Toolbox Talk Series Recap – Considerations for Optimizing Dispute Resolution Clauses
June 05, 2023 —
Michael Filbin - The Dispute ResolverIn the April 27, 2023 edition of Division 1's Toolbox Talk Series moderated by Manuel del Valle, Sergio Andre Laclau (Partner at Mello Torres) and Liza Akins (Senior Assistant GC and Division Counsel at ARCO Design/Build) offered the following strategies for drafting effective ADR clauses in construction contracts:
- Define the ADR process for various types of disputes.
Not all disputes on a construction project are the same, and the parties can tailor the ADR process to different situations. For example, the parties could choose to arbitrate complex disputes and resolve minor claims through mediation. Differentiating the ADR process between complex and minor disputes can save parties time and money.
While Liza prefers arbitration for complex claims because you can get a quick and final decision from an arbitrator experienced with construction disputes, she noted that arbitration costs can add up quickly. Therefore, if the dollar amount in dispute is relatively small, arbitration may not make sense financially. Mediation tends to be a comparatively cheaper and faster option.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Filbin, Cozen O'ConnorMr. Filbin may be contacted at
mfilbin@cozen.com
Defining Constructive Acceleration
March 22, 2021 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to the definition of “constructive acceleration,” the case of Fraser Const. Co. v. U.S., 384 F.3d 1354 (Fed.Cir. 2004) is a cited case and contains an instructive definition, quoted below, for proving a constructive acceleration claim.
In a nutshell, a constructive acceleration claim is when the contractor incurs added costs for trying to complete the contract on time when it should be provided extensions of time to perform based on excusable delay (i.e., delay not caused by the contractor). These added costs could be bringing in additional supervision to manage the work, adding manpower to perform the work, working overtime, working weekends, adding more shift work, stacking trades, etc. However, just because a contractor claims they have been constructively accelerated does not make it so. The contractor has to actually ask for an extension of time based on an excusable delay and the owner either denied the extension or unreasonably sat on the request for an extension of time; thus, the contractor incurred significant costs to accelerate in order to finish the project on time because it was deprived of a requested time extension for excusable delay.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Fine Art Losses – “Canvas” the Subrogation Landscape
February 26, 2024 —
William L. Doerler - The Subrogation StrategistIf a fire or flood destroys a high-net-worth client’s fine art collection, an insurer who pays out a claim related to the loss has an incentive to pursue subrogation. This article explores some of the issues an insurer should “canvas” before pursuing subrogation for these types of claims.
Damage to fine art can occur in a number of ways. For instance, fine art may be damaged in a natural disaster – such as a flood or a wildfire. Artwork may also be accidentally damaged because of a transportation-related incident physically damaging the art. In addition, artwork may suffer fire or smoke damage from a fire within a building. Another possibility is that the artwork suffers damage because of renovations either to the insured’s home or a neighboring property. For example, a renovation contractor may damage artwork due to vibrations or leaking water. A construction worker, moreover, may turn with a tool in his hand, or trip and fall, damaging the artwork.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Doerler, White and Williams LLPMr. Doerler may be contacted at
doerlerw@whiteandwilliams.com
General Liability Alert: ADA Requirements Pertaining to Wall Space Adjacent to Interior Doors Clarified
February 26, 2015 —
Lawrence S. Zucker II and Kristian B. Moriarty – Haight Brown & Bonesteel LLPIn Kohler v. Bed Bath & Beyond (No. 12-56727, filed February 19, 2015) the United States Court of Appeals for the Ninth Circuit affirmed a grant of summary judgment in favor of a department store related to the necessary moving clearance for an interior restroom door pursuant to the Americans With Disabilities Act ("ADA").
Plaintiff, Chris Kohler, is paraplegic and requires the use of a wheelchair to move in public. On two separate days in May 2011, Kohler used the restroom inside the Bed Bath & Beyond store in Riverside, California. Of relevance to the appeal, Kohler contends there was less than ten inches of strike-side wall space on the pull side of Bed Bath & Beyond’s restroom door which allegedly made it difficult for Mr. Kohler to pull open the restroom door by pushing off the strike-side wall with one hand while pulling the door handle with the other. He also contends there was less than three inches of strike-side wall or floor space on the push side of the door, making it difficult for Kohler to open the door from the push side. The door at issue did not have a latch which would stop the door from freely swinging on a hinge.
Reprinted courtesy of
Lawrence S. Zucker II, Haight Brown & Bonesteel LLP and
Kristian B. Moriarty, Haight Brown & Bonesteel LLP
Mr. Zucker may be contacted at lzucker@hbblaw.com
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Are You Taking Full Advantage of Available Reimbursements for Assisting Injured Workers?
January 08, 2019 —
Jonathan Schirmer - Ahlers Cressman & Sleight PLLCWorkplace injuries are an increasingly expensive cost of doing business. While every business does their best to avoid these injuries, even the most prepared employers must deal with them on occasion. The costs associated with these injuries—increased worker’s compensation premiums, decreased productivity, hiring temporary employees, and the loss of experienced workers—can be mitigated by shrewd employers taking full advantage of available assistance programs.
Read the court decisionRead the full story...Reprinted courtesy of
Jonathan Schirmer, Ahlers Cressman & Sleight PLLCMr. Schirmer may be contacted at
jonathan.schirmer@acslawyers.com
A Court-Side Seat: Guam’s CERCLA Claim Allowed, a “Roundup” Verdict Upheld, and Judicial Process Privilege Lost
June 14, 2021 —
Anthony B. Cavender - Gravel2GavelThis is a brief account of some of the important environmental and administrative law cases recently decided.
THE U.S. SUPREME COURT
BP PLC, et al. v Mayor and City of Baltimore
The issue the court confronted was a procedural matter: Can the defendant energy companies use the federal removal statutes (see 28 USC Section 1442) to remove a state law climate change lawsuit to federal court? Here, a group of energy companies were sued by the mayor and city council of Baltimore in state court, where they alleged that the defendants had concealed the adverse environmental effects of the fossil fuel products they promoted and sold in Baltimore City. Several similar lawsuits have been filed in many state courts, where typically it is alleged that the defendants can be sued on various common law theories. Rather than defend these cases in state court, the defendants have sought to remove these cases to federal court because climate change liability appears to be an issue that should be settled at the federal level. These efforts have been unsuccessful, with most federal trial and appellate courts holding that the reasons cited for removal (oftentimes the federal officer removal statute) have not been persuasive. In this case, both the Maryland federal district court and the U.S. Court of Appeals held they had no jurisdiction to authorize removal, and thus returned the case to the state court. Noting that the U.S. Court of Appeals for the Seventh Circuit ruled that a removal action could be countenanced under Section 1442, thus creating a circuit split, the Supreme Court held that a straightforward reading of the removal statute empowers the reviewing court to examine all theories for removal that a district court has rejected. Consequently, the Court remanded the case to the Fourth Circuit where it can decide, “in the first instance,” whether there actually exist grounds to remove this case to federal court.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Construction Contract Terms Matter. Be Careful When You Draft Them.
February 01, 2022 —
Christopher G. Hill - Construction Law MusingsIn a prior post, I discussed the case of Fluor Fed. Sols., LLC v. Bae Sys. Ordinance Sys in the context of the interplay between fraud, contract, and statutes of limitation. Some cases just keep on giving. This time the case illustrates the need for careful drafting of those
pesky, and highly important, clauses in your construction documents.
In the
current iteration of this ongoing saga, the Court considered the contractual aspects of the matter. As a reminder, the facts are as follows: In May 2011, the United States Army (“Army) awarded BAE Systems Ordnance Systems, Inc. (“BAE”) a contract to design and construct a natural gas-fired combined heating and power plant for the Radford Army Ammunition Plant (“RAAP”). On October 7, 2015, BAE issued a request for a proposal from Fluor Federal Solutions, LLC (“Fluor”) to design and build a temporary boiler facility at a specific location on the RAAP property. On October 13, 2015, the Army modified the prime contract to change the location of the boiler facility. On December 10, 2015, the Army modified the prime contract to require BAE to design and construct a permanent boiler facility. On December 30, 2015, Fluor and BAE executed a fixed-price subcontract for Fluor to design and construct the temporary boiler. Throughout 2016, BAE issued several modifications to Fluor’s subcontract to reflect the modifications BAE received from the Army on the prime contract. On March 23, 2016, BAE directed Fluor to build a permanent – rather than temporary – boiler facility. On March 28, 2016, Fluor began construction of the permanent facility and began negotiations with BAE about the cost of the permanent facility. On September 1, 2016, the parties reached an agreement on the cost for the design of the permanent facility, but not on the cost to construct the permanent facility. On November 29, 2016, the parties executed a modification to the subcontract, officially replacing the requirement to construct a temporary facility with a requirement to construct a permanent facility and agreeing to “negotiate and definitize the price to construct by December 15, 2016.” The parties were unable to reach an agreement on the construction price.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Toll Brothers Surges on May Gain in Deposits for New Homes
June 01, 2020 —
Prashant Gopal - BloombergToll Brothers Inc. shares surged after the company posted profit that beat estimates and said deposits on new homes were up in recent weeks, a potential sign of optimism for the luxury housing market.
The homebuilder, which focuses on higher-end customers, has struggled during the pandemic. It reported orders for the second quarter that missed estimates and said the key metric had plunged starting March 16, when much of the economy shut down.
But investors shrugged off those results, focusing instead on a 13% year-over-year gain this month in deposits, which the company called a “leading indicator of current market demand.”
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, Bloomberg