Safe Harbors- not just for Sailors anymore (or, why advance planning can prevent claims of defective plans & specs) (law note)
August 17, 2011 —
Melissa Brumback, Construction Law in North CarolinaHave you ever considered a “Safe Harbor Provision” for your Owner-Architect or Owner-Engineer contract? Maybe it is time that you do.
As you are (probably too well) aware, on every construction project there are changes. Some of these are due to the owner’s change of heart, value engineering concerns, contractor failures, and material substitutions. Some may be because of a design error, omission, or drawing conflict. It happens.
A “Safe Harbor Provision” is a provision that establishes an acceptable percentage of increased construction costs (that is, a percentage of the project’s contingency). The idea is that if the construction changes attributable to the designer is within this percentage, no claim will be made by the Owner for design defects.
Read the full story…
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
English v. RKK. . . The Saga Continues
December 16, 2019 —
Christopher G. Hill - Construction Law MusingsRemember back in 2018 when I thought I’d told you the end of the English Construction story regarding its various consultants, etc.? I was wrong. The matter went up on appeal to the 4th Circuit Court of Appeals where the Appeals Court considered the summary judgment granted to the defendant Rummel, Klepper & Kahl (“RKK”) based upon what came down to a contributory negligence reading of the indemnity clause that was allowed to survive in the first district court opinion relating to these ambiguous contracts finding that English was negligent so couldn’t recover. The 4th Circuit also considered the finding that defendant CDM Smith did not breach its contract as a matter of law and that English’s negligence was the cause of the damages.
The Court of Appeals reversed both of the holdings by the Western District of Virginia court, essentially stating that there was enough of a factual dispute to render any summary judgment to be premature.
As to English’s arguments regarding the indemnity scheme in the contracts, the court found that the interpretation was at least ambiguous enough that summary judgment was inappropriate, stating:
While we are not prepared to settle conclusively these interpretation disputes at the summary judgment stage, English’s proffered interpretation is, at the very least. reasonable. Indeed, of the two interpretations, English’s seems to be more closely aligned with the actual language in the contract. The district court thus erred in rejecting English’s interpretation and adopting RK&K’s interpretation as a matter of law.
[A]t bottom, while the district court was authorized to construe unambiguous language as a matter of law, it could not resolve genuine disputes regarding the meaning of ambiguous contractual language against the nonmoving party on summary judgment. We therefore vacate the court’s grant of summary judgment to RK&K and remand for further proceedings.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
See the Stories That Drew the Most Readers to ENR.com in 2023
January 16, 2024 —
C.J. Schexnayder - Engineering News-RecordAs construction's very busy and eventful year nears its close and the sector awaits many more ups and downs in 2024, ENR offers a look back at the Top 20 news stories that most caught readers' attention across a broad market spectrum—from the construction start of the long-awaited $16 billion New York-New Jersey rail tunnel rebuild and winners shortlisted for the first $7 billion in U.S. government funds for developing clean-energy hydrogen hubs to the still unfolding legal battle over Las Vegas Sphere project complexities and why a Texas jury awarded $860 million in a fatal Texas crane collapse verdict.
Reprinted courtesy of
C.J. Schexnayder, Engineering News-Record
Mr. Schexnayder may be contacted at schexnayderc@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
New California Construction Laws for 2020
March 09, 2020 —
Smith CurrieThe California Legislature introduced more than 3,033 bills in the first half of the 2019-2020 session. This article summarizes some of the more important bills affecting contractors in their roles as contractors, effective January 1, 2020, unless otherwise noted. Not addressed here are many other bills that will affect contractors in their roles as businesses, taxpayers, and employers. Each of the summaries is brief, focusing on what is most important to contractors. Because not all aspects of these bills are discussed, each summary’s title is a live link to the full text of the referenced bills for those wanting to explore the details of the new laws.
BIDDING & PREQUALIFICATIONS
Disabled Veteran Preferences Strengthened (AB 230, Brough)
The California Legislature intends that every state procurement authority meet or exceed a DVBE participation goal of a minimum of 3% of total contract value. State departments must require prime contractors to certify at the completion of each contract the amount each DVBE received from the prime contractor, among other information. This new law requires the prime contractor to provide upon request proof of the amount and percentage of work the prime contractor committed to provide to one or more DVBEs under the contract in addition to proof of payment for work done by the DVBE. Additionally, prime contractors must now obtain permission before they may replace a listed DVBE.
County of San Joaquin Now Authorized to Establish Bid Preferences (AB 1533, Eggman)
This new law extends to the County of San Joaquin existing law that authorizes local agencies to establish preferences for small businesses, disabled veteran businesses, and social enterprises in facilitating contract awards.
Read the court decisionRead the full story...Reprinted courtesy of
Smith Currie
Four Key Steps for a Successful Construction Audit Process
May 03, 2021 —
Ronald L. Williams, Fox Rothschild LLP - ConsensusDocsThe implications of the audit provisions contained in construction agreements between owners and contractors owners extend far beyond post-completion bean counting, and can affect multiple aspects of a project, from project administration to relationships with key subcontractors. It is critically important that contractors give audits the attention they deserve by taking the following four steps. First, invest the time to negotiate the audit provisions that ultimately appear in contracts with the owner. Second, ensure that the project team and the owner’s project auditors engage in timely communication during construction. Third, make certain that post-completion audit administration is prompt and complete. And finally, carefully draft adequate “flow-down” provisions with subcontractors and vendors so that they understand and comply with their contractual obligations, as well as the expectations of the contractor and owner. All four aspects are critical, and if not addressed effectively can undermine the profitability of the contract, and contractors’ business relationships with both upstream and downstream parties.
Negotiations
At the outset of contract negotiations, a contractor must completely understand the owner’s audit process expectations. An owner’s understanding of the audit process and its potential pitfalls depends on their own experience, as well as the knowledge of their personnel, including internal audit members and external auditors. Negotiations, which like the audit itself need not be adversarial, can be educational for both the owner and any representatives involved.
Read the court decisionRead the full story...Reprinted courtesy of
Ronald L. Williams, Fox Rothschild LLPMr. Williams may be contacted at
rwilliams@foxrothschild.com
Federal Judge Refuses to Limit Coverage and Moves Forward with Policyholder’s Claims Against Insurer and Broker
December 07, 2020 —
Michael S. Levine & Casey L. Coffey - Hunton Insurance Recovery BlogOn November 10, 2020, a New York federal judge dismissed an insurer’s counterclaims seeking to cap its exposure under a $15 million sublimit and an order estopping the policyholder from pursuing any additional amounts.
In February 2017, Plaintiff Pilkington North America, Inc. (Pilkington), suffered between $60 and $100 million in damage from a tornado that struck its glass manufacturing factory in Illinois. Pilkington sought coverage for its loss under a commercial property and business interruption policy issued by Defendant Mitsui Sumitomo Insurance Company (MSI). Pilkington also claimed its insurance broker, Aon Risk Services Central, Inc. (Aon), is liable for faulty advice provided while brokering the policy. Aon’s negligence allegedly gave way to MSI’s fraudulent revision of the insurance policy, which caused the losses from the tornado to not be fully compensable.
Pilkington’s fraud and faulty brokering claims stem from MSI’s revision of an endorsement contained in the policy. The revision changed the wording of a windstorm sublimit. Allegedly, Aon was informed by MSI of the changes and failed to inform Pilkington that the revision would substantially reduce coverage for windstorms, including tornados.
Read the court decisionRead the full story...Reprinted courtesy of
Michael S. Levine, Hunton Andrews KurthMr. Levine may be contacted at
mlevine@HuntonAK.com
Seven Key Issues for Construction Professionals to Consider When Dealing With COVID-19
April 13, 2020 —
Jason Adams - Linked InBy now every construction professional has been inundated with articles regarding the impacts of COVID-19 on the construction industry. The sheer volume of information is overwhelming and changes by the hour. This article is intended to summarize key issues affecting construction professionals and serve as a general road map for navigating the crisis.
1. Determine Project Status
The first consideration is whether the construction projects at issue are allowed to proceed given “shelter in place” and related orders.
Generally speaking, Governor Newsom has deemed construction to be essential and, therefore, exempt from California’s “Safer at Home” order. There is some debate as to whether the governor’s order takes priority over contradictory local (City and County) orders. For example, some Northern California counties and the City of Berkeley have issued orders expressly providing that their local orders legally supersede the State order because the local orders are more restrictive.
If a local ordinance, public entity representative, or the project owner orders the project to shut down, the parties will need to make a fact specific determination regarding how to proceed at that time.
If the project proceeds, employee safety is paramount. In the City of Los Angeles employers are required to develop a “comprehensive COVID-19 exposure control plan” that includes a laundry list of safety requirements. Regardless of the jurisdiction, the parties must err on the side of caution and comply with social distancing (six feet), refrain from holding meetings, and close the project to the public. Anyone who can work remotely should be encouraged to do so.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Adams, Gibbs GidenMr. Adams may be contacted at
jadams@gibbsgiden.com
The Business of Engineering: An Interview with Matthew Loos
July 15, 2019 —
Aarni Heiskanen - AEC BusinessMatthew Loos is an experienced project manager in the civil engineering industry. He works as a project engineer at Jones|Carter in Fort Worth, Texas. In this interview, we discuss Matt’s new book, The Business of Engineering.
It is not very common that an engineer writes a non-technical book. What inspired you to do so?
Have you ever gotten an idea stuck in your head that you just couldn’t let go of? A time when you couldn’t go to sleep because the idea was consistently begging for your attention?
That’s what happened to me. The idea for this book hits me right before bed, as most good ideas do. I couldn’t go to sleep after the idea struck me. I spent half of the night writing the chapters of this book in my mind. I had been thinking about the idea of engineering and how it relates to other career fields, even the non-technical ones. I was disenchanted with the trifling number of classes I took that prepared me for the business world. These were the initial thoughts that eventually led me down the road into thinking about engineering as a profession going forward.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at