Evacuations in Santa Barbara County as more Mudslides are Predicted
March 14, 2018 —
Dave Suggs – CDJ StaffAlene Tchekmedyian’s LA times article “Storm triggers evacuations in Santa Barbara County: 'Don't be fooled into thinking that this can’t happen again',” warns of the deadly potential of mudslides following the devastation that occurred in January that caused 21 fatalities and damaged homes in Montecito.
Debris flow could be triggered by rainfall rates predicted to exceed half and inch per hour. In some areas as much as seven-tenths of an inch of rain per hour are possible because of a chance of thunderstorms.
Mandatory evacuations began Monday to protect residents from the fast-moving storm that is predicted to be worse than January’s. Santa Barbara county officials asked that people help spread the word of the evacuation to everyone in their community. They also created an interactive map to help residents determine their risk level.
Matilija Canyon and North Fork in Ventura County are under voluntary evacuation orders. Areas at the highest risk include Thomas, Sherpa, and Whittier burn areas. Residents can find shelter at the Goleta Valley Community Center at 5679 Hollister Avenue.
Read the court decisionRead the full story...Reprinted courtesy of
Why A Jury Found That Contractor 'Retaliated' Against Undocumented Craft Worker
August 22, 2022 —
Richard Korman - Engineering News-RecordOn May 10, 2017, a Boston wall taper who had broken his leg in a fall from a ladder during work six weeks earlier took his two-year-old son to an office of a West Bridgewater, Mass.-based contractor, on the invitation of the CEO who asked him to come and gave the worker $500 to help him get by while recovering.
Reprinted courtesy of
Richard Korman, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Insurer Must Defend Additional Insured Though Its Insured is a Non-Party
November 18, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe plaintiff insurer's motion for partial summary judgment seeking an order that defendant insurer was obligated to defend a non-party as an additional insured was granted. Am Empire Surplus Lines Ins. Co. v. Burlington Ins. Co., 2019 N. Y. Misc. LEXIS 4145 (N. Y. Sup. Ct. July 25, 2019).
Quality Building Construction, LLC was the contractor hired to work on exterior facade of a building owned by Central Park West Corporation. The underlying complaint alleged that Quality caused plastic spacers and pedestals used for the penthouse terrace to fall down the roof drain riser. A clog and rainwater backup resulted in water damage to apartment 8A. The resulting damage was allegedly due to the clogged roof drain riser.
Quality subcontracted the work to Mega State, Inc. The subcontract required Mega to indemnify and hold Quality harmless against claims in connection with Mega's work, as well as name Quality as an additional insured on a primary, non-contributory bases under Mega's CGL policy. Burlington issued a policy to Mega naming Quality as an additional insured. American Empire issued a CGL policy to Quality.
Quality was sued in the underlying action, but Mega was not. American Empire tendered a demand for coverage to Mega and Burlington, relying on the agreement between Quality and Mega. Burlington responded that Mega was not liable for the alleged damages. American Empire sued Burlington. Subsequently, Burlington accepted the tender to defend Quality in the underlying action, and reserved rights as to whether Burlington's policy was primary and on the question of indemnification. American Empire agreed to withdraw its suit if Burlington would modify its reservation of rights. Burlington refused.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Construction Managers, Are You Exposing Yourselves to Labor Law Liability?
February 22, 2021 —
Timothy P. Welch - Hurwitz & Fine, P.C.When dealing with construction site accidents, who a party is matters. Under Labor Law sections 200, 240(1) and 241(6) owners, contractors,
and their agents have a non-delegable duty to provide reasonable and adequate protection to workers from risks inherent at work sites, with a specific emphasis placed on elevation-related hazards. Given the near strict liability nature of Labor Law section 240(1), it is critical to identify whether a party is a proper Labor Law defendant from the get-go.
While identifying the owner (and usually the contractor) may be relatively straightforward, identifying “their agents” has proven to be a more complex undertaking. It should be noted that the requirements set forth in the Labor Law are non-delegable from the standpoint of the owner or contractor, however, the duties themselves can be assigned to “agents” of an owner or “agents” of a contractor. When such an assignment occurs, the same non-delegable duty held by the owner or contractor is imposed on the agents as well. Moreover, “once an entity becomes an agent under the Labor Law it cannot escape liability to an injured plaintiff by delegating the work to another entity.[1]”
An entity that often skirts the line between being an agent and not, is the Construction Manager. Traditionally, the Construction Manager has been found to be outside the purview of the Labor Law when its scope of work is narrowly focused on scheduling and general coordination of the construction process. However, when a Construction Manager’s scope expands, so does its risk that it may, in fact, become a proper Labor Law defendant.
Read the court decisionRead the full story...Reprinted courtesy of
Timothy P. Welch, Hurwitz & Fine, P.C.Mr. Welch may be contacted at
tpw@hurwitzfine.com
Payment Bond Claim Notice Requires More than Mailing
June 18, 2019 —
Christopher G. Hill - Construction Law MusingsIt’s been a while since I posted something new relating to Virginia’s “Little Miller Act” and its various notice requirements for a subcontractor to make a payment bond claim.
I have posted on the basics of a Virginia payment bond claim previously here at Musings. One of these basics is the 90 day notice requirement for suppliers or second tier subcontractors with no direct contractual relationship to the general contractor. A recent case from the Norfolk, Virginia Circuit Court examined when notice is “given” under the Little Miller Act.
In R T Atkinson Building Corp v Archer Western Construction, LLC the Court looked at the question of whether mailing of the notice of claim is enough to constitute notice being “given” in a manner that would satisfy the statutory requirements. In that case, the supplier mailed the notice within the 90 day window, but the defendant argued on summary judgment that it did not receive the notice until 2 days after the 90 day window had closed. In support of this contention, the defendant provided tracking information showing delivery by the USPS on the non-compliant date.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Recent Developments with California’s Right to Repair Act
June 11, 2014 —
Beverley BevenFlorez-CDJ STAFFIn Lexology, Amy Kuo Alexander of Gordon Rees Scully Mansukhani, LLP analyzed recent decisions involving California’s Right to Repair Act, SB 800. According to Alexander, “SB 800, applies to all new residential construction sold after January 1, 2003” and “[i]t establishes a process to resolve certain construction defect claims prior to the filing of any lawsuit by a homeowner of new residential construction.”
Alexander’s three main discussion points include “SB 800 is Not the Exclusive Remedy,” “Notice Requirements to Builder Under SB 800,” and “Parties Can Opt Out of SB 800 to Adopt Their Own Prelitigation Procedure So Long as the Terms Are Not Unconscionable.”
Read the court decisionRead the full story...Reprinted courtesy of
DoD Will Require New Cybersecurity Standards in 2020: Could Other Agencies Be Next?
September 09, 2019 —
Alexander Gorelik - Smith CurrieThe Department of Defense (DoD) has announced a new five-tier standard for cybersecurity certification, which it calls the Cybersecurity Maturity Model Certification, or “CMMC”. Taking an unusual approach to informing the industry, the DoD has provided only limited information about the new standard through its website and a “road tour” led by the newly-appointed head of the DoD’s Chief Information Security Office (CISO), Ms. Katie Arrington.
During her recent presentation at the National Institute of Standards and Technology’s (NIST’s) Information Security and Privacy Advisory Board (ISPAB) meeting, on August 8, 2019, Ms. Arrington revealed several new details about the requirements. Outlined below are the most significant facts from that presentation and the DoD’s website:
All companies doing business with DoD (and all tiers of subcontractors) will need to obtain CMMC certifications.
DoD will require the new certifications from all contractors (including suppliers and subcontractors) that are performing under a DoD contract. Even contractors that do not process or handle Controlled Unclassified Information (CUI) must obtain CMMCs.
Read the court decisionRead the full story...Reprinted courtesy of
Alexander Gorelik, Smith CurrieMr. Gorelik may be contacted at
agorelik@smithcurrie.com
Options When there is a Construction Lien on Your Property
June 02, 2016 —
David Adelstein – Florida Construction Legal UpdatesThere is a construction lien on my property. What are my best options? I hear this question quite a bit…so here it goes…
(1) Do nothing. That’s right – do nothing. If you are not looking to sell your house or refinance in the next year or so, you can do nothing and see whether the lienor files a construction lien foreclosure lawsuit. The lienor has one year from the recording of the lien to file the lawsuit.
(2) Record a
Notice of Contest of Lien. The
Notice of Contest of Lien shortens the lienor’s statue of limitations to foreclose on the lien from one year to 60 days. If the lienor fails to foreclose on the lien within 60 days, the lien is extinguished by operation of law. This is the route I tend to prefer. If the lienor is going to file a lien foreclosure lawsuit, I tend to think it is better forcing the issue on the front end as opposed to waiting a year. But every situation is different.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at