Public Projects in the Pandemic Pandemonium
September 07, 2020 —
Ashlynn E. Hutton, Michael J. Crook & Christian F. Torgrimson - Construction ExecutiveDespite the ongoing pandemic, states are opening up for business and establishing a new normal. This determination to move forward includes pushing public transportation projects full steam ahead. While this may be good news for certain industries, it may not be for commercial property owners hoping to see a slow down to public projects and avoid a taking of private property. As many grapple with new economic realities, we examine the approaches employed by states in the southeast to manage construction of public projects in this unprecedented time.
GEORGIA
The Georgia Department of Transportation (GDOT) is moving forward with all of its previously funded public projects, including the massive I-285 Top-End Project, designated as a “Major Mobility Project” for the Atlanta metro region. Affecting approximately 260 property owners along I-285 and Georgia Highway 400, environmental review of the project continues. GDOT anticipates a contract let date in 2022 and construction start in 2023. Like ocean liners, these projects don’t turn on a dime. Under the 2015 Transportation Funding Act, the budgeted funds cannot be shifted to other needs or projects due to economic shutdown. Once environmental review is complete, GDOT will approve the final design and move toward acquiring right-of-way from affected property owners.
Reprinted courtesy of
Ashlynn E. Hutton, Michael J. Crook & Christian F. Torgrimson, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Federal Court of Appeals Signals an End to Project Labor Agreement Requirements Linked to Development Tax Credits
October 20, 2016 —
Gregory R. Begg & Aaron C. Schlesinger – Peckar & Abramson, P.C.What Action Should Owners, Developers and Contractors Take in Anticipation of Successful Challenges to PLA Requirements?
Recently, a federal court in New Jersey issued a decision which very well may invalidate all Project Labor Agreements (“PLA’s”) entered into as a condition to receipt of tax incentives for private development. Tax incentives utilized to promote private development are different, according to the court, than typical public works projects where PLA requirements have generally been held valid. Owners, developers, contractors and governmental entities must assess the consequences of this decision upon contracts already and to be awarded in the future where tax benefits may be linked to a PLA requirement.
In 1993, in what has become known as the Boston Harbor Case, the United States Supreme Court held that state and local governmental entities may condition the award of public works contracts on the contractor’s agreement to enter into PLA’s.
That decision has been followed nationwide since then to uphold the validity of various state and local law bidding conditions requiring successful bidders to negotiate and enter into project labor agreements as a condition to the award of public works contracts. The rationale is that when the government, like any other private party, is participating in an economic market, it may exercise its discretion in setting terms and conditions it believes best suit its interests in the efficient procurement of goods and services in that market. Therefore, a PLA requirement by a governmental entity engaged in market activity is no more or less valid than a PLA requirement on a purely private project.
Reprinted courtesy of
Gregory R. Begg, Peckar & Abramson, P.C. Aaron C. Schlesinger, Peckar & Abramson, P.C.
Mr. Begg may be contacted at gbegg@pecklaw.com
Mr. Schlesinger may be contacted at aschlesinger@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Define the Forum and Scope of Recovery in Contract Disputes
March 02, 2020 —
Phillip L. Sampson Jr. & Richard F. Whiteley - Construction ExecutivePrivate and public companies spend billions of dollars every year on construction projects. For these projects, time is money, and incorporating the most advantageous legal terms in the construction contract can minimize the number and extent of disputes, and ultimately save money.
It is important to remember that the provisions in construction contracts are negotiable. In a common scenario, the contractor and owner informally agree to the scope of a construction project and its cost. When it is time to reduce the deal to writing, the contractor and owner decide to use an AIA contract that appears to be a standard form. The document looks to be on point, and the parties simply need to fill in a few blanks with the cost and scope-specific information. Presuming that the AIA provisions are mutually protective and beneficial, the parties do not think about altering the “standard” terms. They sign the contract, and the project begins.
Months later, the owner and contractor end up disputing delays on the project, entitlement to various payments, and whether certain aspects of the work are defective. At this point, the parties realize that some of the contract’s terms could have been drafted a bit more favorably—but by that time it’s too late. So remember, construction contracts are negotiable, even provisions within “standard” AIA contracts.
Reprinted courtesy of
Phillip L. Sampson Jr. and Richard F. Whiteley, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Sampson may be contacted at phillip.sampson@bracewell.com.
Mr. Whiteley may be contacted at richard.whiteley@bracewell.com.
Read the court decisionRead the full story...Reprinted courtesy of
Determining Duty to Defend in Wisconsin Does Not Include Extrinsic Evidence
September 22, 2016 —
Tred R. Eyerly – Insurance Law HawaiiThe policyholder's attempt to extend the duty to defend analysis beyond the complaint's allegations and the four-corners of the policy failed before the Wisconsin Supreme Court. Water Well Solutions Service Group Inc. v. Consolidated Ins. Co., 2016 Wisc. LEXIS 163 (Wis. Sup. Ct. June 30, 2016).
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Bertha – The Tunnel is Finished, but Her Legacy Continues
September 28, 2017 —
John P. Ahlers - Ahlers & Cressman PLLCThe Tunnel Boring Machine (“TBM”) known as “Bertha,” built by Hitachi Zosen Corp in Osaka, Japan, was the world’s largest TBM at 57.5 ft. in diameter. The TBM was built to drill the Seattle SR 99 Viaduct replacement tunnel. Seattle Tunnel Partners (“STP”) has a contract with the Washington State Department of Transportation (WSDOT) to dig the two-mile tunnel which is now complete.
In December of 2013, tunneling was stopped ostensibly because a 119 ft.-long, eight-inch diameter steel well casing halted the TBM. See 2/15 Blog “Bertha is Stuck and She Remains Mired in Controversy.” Reports are that WSDOT installed the pipe in 2002 to measure groundwater levels and the pipe was allegedly mentioned in the reference material provided to bidders. STP had assumed that the pipe had been removed until the steel casing got stuck in Bertha’s cutting teeth, halting progress. See 1/30/14 Blog “Big Bertha Stuck: Differing Site Condition Principles Revisited.” STP had a design-build contract with WSDOT. The contract contains a Differing Site Conditions (“DSC”) clause pursuant to which if the contractor can prove that the eight-inch pipe was an unforeseen condition (not disclosed in the contract documents), and that the unforeseen condition caused the TBM’s failure, STP is entitled to an equitable adjustment of its contract.
Read the court decisionRead the full story...Reprinted courtesy of
John P. Ahlers, Ahlers & Cressman PLLCMr. Ahlers may be contacted at
jahlers@ac-lawyers.com
Google’s Biggest Moonshot Is Its Search for a Carbon-Free Future
November 15, 2021 —
Mark Bergen - BloombergGoogle Bay View, the company’s newest campus, consists of three squat buildings nestled near the San Francisco Bay shoreline a few miles east of its headquarters in Mountain View, Calif. The first things visitors notice are the roofs.
They curve down gently from pinched peaks, like circus tents, sloping almost to the ground. Each roof is blanketed with overlapping solar panels that glisten with a brushed metal sheen on the edges. Google calls this design Dragonscale, and indeed it looks as if a mystical beast is curled up by the water in Silicon Valley.
Google envisions its latest campus as the embodiment of a grander ambition to run its operations entirely free of carbon. The company plans to open Bay View in January to “a limited number” of employees, depending on the pandemic. Beneath the buildings, thousands of concrete pillars plunged into the ground will serve as a sort of geothermal battery, storing heat to warm the building and water supply without natural gas. The roof panels were constructed with a unique textured glass to prevent glare and with canopies that emit a soft, glowing light into the spacious atria inside. “We call this the Cathedral of Work,” says Asim Tahir, who oversees energy decisions in Google’s real estate division. He stands by the southern entrance in a hard hat, mask, and safety vest.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Bergen, Bloomberg
Milwaukee's 25-Story Ascent Stacks Up as Tall Timber Role Model
January 25, 2021 —
Nadine M. Post - Engineering News-RecordIn January 2019, Preston Cole left his post as Commissioner of the Milwaukee Dept. of Neighborhood Services and became Secretary of Wisconsin’s Dept. of Natural Resources. It was a step up for the 25-year veteran of public service—a forester by profession—who as the city’s top building official had reformed DNS by fostering a developer-friendly environment.
Reprinted courtesy of
Nadine M. Post, Engineering News-Record
Ms. Post may be contacted at postn@enr.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
The International Codes Development Process is Changing to Continue Building Code Modernization
March 06, 2023 —
The International Code CouncilWashington D.C., March 02, 2023 (GLOBE NEWSWIRE) -- The International Code Council is revising its rigorous code development process. The changes will take effect in 2024-2026 for the development of the 2027 International Codes (I-Codes) and will move the development process to an integrated and continuous three-year cycle.
In the new timeline, year one will include two Committee Action Hearings for Group A Codes; year two will include two Committee Action Hearings for Group B Codes; and year three will be the joint Public Comment Hearings and Online Governmental Consensus Vote for both Group A and B Codes.
The addition of the second Committee Actions Hearings in year one and two will foster a more in-depth vetting of code change proposals, allowing an opportunity for the committee members to review and evaluate the original proposals and consider the submitted responses. This also provides more opportunity for proponents to build consensus for their code change proposal and ensure the best version of their intended improvement to the existing codes.
Additionally, with combined Public Comment Hearings in the third year, voting members are able to vote on all suggested changes to the next edition of the I-Codes at one time. The updated process also provides more opportunity for proposed new referenced standards to be developed and finalized on a consistent timeline regardless of the group (Group A or B) with which they are associated.
About the International Code Council
The International Code Council is the leading global source of model codes and standards and building safety solutions. Code Council codes, standards and solutions are used to ensure safe, affordable and sustainable communities and buildings worldwide.
Read the court decisionRead the full story...Reprinted courtesy of