamities
February 10, 2020 —
Mitch Cohen - Construction ExecutiveWithout warning, an under-construction structure in the southern United States suffered a catastrophic collapse. The tragedy resulted in the death of several people. As a result, engineering and construction post-collapse forensics experts engaged in an 18-month investigation.
Those involved in the design and build project included the general contractor hired by the owner, a prime engineer, a consulting peer-review engineer and a prime structural design firm supported by a sub-consulting structural engineer. Although significant cracking was noticed several weeks before the failure, no one sounded the alarm or deemed the cracking worthy of corrective action.
In their findings, forensic experts found the collapse resulted from the combined failure of the general contractor, engineers and even the owner, who all failed to shut down the work once the cracking reached unacceptable levels and/or take the appropriate actions needed to secure the public safety and mitigate the risk. This was even after the general contractor requested that the engineer-of-record and design manager assess the structure’s extreme cracking. Consequently, the choice to not seriously investigate the crack or seek an independent peer review to design a rectification plan contributed directly to the tragedy. This is typically referred to within the industry as a “negligent professional design error.”
Reprinted courtesy of
Mitch Cohen, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Cohen may be contacted at
mitch.cohen@rtspecialty.com
Need to Cover Yourself for “Crisis” Changes on a Job Site? Try These Tips (guest post)
July 02, 2018 —
Melissa Dewey Brumback – Construction Law in North CarolinaToday, we welcome back friend of the blog Christopher G. Hill.
Chris is a LEED AP, a Virginia Supreme Court certified mediator, construction lawyer and owner of the Richmond, VA firm, The Law Office of Christopher G. Hill, PC. Chris authors the Construction Law Musings blog where he discusses legal and policy issues relevant to construction professionals.
As construction professionals we’ve all been there. Something happens on a job site that requires immediate attention and possibly a changed sequence of work or possibly a change to a subcontractor’s scope. It could be a buried power line that Miss Utility failed to mark properly or an owner that wants a different HVAC configuration at the last minute. It could also simply be that it rained too much, and work had to slow down.
The above examples are instances of items that are beyond the control of the general contractor or the subcontractors and are the type that require shifts in work schedules and changes in scope that must be dealt with on the fly and require quick decisions and immediate action if the project is to meet any time of completion reasonably close to that which is listed in the contract documents. It can often seem that there is no time to meet the written change order provisions of any well drafted construction contract.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale Liggett PLLCMs. Brumback may be contacted at
mbrumback@rl-law.com
CAPSA Changes Now in Effect
November 14, 2018 —
Wally Zimolong - Supplemental ConditionsBack in June, I posted about changes coming to the Pennsylvania Contractor and Subcontractor Payment Act (CAPSA), 73 P.S. Section 501, et. seq. The Act applies to virtually all private construction projects in Pennsylvania. As of last week (Oct. 10), those changes are effective. While there is some argument to the contrary, these changes are NOT retroactive and apply to all projects going forward from that date. To recap, here are some of the important changes you need to be aware of:
- Contractual waivers. Parties cannot waive the applicability of the act through contract. Therefore, any clause in a contract purporting to waive the Payment Act’s applicability is void.
- Suspension of work. Unpaid contractors and subcontractors have always enjoyed a common law right to suspend performance until payment was made. Now, they also have a statutory right to do so. Section 5 of the Payment Act ads a subpart (e) which states that an unpaid contractor or subcontractor can suspend performance without penalty if it is not paid.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com
Builders Can’t Rely on SB800
October 01, 2013 —
CDJ STAFFIn coming to their ruling on SB800, the California Court of Appeals looked to the legislative intent behind the law. Valentine Hoy, Timothy Hutter, and Erin Sedloff of Allen Matkins, in an article on the ruling, note that SB800 was written in response to Aas v. Superior Court, in which the court found that there was no remedy for construction defects that had not resulted in property damage. In the latest ruling, Liberty Mutual v. Brookfield Crystal Cove, LLC, the court concluded that SB800 was passed to give homeowners a way to address defects that had not lead to damage. However, the court also concluded that the legislature did not intend for SB800 to be the only remedy.
In Liberty Mutual, the insurance company sought reimbursement for claims it had paid on a homeowner’s claim after a fire sprinkler pipe burst. Liberty Mutual had insured the homeowner and sought repayment from the builder. Escrow had closed on the home in 2004, the pipe burst in 2008, and Liberty Mutual filed their claim in 2011, seven years after the close of escrow. But for plumbing issues, SB800 has a four-year statute of limitations.
The writers describe California as “a hotbed for construction defect litigation.” Due to the Liberty Mutual ruling, developers now “cannot rely on the statutes of limitation set forth in SB800.”
Read the court decisionRead the full story...Reprinted courtesy of
Quick Note: Subcontractor Payment Bond = Common Law Payment Bond
February 16, 2017 —
David Adelstein – Florida Construction Legal UpdatesWhat is a common law payment bond? A common law payment bond is a bond not required or governed by a statute. For example, if a prime contractor provides the owner a payment bond, that bond will be a statutory payment bond. On the other hand, if a subcontractor provides the general contractor with a payment bond, that bond will be a common law payment bond. Why? Because there is not a statute that specifically governs the requirements of a subcontractor’s payment bond given to a general contractor. The subcontractor’s payment bond is aimed at protecting the general contractor (and the general contractor’s payment bond) in the event the subcontractor fails to pay its own subcontractors and suppliers. The subcontractor’s payment bond will generally identify that claimants, as defined by the bond, are those subcontractors and suppliers the subcontractor has failed to pay. This common law payment bond is not recorded in the public records so sometimes it can be challenging for a claimant (anyone unpaid working under the subcontractor that furnished the bond) to obtain a copy of the bond. With that said, an unpaid claimant should consider pursuing a copy of this bond in certain situations, particularly if it may not have preserved a claim against the general contractor’s statutory payment bond.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Washington State Updates the Contractor Registration Statute
June 17, 2015 —
Beverley BevenFlorez-CDJ STAFFRyan W. Sternoff of Ahlers & Cressman PLLC, analyzed SHB 1749, which recently amended RCW 18.27.010, Washington State’s legislature’s contractor’s registration statute. According to Sternoff, “a broad reading of the contractor’s registration statute, RCW Ch. 18.27, would require just about any person or entity, other than a residential homeowner, who is involved at any level in improving real property to be registered as a ‘Contractor,’ irrespective if that person or entity hired a licensed contractor to perform work on real property that they own.” SHB 1749 amended the statute “so that those who ‘offer to sell their property without occupying or using the structures, projects, developments or improvements’ are excluded from the definition of ‘contractor’ and not required to be registered, provided that the person or entity ‘contracts with a registered general contractor and does not superintend the work.’”
Read the court decisionRead the full story...Reprinted courtesy of
2021 California Construction Law Update
December 29, 2020 —
Garret Murai - California Construction Law BlogThis Christmas looks to be a Blue Christmas as the nation grapples with rising infection, hospitalization and death rates due to COVID. But there’s always 2021 to look forward to, which, of course, also means new laws impacting the construction industry.
Due to COVID there were two unscheduled breaks during the second half of the 2019-2020 legislative session as legislators sheltered-in-place. As a result, there were fewer bills introduced and enacted than in previous legislative session. A total of 2,223 bills were introduced in 2020 compared to 2,625 bills in 2019, of which 428 bills made it to the Governor’s desk, and 372 were signed into law.
Among the bills signed into law were bills, unsurprisingly, related to COVID. In addition, the 2020 legislative session saw the passage of legislation creating a new licensing classification for residential renovation contractors, new laws expanding and clarifying when prevailing wages are required to be paid, and legislation extending the period during which seniors can cancel certain contracts.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com